| 1 | 9 Mtr. Long Pole (ST-410 SP33) |
| 2 | 8 Mtr. Long Pole (ST-410 SP15) |
| 3 | ACSR 0.05 Conductor (50 mm² ACSR Conductor) |
| 4 | G I Channel/ Angle/ Flat for cross, braces of sizes including clamps & Nut Bolts |
| 5 | 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 6 | 11KV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type |
| 7 | 11KV Gapless Surge Arrestor,9 kV ,10 kA ,LA with polymer housing, Stn. Type |
| 8 | LT Fuse Set |
| 9 | 185 mm2 Single Phase Cable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 10 | 300 mm2 Single Phase Cable,1.1K V Grade, PVC Insulated Stranded Conductor FRLS type |
| 11 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 12 | Dismantling and Re-erection of Existing Transformer (Complete Job) |
| 13 | Mucki clamps/LT Shackles with insulators |
| 14 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 3202 |
| 15 | 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with fitting |
| 16 | Earthing Complete by GI Pipe 40 mm or GI Rod 20mm 2.5 mtr long through GI Strip. |
| 17 | Painting of Poles Red Oxide |
| 18 | Painting of Poles Aluminium Paint |
| 19 | Cement bottoming of poles 1:2:4 mix as per REC standards 0.48cum /pole |
| 20 | Cement bottoming of poles 1:2:4 mix as per REC standards 0.44cum /pole |
| 21 | Danger Plates with Clamps for 9 meter HT Poles |
| 22 | Dismantling of old red material, loading, transportation and deposition at Divisional Stores (Complete Job) |
| 23 | \\"Providing Geo-tagged Photographs (8'' × 6'') on photo paper along with soft copies of the Sub-Station before, during, and after execution of the work, complete. |
| 24 | Providing and Installation of Wedge Connectors/ PG Clamps |
| 25 | Providing and Installation of Sundry items like Aluminium lugs, jumpers, Binding Tape Please Enable Macros to View BoQ information |