| 1 | Earth work in excavation of foundation trenches inordinary soil (vide classification of soil item-A) and disposal of excavated earth so obtained to a distance uoto 50 m including all lifts levelling, ramming the foundation trenches removing the roots of trees, shrubs etc. all complete as per approved design, building specification and direction of E/I. |
| 2 | Soling - Providing dry/trap/granite/quartzite/gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting tc. Complete. |
| 3 | Providing Tor steel reinforcement of 10mm, 12mm, & 16mm dia bars as per approved design and drawing complete. |
| 4 | (C) 10mm (TMT coil Fe 500) {only valid for Tata (Tiscon), SAIL, JSPL, Electro steel Steels Ltd. Bokaro and Vizag (RINL)} |
| 5 | Centering and shuttering including strutting, propping etc. and removal of forms for |
| 6 | Foundation, footings, bases of columns etc. for mass concrete |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - all work upto plinth level: 1:2:4 (1 cement :2 coarse sand (zone III): 4 graded sone aggregate 20 mm nominal size) |
| 8 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring and shuttering, finishing and reinforcement - all work upto plinth level: 1:1.5:3 (1 cement :1.5 coarse sand (zone III): 3 graded sone aggregate 20 mm nominal size) |
| 9 | Supply, Installation , Testing and Commissioning (SITC) of package sewerage treatment plant on MBBR technology with all required equipments, media, filter, pipes, valves, fittings and all plumbing , electromechanical components etc. necessary to complete the job as per specification and direction of engineer in charge. |
| 10 | Operation and maintenance for the entire system for one year including cost of water, electricity, fuel, repair, renewal, consumables, cost of machinaries, maintenance cost civil/mechanical/electrical works, manpower, material cost, safety tools, power, energy cost etc all complete as per direction of engineer in charge. |
| 11 | Add GST 18% |
| 12 | Add Cess 1% Please Enable Macros to View BoQ information |