| 1 | Carriage of following materials from Elec. Store Center Unnao to work dump site along with loading unloading and propoer stocking. |
| 2 | ST Pole 13 mtr long |
| 3 | PCC Pole 9 mtr long |
| 4 | PCC Pole 11 mtr long |
| 5 | Other loose line materials with including conductor, Single and double Pole accessories, complete stay & earthing, insulator, x-arm, G.I. wire etc. |
| 6 | ACSR Dog Conductor |
| 7 | ACSR Rabbit Conductor |
| 8 | 11 KV XLPE Cable 3x300 sq mm |
| 9 | Carriage of following other materials from Elec. Store Center Unnao to work dump site along with loading unloading and propoer stocking. |
| 10 | 11 KV V.C.B. O/G CTR 200/100/5A, 350 MVA |
| 11 | 11 KV I/D Jointing Kit for XLPE Cable size 3x300 sq mm |
| 12 | 11 KV O/D Jointing Kit for XLPE Cable size 3x300 sq mm |
| 13 | Supply & Fixing of following materials |
| 14 | Gaurding Angle |
| 15 | Holding clamps for Gaurding angle with nuts & Bolts |
| 16 | Eye bolts for guard wires |
| 17 | F-Bracket |
| 18 | X-arm holding Clamp With Nut & Bolt |
| 19 | Holding Clamp with Nuts & Bolts for top & dropper Channels |
| 20 | Stay clamps with nuts & Bolts |
| 21 | Stay insulator |
| 22 | Earthing wire Clamp |
| 23 | PG Clamp |
| 24 | Stringing and sagging of 2 wire of 6/10 SWG GI wire for guarding and making lacing at one meter part in all span between all support including carriage from dump site to Work site with complete all work as required. |
| 25 | Dismentling of 33 K.V. line on existing pole including rolling back its conductor/G.I. wire and iron pole from work site to dump site. |
| 26 | Erection of PCC/ST Pole (33 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 27 | Erection of PCC/ST double pole (33 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 28 | Erection of PCC/ST Pole (11 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 29 | Erection of PCC/ST double pole (11 KV Line) including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 30 | Making T-off arrangement including fabrication & fitting of accessories. |
| 31 | Grouting of PCC/ST Pole as per RESPO Norms with grouting materials. |
| 32 | Earthing of pole as per RESPO Norms. |
| 33 | Digging of pits, fixing nuzzling and grouting of stay rods as per RESPO Norms with grouting materials. |
| 34 | Laying stringing and sagging of following type HT/LT Lines including all associated work with joint/jumpers and binding of insulator as required. |
| 35 | 33 KV Line Three Phase |
| 36 | 11 KV Line Three Phase |
| 37 | Laying of 11 KV XLPE Cable of diff. size with sand and bricks as per RESPO Norms. |
| 38 | Laying of underground 11 KV XLPE Cable of size 3x300 sq mm by drilling (HDD method) including laying of HDPE Pipe as per RESPO Norms with complete all work as required. (All the required materials for above job shall be provided by contractor except 11 KV XLPE Cable size 3x300 sq mm) |
| 39 | Fixing of 11 KV I/D Jointing Kit for XLPE Cable size 3x300 sq mm |
| 40 | Fixing of 11 KV O/D Jointing Kit for XLPE Cable size 3x300 sq mm |
| 41 | Fixing & Providing of HDPE 120 mm (6 inch dia) for underground 11 KV Line |
| 42 | Carriage of old and jarjar conductor/G.I. Wire from dump site to ESC Unnao with loading, unloading and proper stacking. |
| 43 | Installation & Energisation of 11 KV VCB |
| 44 | Clearing of sand from cable trench |
| 45 | Erection And installation of new 11 KV Pannels |
| 46 | Bore type Earthing of 11 KV VCB Pannel by way of boring and lowering of ‘B’ class G.I. Pipe 1.5” dia from ground up to the water level (Minimum 40 ft. Deep) with a solid cone at the lower end of G.I. pipe. Connecting and bringing out contineous G.I. Strip size 32X5 mm. from the cone to the ground surface where it will be connected with G.I. pipe clamp from VCB Panel connection being done by G.I. Strip as per RESPO norms . (All the material will be arranged by the contractor) |
| 47 | Connection of 11 KV Cables |
| 48 | Refilling of trench |
| 49 | Safe energisation of Pannels Please Enable Macros to View BoQ information |