| 1 | Dismantling cement concrete or brick or granolithic floors including base concrete and including stacking of dismantled materials as directed by the Engineer-in-charge within a distance of 60 metre (200 feet) SI NO. 697 |
| 2 | Disposal of wests malba from site upto 5.0km i/c all complete of work |
| 3 | Excavation in foundation in ordinary soil (Loam, clay or sand) Including lift upto 1.50 M. and lead upto 30 M. and including filling watering and rammind of excacated earth into the treaches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M. from the foundation trenches.(SOR UP PWD SI - 251A) |
| 4 | Earthwork in filling upto 8km distance loading and unloading in all complete |
| 5 | Concrete with 4 cm. gauge brick ballast, Fine sand of 1.25 F.M. and cement, in proportion of 12:6:1 in foundations and under floors, including supply of all materials, labour, Tools & plants etc. required for proper completion of the work. SI NO. 273 |
| 6 | M-150 class Brick in 1:4 (One cement & four fine sand of 1.25 F.M.) mortar.SI 305 |
| 7 | 12MM Thickb 1:4 cement finesand & mortar SI NO. 584 |
| 8 | Cement Concrete with 2 cm gauge approved stone grit, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work SI NO. 279A |
| 9 | supply and laying of gsb 22.5 to 53 mm stone / GSB STONE Including labour t&p etc AR. |
| 10 | Providing and laying of interlocking concrete Block pavement having thickness 80 mm as per drawings and technical specification Clause 1504. (Exclusive G.S.B) SI NO. CH-20 NI- 14 |
| 11 | Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in proportion of 1:1.50:3 in cc pavement (theckness as per design) cement coarse & fine aggregate confirming to IS standard mixed in concrete ....mixture /Plant of not less then 0.2 cum capacity & appropriate ..... material etcl & concrete etc. SI NO. CH20 |
| 12 | Cement Concrete in proportion of 8:4:1 with 4cm guage approved stone ballast, Coarse sand & cement in the materials, labour Tools & plants etc. required for proper completion of the work. (SOR UP PWD SI - 281) |
| 13 | C.C coarse sand & 2 cm gauge approved stone grit in proportions of 1:1.5;3 in lintels of door & windows excluding supply of reinforcement and its bending,but including its fixing and binding the same with 24 B.W.G.I. binding wire and including necessary centering and shuttering etc.slabs in 1:1.5:3. SI NO 284A |
| 14 | M.S. (tor steel or plain) in Plain work such as R.C.C. or R.B. work including bending for proper shape and including supply of steel & its wastage, bend, hooks, and authorised overlapping shall be measured and including cost of binding wire.SI NO. 504/AR |
| 15 | M.S. or iron work of small sizes and section such as holding down bolts, hold fast, tie rods grating etc. wrought to required from including supply of steel bolts, nuts wastage etc. and their fixing required for proper completion of the work. Same as in item 502 above but in M.S. Grills / Stair case railing / gates / trusher / racks etc. (SOR UP PWD SI - 279A) |
| 16 | Add 18%GST Please Enable Macros to View BoQ information |