| 1 | Loading, carriage & unloading of following materials from centre store Daliganj/Chinhat to work site and its stacking. Distance approx (0-35) kms. |
| 2 | Line Material |
| 3 | 100 KVA T/F |
| 4 | 250 KVA T/F |
| 5 | LT PVC Cable 1x400/3.5x 240/1x 70/630SQMM |
| 6 | ABC( 3x120/95/70/50/16) Sqmm. |
| 7 | Dismantling of 25/63/100 KVA T/F from Double Pole along with dragging, loading cartage and unloading with proper safety to work site J.E. dump store/Central Store. |
| 8 | Installation of interlocking tiles with proper levelling inside transformer fencing and entrance gate as per Respo norms. |
| 9 | Construction of T/F plinth of size 2x2x1.5 meters with help of 1st class bricks and massonary in the ratio 1:4 cement & sand coarse, filling the structure completely as per norms with RCC top 1:2:2 cement, sand coarse, stone grit with MS bar and MS channel for resting T/F. All material shall be arranged by the contractor.as per RESPO specification. |
| 10 | Wiremess fencing of 11/0.4 KV S/S shall be made of rectangular of size as per site requirement not exceeding 3 meter fabrication 50x50x6 mm angle the frame is also have 1 no. Horizontal runner of MS flat 40x5 welded in middle to support of wire mess. Rectangular welded type wire mess of size 50x25 made of 10 S.W.G. wire mess shall be welded all along the periphery of the frame of size as well as on horizontal runner to give extra strength of welding to wire mess welded on the frame with door and locking arrangement. Diagonal bracing of all the frame panel will be welded with MS flat of size 50x5mm to support as per RESPO specification & direction of E/I. |
| 11 | Construction of masonry type Distribution Pillar box with first class brick ballast cement, coarse sand, local sand, brick ballast and MS Round bar of 10 mm dia including supply and mounting of 02 nos. Straight MS Angle 50x50x6x1400 mm- 2 nos., Henely type tailless fuse units 500 Amps. 650 Volts one no. for incoming and other 2No. outgoing, Copper bus bar 4 nos. 1000x50x5 mm including space for future extention of 01 no additional LT circuit with locking arrangement made of 18 SWG BP Sheet as per RESPO specification. |
| 12 | Providing and fixing of 11 KV DO fuse set along with clamps & nut bolts on existing of double pole as per IS/RESPO norms. |
| 13 | Providing and fixing SMC type Distribution fuse unit box as per RESPO specification. |
| 14 | Painting of ST Pole with Red Oxide and AL painting double coating as per RESPO specification. |
| 15 | Providing and Fixing of 11 KV Dropper Channel along with clamps & nut bolts on existing of double pole as per IS/RESPO norms. |
| 16 | Ordinary earthing by MS earth Rod 2500mm long as per RESPO Schedule. Only GI wire& Earth rod shall be supplied by the department. |
| 17 | Erection & commissioning of (3x120/95/70/25/16 Sq.mm) Aerial Bunched Conductor as per IS/RESPO norms. |
| 18 | Laying of LT PVC Cable 1x400/3.5x240/630 SQMM as RESPO specification & direction of E/I. |
| 19 | Cutting and Chopping of tree branches for clearance of HT/LT Line. After clearance line throughout pieces of tree branches of site. |
| 20 | Earthing of Lightening arrester Chemical type with GI strip 25x5 mmx10 meter long attached with clamps etc. All material shall be supplied by the contractor. |
| 21 | Earthing of T/F Neutral Chemical type with GI strip 50x5 mmx5 meter long attached with clamps, nut & bolts with chamber type arrangement. All material shall be supplied by the contractor. |
| 22 | Provioding and Installation of 3no. (R,Y,B phase) 11 KV Lightening Arrester set on Top of TF DP with proper arrangement of new earthing and it's connection with GI strip. |
| 23 | Safe Installation of 100 KVA T/F on double pole by providing and fixing of proper size all accessories. along with making HT/LT connection and its commissioning as per IS/RESPO norms. |
| 24 | Safe Installation of 250/400 KVA T/F on plinth by providing and fixing of proper size all accessories. along with making HT/LT connection and its commissioning as per IS/RESPO norms. |
| 25 | Safe Installation of 250/400 KVA T/F on double pole by providing and fixing of proper size transformer base arrangement & all other accessories . along with making HT/LT connection and its commissioning as per IS/RESPO norms. |
| 26 | SUPPLY AND INSTALLATION OF FOLLOWING MATERIAL |
| 27 | AL LUG 240/400/630 SQ MM |
| 28 | EYE-HOOK |
| 29 | SUSPENSION CLAMP |
| 30 | PG CLAMP |
| 31 | DEAD END CLAMP |
| 32 | CU L PIECE |
| 33 | AL LUG 95/120 SQ MM |
| 34 | DANGER BOARD WITH CLAMP |
| 35 | NUMBER PLATE WITH CLAMP |
| 36 | BARBED WIRE GST will be paid extra as per rule. Please Enable Macros to View BoQ information |