| 1 | Repair Works |
| 2 | OD194932/2024-2025:Removing damaged concrete:Loose and delaminated concrete shall be identified and marked before proceeding with the removal. The loose cover concrete including the loose damaged concrete shall be removed upto beyond the corroded bars to a minimum depth of 10 mm behind the reinforcement. Only affected concrete shall be removed and conducting proper investigation, (Good & sound concrete should not be chipped / damaged) by chipping / hacking with chisel and hammer or by mechanical means like light weight chisel hammer, pneumatic chippers, making saw cut at periphery to avoid feather edge for all height and removal and disposal of debris at designated location including all material, labour, tools, temporary supports for structures, electricity, plant and machineries etc. complete as directed by Engineer-in-charge and/or Consultant. Depth of chipping may vary from 20 to 100 mm. |
| 3 | OD353191/2025-2026:Engaging Man Mazdoor for cleaning the deposited debris near pier and abutment ,cleaning the premises of bridge etc. |
| 4 | OD194924/2024-2025:Rust remover/Rust Convertor:Cleaning of rust / scales / corrosion from reinforcement bars should be carried out using acid based rust remover, Reebakleens RR of Fosroc or equivalent, or using alkali based rust converters such as Feovert of Krishna Conchem. The material is to be applied to the rusted metal bar, using brush and leaving it to dry for 30 Min. & washing surface with fresh water as required to exposed reinforcement bar at all heights, including all material, labour, tools, temporary supports for structures, electricity, plant and machineries complete as per detail specification and as directed by Engineer-in-charge and/or Consultant. The concrete surface area containing the cleaned rebars shall be measured for payment. |
| 5 | OD194930/2024-2025:Anti Corrosive treatment to Steel:Providing & applying inhibition coats/system to exposed reinforcement bars & also new bars, after cleaning & removing scales and rust completely as specified in 1.4, Two component inhibitor Nitozinc Primer std. of Fosroc or MasterEmaco P130 of BASF or equivalent having specific gravity of 1.75 and solid content 57(+/-3) Adhesive bond strength > 1.5 N/mm2, 40 microns DFT per coat as approved by Engineer-in-charge and/or Consultant shall be used as per manufacturer?s specification in two coats at all heights, including all material, labour, tools, temporary supports for structures, electricity, plant and machineries, necessary surface preparation and necessary protection after and during work. The concrete surface area contianing the rebars where the treatment is carried out shall be considered for measurement. |
| 6 | OD194933/2024-2025:Polymer Modified Mortar (Pre-Packed):Providing and Applying single component, high strength, fibre reinforced, thixotropic cementitious patch repair mortar that achieves compressive strength minimum of 15 MPa at 1 day and 45 MPa at 28 days and capable of applying upto 50mm thick in single layer such as Renderoc SP40 of Fosroc or Master Emaco S 348 of BASF or equivalent, to the prepared concrete area for thickness up to 50mm, after applying epoxy resin based bonding coat as per manufacturer?s specification, before the bonding agent becomes tack free, initially by hand and finally finishing the same with trowel carefully compacting the same around the rebar and finishing to bring it in line with existing concrete surface on the columns, slabs, beam etc. at all heights, where the thickness of application is less than 50 mm in patches as per specification . Item rate is inclusive of all material including the bond coat, labour, tools, temporary supports for structures, electricity, plant and machineries, curing etc. complete and as directed by Engineer-in-charge and/or consultant.(Payment to be made in Sq.M for thickness upto 50mm of PMM for patch area repaired) |
| 7 | OD194935/2024-2025:Microconcrete Reinstatement for thickness more than 50mm for RCC members:-Providing and laying of special repair material micro-concrete for reinstatement of members having thickness of repair more than 50mm and jacketing, using Single component, high strength, high flow cementitious micro-concrete having compressive strength minimum of M40 at 28 days such as MasterEmaco 346 or Renderoc RGL / RGS of Fosroc or equivalent, blended with washed saturated surface-dry (SSD), graded, low absorption, high density, aggregates of size 3mm to 10mm at 50% by weight of micro concrete (if thickness is 100mm or more) and water as per data sheet and pouring into the shuttering if required than use birds beak type form work using suitable arrangement or if required using pumping device for uniform flow of Microconcrete. The side shuttering can be removed after Minimum of 24 hours, preferably 3 days and the bottom shuttering after 7 days ensuring proper bond between the micro concrete and existing concrete substrate at all heights, including all material, labour, tools, temporary supports for structures, electricity, plant and machineries, curing etc. complete as directed by Engineer-in-charge and/or consultant. (Payment shall be made in Sq.M for thickness upto 100mm of Microconcrete of area repaired, ) including shuttering work (Only steel reinforcement shall be paid in other relevant items) |
| 8 | OD195312/2024-2025:Replacement of rusted portion of GI drainage spout with PVC pipes 4 kgf/cm2( 60 mm to 100mm outer dia as per site condition)of length 50cm . The item includes removal of rusted portion of drainage spout, fixing the PVC pipe over uncorroded length of existing drainage spout by suitable method of gluing/bolting/connectors including all material labour etc. as per the direction of Engineering in charge. |
| 9 | OD350619/2025-2026:Providing and fixing hanging platform for inspection of repair works using steel hollow sections and maintaining it in a serviceable condition for the required duration as approved and removing it there after. The scaffolding system shall be equipped with accessibility provisions with ladders and the same shall be stiffened with bracings, runners, connection with the bridge deck etc. at required location with essential safety features for the workmen etc. complete as per directions and approval of Engineer- in Charge. The horizontal area of the scaffolding shall be measured for payment purpose. The payment will be made once irrespective of duration of scaffolding. |
| 10 | OD350611/2025-2026:Providing and applying elastic, elastomeric membrane forming system with anticarbonation and breathing properties. The system should be based on solvent free acrylic polymers with selected mineral fillers and should be ultra-violet resistant, crack bridging type, carbonation resistant, breathable, enviornment friendly, water proofing coating. For anticarbonation, equivalent air layer thickness denoted as R or SD CO2 grater than 50 m and for breathability equivalent air layer thickness denoted as SD H2O shall be less than 4 m for vapour transmitting barrier. The system consists of one coat primer @ 75- 100 g/m2. The consumption of main polymer coating to give film thickness of 200-225 microns (Solid contents- 70%+ -3%) should be approximately. 400-450 g/m2 per two coats depending upon the method of application (either by roller or brush) and surface smoothness of the concrete. The total dry film thickness of the coating system should be minimum 200 microns for the above system. Polymer coating should be in suitable approved shades, including cost of materials, cleaning, chipping and removing the dirt particles of the concrete slab with wire brush and water,labour charges for filling the bug holes, cracks, joints etc with one component polymer modified fine repair and cosmetic mortar, labour for applying the above coating etc. complete as per IRC SP:80 Clause 6.5.1 and Clause 2808 in the Specifications Book for Roads & Bridges published by the Ministry during April 2013. (excluding scaffolding) |
| 11 | Repair Works |
| 12 | 2.3.1.A:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of light jungle - By Manual Means |
| 13 | 2.1.1:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. Girth from 300 mm to 600 mm |
| 14 | 2.1.2:Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. Girth from 600 mm to 900 mm |
| 15 | 3.11:Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305. |
| 16 | OD346290/2025-2026:Removal of old expansion joint including the breaking of concrete, cutting of lugs and shifting of broken material etc. |
| 17 | 2.5.2.A:Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately Bituminous course - By Mechanical Means |
| 18 | OD346536/2025-2026:Providing expansion joint with Aluminium sheet 16 gauge thick 7.5m long and 50cm wide and bending sheet to required shape with slot of size 10cm*3cm @30cm c/c placing in position etc complete including the cost and conveyanace of all materials all charges for filling the joint with a mixture of saw dust and bitumen emulsion , including all labour charges as per the direction of departmental officers at site. |
| 19 | 2.4.2.B:Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres Prestressed / reinforced cement concrete grade M-20 & above - By Mechanical Means |
| 20 | OD346210/2025-2026:Anchoring mainsteel and stirrups:Drilling holes of min 4mm larger than new rebar diameter into existing concrete substrate foranchoring of new rebar and depth of Min. 10 times the diameter of rebar and fixing with anchorresin grout Lokfix E (35/55/75) series or Lokfix P or Emfix or chemical anchor material orMasterflow 935 of BASF or equivalent as per NF P 18-831 and NF P 18-836 includingcleaning, cutting, fabricating, chemicals, material, labour, tools, temporary supports forstructures, electricity, plant and machineries etc. complete as directed by Engineer-in-chargeand/or consultant for all heights. As per approved data of Rehabilation of kalluthan kadavu bridge) |
| 21 | 12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications |
| 22 | 12.8.G.1.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. RCC Grade M30 - Using Concrete Mixer |
| 23 | 12.8.B:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications PCC Grade M20 (Without formwork) |
| 24 | 8.5:Providing and fixing of direction and place identification retro-reflectorised sign with 7 years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade sheeting fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4 mm thick with area not exceeding 0.9 sqm, with suitable back supporting frame of MS angle 40x40x6 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. |
| 25 | OD195311/2024-2025:Providing and erecting retro-reflectorised Object Hazard Marker 300mm x 900mm <br>Providing and erecting retro-reflectorised Object Hazard Marker sign with 07 years warranty, manufactured as per IRC 67 USING Type IV ASTM D 4956-09 micro prismatic retro reflective sheeting fixed over aluminium sheetig, 2 mm thick / aluminium composit material sheeting 4 mm thick with suitable back support frame and supported on a mild steel angle iron post 75mmx75mmx6mm, firmly fixed 30cm above ground level by means of properly designed foundation with M 15 grade cement concrete 30cmx30x45cm, 45cm below ground level including painting all non-reflective faces with epoxy paint 2 coats over epoxy primer as per approved drawing and clause 801.<br>300 mm x 900 mm |
| 26 | 55.16:Providing and fixing guard post Providing and fixing guard post of size 200mmx200mm, 1400mm long, 800mm above ground level and 600mm below GL. casted in M20 Grade concrete reinforced with 4 nos of 8mm dia longitudinal bars and 6mm dia stirrups @ 100mm c/c, firmly fixed in position by means of foundation of size 0.5mx0.5mx0.7m in M15 grade concrete below ground level including painting 2 coats on exposed surface with synthetic enamel paint in alternate white & black band 20cm wide Please Enable Macros to View BoQ information |