| 1 | Dismantling of old V.R.B. and proper disposal including all cost of materials,T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 2 | Dismantling of old & damage Reinforced cement concrete slab and its proper disposal including all cost of materials, T&P and labours for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 3 | Earth work in excavation of foundation including digging and refilling the trenches with all lead & lift including cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 4 | Laying C.C. 1:2:4 M15 in foundation with cement, sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (20 mm to 40 mm.) including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 5 | Laying R.C.C. work in 1:1:2 (M25) sonbhadra coarse sand of FM. Not less then 2.50 and dala grit (10mm to 20mm.) for raft,pedestal,abutment,slab, pier cap,wing wall & parapet including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 6 | Providing and laying Steel as Reinforcement (TATA,SAIL&JINDAL) including cost of steel carriage, bending, cutting, placing in position and binding with steel binding wire etc. including cost of all materials, labour and T&P with all leads and lift for proper completion of work |
| 7 | Centering and shuttering for Plain Cement Concrete work in foundation including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. |
| 8 | Centering and shuttering for R.C.C. work including cost of all materials, labour and T&P etc with all leads and lift/down for proper completion of work and as directed by Engineer-in-Charge as per I.D. specifications. |
| 9 | Supply and laying of joint filler board on abutment and wing wall and on slab joint including cost of all material labour T&P required for proper completion of work as directed by Engineer-in-charge and as per I.D. specifications. |
| 10 | Supply & Laying one layer of tarfelt / Membrane sheet below for slab including cost of all material labour and T & P etc. with proper completion of work as directed by Engineer-in-charge and as per I.D. specifications. |
| 11 | Laying dismantled Brick on approach road including cost of all material (but excluding cost of dismantled brick ballast) & including cost of labour and T&P with proper completion of work as directed by Engineer-in-charge and as per I.D. specifications |
| 12 | Earth work in filling ( for making diversion , filling of approach road )with all lead & lift including cost of labour and T&P with proper completion of work as directed by Engineer-in-charge and as per I.D. specifications. |
| 13 | Brick on edge soling with 1st class brick( on approach road of culvert) including preparation of sub-grade to prescribed camber, filling joint with Local sand including cost of material, labour and T&P etc for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 14 | Boring with 100 mm diameter casing pipe including lowering & extraction of assembly,loading,unloading & carriage including cost of all materials, labour and T&P etc. required for complete work as directed by Engineer-in-Charge as per I.D. specifications. |
| 15 | Running of 10 H.P. generator set pump for dewatering including arrangement of Pump suction and delivery pipes and other accessories at site including cost of all materials, labour and T&P etc.for complete work as directed by Engineer-in-Charge as per I.D. specifications. |
| 16 | Supplying and Fixing PVC Pipe of 75 mm dia including cost of pipe, other material, labour, T&P etc. required for complete work as directed by Engineer-in-Charge and as per drawing and I.D. specifications. |
| 17 | Earth work in removing of diversion including cost of labour and T&P with proper completion of work approved by Engineer-in-charge as per drawing and I.D. specification. |
| 18 | Finishing wall with acrylic smooth exterior paint(Asian apex,berger & branded company) of required shade including cost of all materials, labour and T&P for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. |
| 19 | Painting/Printing letter on culvert height including cost of all materials, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge and as per I.D. specifications. Please Enable Macros to View BoQ information |