| 1 | [10.3]Supplying and providing of Tangri River Sand under floors Including watering and compaction in 25cm layers, dressing etc. complete In all respects (As per item 10.2) [Through Rate] |
| 2 | [10.7]Providing and laying of conglomerate floor 50mm thick cement concrete topping 1:2:4 [Through Rate] |
| 3 | [11.11.1]12 mm cement plaster finished with a floating coat of neat cement of mix : 1. 1:3 (1 cement: 3 fine sand) [Through Rate] |
| 4 | [11.12.1]15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix : 1. 1:3 (1 cement: 3 fine sand) [Through Rate] |
| 5 | [17.15.1]Granular Sub-Base with Coarse Graded Material - Grading-I or II or III (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORTandH specifications 1. Grading I material [Through Rate] |
| 6 | [17.24]Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per technical clause 406 of MORT&H specifications [Through Rate] |
| 7 | [17.25.1]Prime Coat @ 0.85kg per sqm 1. Prime Coat @ 0.60kg per sqm Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means as per technical clause 503 of MORT&H specifications [Through Rate] |
| 8 | [21.28]Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, re-handling etc., complete in all respect to the satisfaction of Engineer-in-charge [Through Rate] |
| 9 | [21.43]Extra over the rate laid down in this schedule for cement concrete work more making and finishing benching and complicated floor work in manholes, including formation of channels and bulldozing and smooth finishing the surface accurately to template. [Through Rate] |
| 10 | [21.96.10]Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths ISI marked HDPE pipe of PE-80 grade and PN- 4 for sewer application as per IS 14333-1996 (amended up to date) in trenches in complete including cost of HDPE Specials, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications and as per direction of Engineer. Note: E/w to be measured and paid separately. Rate includes cost of all specials like bends, tees required during laying of pipe line along required alignment. 10. 560 mm Outside Dia [Through Rate] |
| 11 | [21.96.7]Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths ISI marked HDPE pipe of PE-80 grade and PN- 4 for sewer application as per IS 14333-1996 (amended up to date) in trenches in complete including cost of HDPE Specials, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications and as per direction of Engineer. Note: E/w to be measured and paid separately. Rate includes cost of all specials like bends, tees required during laying of pipe line along required alignment. 7. 400 mm Outside Dia [Through Rate] |
| 12 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 13 | [4.16.1.2]Excavating trenches of required width and depth for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m. 1.2. All kind of soil Pipes, cables etc, exceeding 80 mm dia but not exceeding 300 mm dia. [Through Rate] |
| 14 | [4.17]Extra for excavating trenches for pipes, cables etc. in all kinds of soil for depth exceeding 1.5 m, but not exceeding 3 m. (Rate is over corresponding basic item for depth up to 1.5 metre). [Through Rate] |
| 15 | [4.18]Extra for excavating trenches for pipes, cables, etc, in all kinds of soil for depth exceeding 3 m in depth, but not exceeding 4.5 m. (Rate is over corresponding basic item for depth up to 1.5 metre.) [Through Rate] |
| 16 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 17 | [6.1.7]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 7. 1:5:10 (1 cement : 5 coarse sand (zone-III): 10 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 18 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 19 | [6.15.1]Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor four level, excluding cost of centering, shuttering, finishing and reinforcement : 1. 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 20 | [6.30.1]Centering and shuttering including strutting, propping etc. and removal of form for 1. Foundations, footings, bases of columns, etc. for mass concrete [Through Rate] |
| 21 | [6.30.2]Centering and shuttering including strutting, propping etc. and removal of form for 2. Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. [Through Rate] |
| 22 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 23 | [6.33.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate] |
| 24 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] |
| 25 | [7.21.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] |
| 26 | [7.22.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] |
| 27 | Providing and fixing of RCC pole at site of work size 7` long with 6`x4` at bottom and 4`x4` at top including excavation and cement concrete 1:2:4 complete in all respect as per satisfaction. |
| 28 | Providing and fixing of barbed wire fencing 6 Nos. GI wires (6Hz and 2diagonal) on existing RCC poles / angles including cost of GI wire fixing extra complete in all respect as per satisfaction. |
| 29 | ...Providing and applying tack coat with penetration grade bitumen VG - 10 using bitumen pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous/ granular surface cleaned with mechanical broom as per technical clause 503 of MORTandH specifications. |
| 30 | -_ - Dense Graded Bituminous Macadam 50 mm to 75 mm thickness (Grading II) Providing and laying 50mm - 75 mm dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG 30 @ 4.5% by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction complete, as per technical clause No. 505 of MORTandH specifications |
| 31 | -_ -Bituminous Concrete 30 mm to 45 mm thickness (grading II) with 100-120 TPH batch type HMP Providing and laying 30mm - 45 mm bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder VG - 30 @ 5.4% per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction complete as per technical clause 507 of per MORTH specifications Please Enable Macros to View BoQ information |