| 1 | (a) Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M. and lead upto 30 M. and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in charge upto a distance of 30 M. from the |
| 2 | Disposal of waste malba from site upto 5.0 km i/c all comp of work |
| 3 | Concrete with 4 cm gauge brick ballast fine sand and cement in proportion are 1:6:12 in foundation and under floors, including supply of all materials, labour, T&P etc. required for proper completion the work |
| 4 | Cement Concrete with 4cm gauge approved stone grit, coarse sand & cement in the proportion of 8:4:1 including supply of all materials ,labour, Tools & plants etc .required for proper completion of the work. |
| 5 | M-150 Brick work in 1:4 one cement and four course sand, mortar in foundation in plinth including supply of all material labour, T & P etc. required for proper completion of the work. |
| 6 | 12 mm thick plaster with cement and approved c sand mortar in 1:4 over brick work minium thickness not to be less than 1 Cm including supply of all material labour Tool & Plants etc. required for proper completion of the work. |
| 7 | Cement Concrete with 2 cm gauge approved graded stoneee grit, coarse sand and cement in the proportion of 4:2:1, including supply of all materials, labour, tools & plants etc required for proper completion of the work As per direction of E/I. |
| 8 | Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in proportion of 1:1.50:3 in cc pavement (thickness as per design) cement coarse & fine aggregate confirming to IS standard mixed in concrete mixture /Plant of not less then 0.2 cum capacity & appropriate weight batcher using approved mix design, laid in approved fixed form work (steel) channel) laying and fixing of 125 micron thick polythene film, wedges, steel plates including leveling the form work spreading the concretewith shovels, rakes, compacted using |
| 9 | Construction of Granular sub- base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in lace method with rotavator of OMC, and compacting with vibratory power roller to achive the desired density, complete (As per clause 401 RA) |
| 10 | Providing and laying of interlocking concrete Block pavement having thickness 80 mm as per drawings and technical specification Clause 1504. |
| 11 | R.C.C. 1:1.5:3 cement course sand and 20 mm gauge stone grit all work complete |
| 12 | M.S. (tor steel or plain) in Plain work such as R.C.C. or R.B. work including bending for proper shape as necessary inclding bending for proper complition of the work and including supply of all steel & wastage, bend, hooks and authorised overlapping hall be measured.(As per analysis) |
| 13 | Add 18%GST Please Enable Macros to View BoQ information |