| 1 | Carriage of following materials from Elec. Store Center Unnao to work dump site along with loading unloading and propoer stocking. |
| 2 | PCC Pole 8.5 mtr long |
| 3 | PCC Pole 11 mtr long |
| 4 | Other loose line materials with including conductor, Single and double Pole accessories, complete stay & earthing, insulator, x-arm, G.I. wire etc. |
| 5 | ACSR Weasel Conductor |
| 6 | ACSR Rabbit Conductor |
| 7 | A.B. Conductor 3x120+1x95+1x16 sq mm |
| 8 | 33 KV C.T., 400/200/1-1-1A |
| 9 | Transformer Fresh Oil |
| 10 | Carriage of following T/F from Elec. Store Center Unnao to diff. work dump site along with loading unloading and propoer stocking. |
| 11 | T/F 250 KVA 11/0.4 KV |
| 12 | Carriage of following other materials from Elec. Store Center Unnao to work dump site along with loading unloading and propoer stocking. |
| 13 | Battery Set |
| 14 | Charger Set |
| 15 | Line Isolator 800A. 33 KV |
| 16 | LT PVC Cable size 1x400 sq mm |
| 17 | Supply & Fixing of following materials |
| 18 | F-Bracket |
| 19 | X-arm holding Clamp With Nut & Bolt |
| 20 | Holding Clamp with Nuts & Bolts for top & dropper Channels |
| 21 | Stay clamps with nuts & Bolts |
| 22 | Stay insulator |
| 23 | LT CLAMP |
| 24 | I HOOK |
| 25 | Suspension clamp |
| 26 | Dead end clamp |
| 27 | Copper L-Piece 50x2225x10 mm(LS) |
| 28 | All. Lugs of 400 Sq.mm. long barrel. |
| 29 | 11 KV D.O. Fuse Set |
| 30 | D.O. Fuse mounting Channel |
| 31 | Fixing of Line isolator 800 A/ Bus isolator structure with nut & bolts including all associated work. |
| 32 | Fixing of 11 KV D.O. Fuse Set at Double Pole with D.O. Fuse mounting Channel, clamps and nut & bolts including all associated work. |
| 33 | Construction of T/F Plinth of size 2x2x1.5 m on a padding 0.25 M deeo in ground 1:5:10 cement sand and brick ballast on the top of padding brick work Ist class brick of 0.95 mtr height & 0.35 mtr wall will be constructed. Rest wall should be 0.23 mtr thick, brick work in ration 1:4 cement & cores sand in the hollow portion the sand should be filled from the ground level up to 15 centimeter below from the top of wall, cement, sand & brick ballasts should be filled up to 15 centimeter. Two nos. of channel 100x50 in length 1500 mm will be grouded, 0.35 CM. RCC will be done with cores sand, cement and stone ballast in the ratio of 1:2:4. The T/Fs plinth should be plastered on all sides 12 mm thick in ratio 1:6 by cement and cores sand. (All the material will be arranged by the contractor) |
| 34 | Placement of 11/0.4 KV T/F from dump site to newly constructed T/Fs Plinth & installation and commissioning of 250 KVA & 400 KVA T/Fs of T/F Plinth and including jumpering with the system. (All the required materials as Al. Lugs Crimping Type for 250 KVA T/F & 400 KVA, Copper L-piece 62x225x12 mm etc for above job shall be provided by contractor except T/Fs and LT PVC Cable) |
| 35 | Construction of retaining wall, fabrication & erection of Wiremesh fencing around Transformer with retaining wall & 01 nos. gate with locking arrangement made of MS Angle Iron of size 50x50x6 mm jointed with nuts and bolts. Wiremesh of size 10 swg rectangle type, its painting as per norms of RESPO. (All the materials will be arrangement by the contractor) |
| 36 | Earthing of Neutral of Transformer, Transformer body and double pole by way of boring and lowering of ‘B’ class G.I. Pipe 1.5” dia from ground up to the water level (Minimum 40 Mtr. Deep) with a solid cone at the lower end of G.I. pipe. Connecting and bringing out contineous G.I. Strip size 32X5 mm. from the cone to the ground surface where it will be connected with G.I. pipe clamp from which Transformer neutral, Body & D.P. connection being done by G.I. Strip.(All the materials will be arrangement by the contractor) |
| 37 | Earthing of Neutral of Power Transformer, Transformer body and L.A. Structure and line isolator and bus insolator by way of boring and lowering of ‘B’ class G.I. Pipe 1.5” dia from ground up to the water level (Minimum 60 Mtr. Deep) with a solid cone at the lower end of G.I. pipe. Connecting and bringing out contineous G.I. Strip size 32X5 mm. from the cone to the ground surface where it will be connected with G.I. pipe clamp from which Power Transformer, Transformer body and L.A. Structure and line isolator and bus insolator connection being done by G.I. Strip.(All the materials will be arrangement by the contractor) |
| 38 | Supply & Fixing of Henley Type Tailless Unit Protection Cubical Panel 500 A, 650 V for 250 KVA DT including all associated work as per RESPO Norms. (All the material will be arranged by the contractor) |
| 39 | Laying of LT PVC Cable of size 1x400 sq mm from Transformer to LT Fuse Unit system including all associated work. (All the required materials for above job shall be provided by contractor except LT PVC Cable) |
| 40 | Dismentling of 11 K.V. line on existing pole including rolling back its conductor/G.I. wire from work site to dump site. |
| 41 | Erection of PCC/ST Pole (11 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 42 | Erection of PCC/ST double pole (11 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 43 | Erection of PCC/ST Pole (LT Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 44 | Making T-off arrangement including fabrication & fitting of accessories. |
| 45 | Grouting of PCC/ST Pole as per RESPO Norms with grouting materials. |
| 46 | Digging of pits, fixing nuzzling and grouting of stay rods as per RESPO Norms with grouting materials. |
| 47 | Laying stringing and sagging of following type HT/LT Lines including all associated work with joint/jumpers and binding of insulator as required. |
| 48 | 11 KV Line Three Phase |
| 49 | L.T. Line by ABC Three Phase |
| 50 | Carriage of old and jarjar conductor/G.I. Wire from dump site to ESC Unnao with loading, unloading and proper stacking. |
| 51 | Installation of Battery & Charger Set |
| 52 | Dismantling of old Batter Set |
| 53 | Dismantling of Old Line isolator/ Bus isolator with nut & bolts including all associated work. |
| 54 | Installation of new Battery Set with complete all work as required |
| 55 | Installation of new Charger Set with complete all work as required |
| 56 | Replacement, Installation, Energization of New/old 33 KV CT/ 33 KV PT unit and all related work. |
| 57 | Carriage of Old Battery & Charger Set from dump site to ESC Unnao with loading, unloading and proper stacking. |
| 58 | Received Back Old and Jarjar Batter Set Please Enable Macros to View BoQ information |