| 1 | Item Rate BoQ BoQ_Ver3.0 Item Rate Normal INR Only INR Select, Excess (+), Less (-) Less (-) Tender Inviting Authority: Superintending Engineer, EDC, Gauriganj Name of Work: 11 KV Devkali Feeder bifuercation at 33/11 KV Sub-Station-Jagdishpur and other line related work under EDD-Jagdishpur, Distt. Amethi. (Business Plan Year 2026-27) Tender No: 29/E.D.C.(G.)/2026-27 Name of the Bidder/ Bidding Firm / Company : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Sl.No. Work Description Item Code / Make Quantity Unit Estimated Rate inRs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category PERIOD IN month TOTAL AMOUNT Without Taxes inRs. P TOTAL AMOUNT Without Taxes TOTAL AMOUNT In Words |
| 2 | Loading, carriage of following items from Store Centre, Gauriganj/Sultanpur to dump store including unloading and proper stacking (distance 0-70 km.) (Sl. No. 2 - 17) |
| 3 | PCC/ ST Pole |
| 4 | ACSR RABBIT CONDUCTOR |
| 5 | ACSR Weasel Conductor |
| 6 | X-ARM 11 KV |
| 7 | Pin insulator 11kv with pin |
| 8 | Disk insulator 11kv with fitting |
| 9 | T-of Channel |
| 10 | Earthing complete |
| 11 | Stay Set complet |
| 12 | Top channel |
| 13 | 11 KV Bracing Angle |
| 14 | DROPPER CHANNEL |
| 15 | 11 KV XLPE CABLE 3*120 SQ MM |
| 16 | 11 KV XLPE CABLE JOINTING KIT 3*120 SQ MM O/D |
| 17 | 11 KV VCB FOR O/G CTR 200/100/A 350 MVA |
| 18 | Other Line Material |
| 19 | Dragging of pole from JE Dump Store to site |
| 20 | Digging of pits up to the depth of 1650/2200 mm. as per site requirement. Fabrication & erection of single pole support on PCC/ST pole support including digging of pit & fixing of all accessories and clamps as per RESSPO norms . |
| 21 | Grouting of STP/PCC pole in ratio 1:4:8 with cement stone ballast, coarse sand and plinthing 300 mm above ground level as well as muffing of plinth. |
| 22 | Stringing and sagging of ACSR Rabbit Conductor including nuzzling binding and jumpering (weasal conductor will be provided by the department) |
| 23 | Stringing and sagging of ACSR weasel Conductor including nuzzling binding and jumpering (weasal conductor will be provided by the department) |
| 24 | Concreting & nuzzling of stay complete including fixing of necessary clamps with the help of nuts & bolts other accessorise required for completing the work as well as its grouting by civil material viz. Sand, stone ballast and cement. The contractor will provide all civil material as well as stay insulator |
| 25 | Ordinary earthing by 11 KV MS earth rod 2500 mm long as per RESPO norm. |
| 26 | Installation of 11 KV VCB FOR O/G CTR 200/100/A 350 MVA |
| 27 | Laying of XLPE Cable 3x120 sq.mm. By MM Manually/Drill Method |
| 28 | Installation of cable jointing kit 3x120 sq.mm. O/D |
| 29 | Testing of XLPE Cable all size. |
| 30 | Hosting of Cable all size. |
| 31 | Providing & Fixing of various type materials. All materials shall be supplied by the contractor. |
| 32 | X-arm holding clamp |
| 33 | F- Barket with nut &bolt |
| 34 | Gaurding/Top/T-Off/Clamp |
| 35 | Handover of received back materials to store centre Gauriganj. |
| 36 | All matching materials which is nessceary for completion of electric line will be provided by free of cost including rout marker etc. Total in Figures 0.0 0.0 INR Zero Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |