| 1 | Erection,Installation, Commissioning of Single Pole/Double Pole of 11 KV and LT KV Overhead/Underground Lines and Transformers By Completeing Following Works/Jobs As Per Respo Drawings/Estimate With all required Materials.Work Includes All Cartage, Carriage, of including Received Back Material. T&P, Raw Materials And Any Other Material/Work Which Is Required For Completion of Said Work But Not Mentioned In This Boq/Estimate. | Erection,Installation, Commissioning of Single Pole/Double Pole of 11 KV and LT KV Overhead/Underground Lines and Transformers By Completeing Following Works/Jobs As Per Respo Drawings/Estimate With all required Materials.Work Includes All Cartage, Carriage, of including Received Back Material. T&P, Raw Materials And Any Other Material/Work Which Is Required For Completion of Said Work But Not Mentioned In This Boq/Estimate. |
| 2 | Carriage of 8.5 Mtr Long PCC Pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. (Distance 00-70 Kms.) | Carriage of 8.5 Mtr Long PCC Pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. (Distance 00-70 Kms.) |
| 3 | Carriage of 09/11 Mtr Long ST Pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. (Distance 00-70 Kms.) | Carriage of 09/11 Mtr Long ST Pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. (Distance 00-70 Kms.) |
| 4 | Carriage of 11 KV XLPE Cable size 3x70/120/185 sq.mm. Cable form Store Center Mathura/Agra including cost of shifting of drum from inside of store, removing of cable from drum and re-rolling of extra removed cable including loading & unloading at both ends. | Carriage of 11 KV XLPE Cable size 3x70/120/185 sq.mm. Cable form Store Center Mathura/Agra including cost of shifting of drum from inside of store, removing of cable from drum and re-rolling of extra removed cable including loading & unloading at both ends. |
| 5 | Carriage of Line material i.e. conductor, G.I. wire TPMO stay rod, disc insulator, cross arm, Angle channel and other required material from Store Center at 132 KV substation Mathura to the site of work including loading and unloading of material at both ends. | Carriage of Line material i.e. conductor, G.I. wire TPMO stay rod, disc insulator, cross arm, Angle channel and other required material from Store Center at 132 KV substation Mathura to the site of work including loading and unloading of material at both ends. |
| 6 | Erection of Single pole structure 8.5 Mtrs Long PCC Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. | Erection of Single pole structure 8.5 Mtrs Long PCC Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. |
| 7 | Erection of Double pole structure 8.5 Mtrs Long PCC Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. | Erection of Double pole structure 8.5 Mtrs Long PCC Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. |
| 8 | Erection of Single pole structure 09/11 Mtrs Long ST Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. | Erection of Single pole structure 09/11 Mtrs Long ST Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. |
| 9 | Erection of Double pole structure 09/11 Mtrs Long ST Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. | Erection of Double pole structure 09/11 Mtrs Long ST Pole by digging of pits fitting of all relevant accessories with grouting in ratio 1:4:8 cement, sand and brick ballast as per standard norms. (Grouting material will be provided by contractor) as per RESPO norms. |
| 10 | Mounting of 10/16 KVA Transformer on the Single pole structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) | Mounting of 10/16 KVA Transformer on the Single pole structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) |
| 11 | Mounting of 25 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) | Mounting of 25 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) |
| 12 | Mounting of 63 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) | Mounting of 63 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) |
| 13 | Mounting of 100 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) | Mounting of 100 KVA Transformer on the Double pole Structures and connections thereof (including Carriage of Transformer from Store Centre, Mathura to site of work with loading & unloading at both ends) |
| 14 | Construction of Section pole/“T” pole for L.T./H.T. line on the erected pole as per RESPO manual and as per direction of supervising engineer. It including the cost of all labour, T&P, etc. required for proper completion of work. | Construction of Section pole/“T” pole for L.T./H.T. line on the erected pole as per RESPO manual and as per direction of supervising engineer. It including the cost of all labour, T&P, etc. required for proper completion of work. |
| 15 | Installation of stay set with grouting and nuzzling etc. as per RESPO drawing along with all routine material to be used for such works. | Installation of stay set with grouting and nuzzling etc. as per RESPO drawing along with all routine material to be used for such works. |
| 16 | Earthing of poles by fixing earthing rods and binding with earth wire as per standard norms including cost of labour T&P and required material for such work. | Earthing of poles by fixing earthing rods and binding with earth wire as per standard norms including cost of labour T&P and required material for such work. |
| 17 | Laying, sagging stringing and binding of ACSR Dog Conductor on the erected PCC pole/STP including jumpering as per RESPO manual. | Laying, sagging stringing and binding of ACSR Dog Conductor on the erected PCC pole/STP including jumpering as per RESPO manual. |
| 18 | Laying, sagging stringing and binding of ACSR Weasel Conductor on the erected PCC pole/STP including jumpering as per RESPO manual. | Laying, sagging stringing and binding of ACSR Weasel Conductor on the erected PCC pole/STP including jumpering as per RESPO manual. |
| 19 | Laying, sagging stringing and binding of Arial Bunch Conductor of Different Size on the erected PCC pole/STP including jumpering as per RESPO manual. | Laying, sagging stringing and binding of Arial Bunch Conductor of Different Size on the erected PCC pole/STP including jumpering as per RESPO manual. |
| 20 | Laying 3x70/120/185 sqmm XLPE Cable in HDPE Pipe/G.I. Pipe/Trench as per direction of supervising engineer work includes Making loops and connecting the XLPE Cable with double pole and complete commissing of the line as per RESPO Norms. | Laying 3x70/120/185 sqmm XLPE Cable in HDPE Pipe/G.I. Pipe/Trench as per direction of supervising engineer work includes Making loops and connecting the XLPE Cable with double pole and complete commissing of the line as per RESPO Norms. |
| 21 | Installation of 11 KV CT/PT Combined metering unit on existing double pole structure of large & heavy, power consumers to avoid possibility of theft of energy & 11 KV feeders at 33/11 KV sub- station including the cost of accessories (Nut & Bolt, PVC Tape etc.) required for proper completion of work also provided by the contractor. (including carriage of New 11 KV CT/PT combined metering unit from Store Center Mathura to Site of work.) | Installation of 11 KV CT/PT Combined metering unit on existing double pole structure of large & heavy, power consumers to avoid possibility of theft of energy & 11 KV feeders at 33/11 KV sub- station including the cost of accessories (Nut & Bolt, PVC Tape etc.) required for proper completion of work also provided by the contractor. (including carriage of New 11 KV CT/PT combined metering unit from Store Center Mathura to Site of work.) |
| 22 | Fixing of meter pilfer box (service connection meter holding capacity) including its carriage from Electricity Store Centre Mathura to site of work including grouting of meter pillar box in ratio 1:4:8 cement, sand and brick ballast as per standard norms. | Fixing of meter pilfer box (service connection meter holding capacity) including its carriage from Electricity Store Centre Mathura to site of work including grouting of meter pillar box in ratio 1:4:8 cement, sand and brick ballast as per standard norms. |
| 23 | Providing & Fixing of 11 KV Cable Indoor/Outdoor Jointing Kit of size 3x70 sq.mm Outdoor including removal of insulation, semi-conductor of the cable end and filling of cable box complete work as per direction of supervising engineer. | Providing & Fixing of 11 KV Cable Indoor/Outdoor Jointing Kit of size 3x70 sq.mm Outdoor including removal of insulation, semi-conductor of the cable end and filling of cable box complete work as per direction of supervising engineer. |
| 24 | Providing & Fixing of 11 KV Cable Indoor/Outdoor Jointing Kit of size 3x185 sq.mm Outdoor including removal of insulation, semi-conductor of the cable end and filling of cable box complete work as per direction of supervising engineer. | Providing & Fixing of 11 KV Cable Indoor/Outdoor Jointing Kit of size 3x185 sq.mm Outdoor including removal of insulation, semi-conductor of the cable end and filling of cable box complete work as per direction of supervising engineer. |
| 25 | Installation of 11 KV Fuse Set as per RESPO Norms | Installation of 11 KV Fuse Set as per RESPO Norms |
| 26 | Making of 11 KV Guarding by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. (Work includes All labour, T&P etc. required for proper completion of work) as per RESPO Norms. | Making of 11 KV Guarding by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. (Work includes All labour, T&P etc. required for proper completion of work) as per RESPO Norms. |