| 1 | Part-A, Carriage, loading-unloading with proper stacking of following material from Central Store /department store to Site distance approx 20 Km. |
| 2 | ST Pole 11 Mtr. Long |
| 3 | PCC Pole 8.5 Mtr |
| 4 | 11 KV Polymeric Pin INSULATOR with Nut |
| 5 | LT PVC cable (1x240/400/630 sqmm)/ (3.5x240/400/630 sqmm.) |
| 6 | 11 KV Polymeric Disc Insulator B&S Type |
| 7 | Disc Fitting |
| 8 | ABC (3x120+1x95+1x16) Sqmm. |
| 9 | 3 Phase DP Box with Clamp |
| 10 | 11 KV (3X70/120/185)/(1x630) XLPE |
| 11 | 11 KV XLPE Cable (3x70) Sqmm. Cable Jointing Kit |
| 12 | Distribution Transformer 100 KVA |
| 13 | Distribution Transformer 250 KVA |
| 14 | Laying of XLPE/PVC Cable (1x240/400/630)/ (3.5x240/400/630) Sqmm.Sqmm cable with Material. (Only Cable shall be supplied by department) |
| 15 | Stringing & sagging of AB Cable (3x95+1x70+1x16) /(3x120+1x95+1x16) Sqmm with proper jumpring and connections with required Clamps, jumpers, piering connector. (Cost of clamps etc. shall be borne by contractor) (Only Cable shall be supplied by department) |
| 16 | Demounting of 100 KVA Distribution transformer from existing plinth after opening of all connections and opening of wire mesh fencing & safe carriage upto Central store & safe unloading. |
| 17 | Mounting of 250 KVA Transformer on plinth with making all connections & fixing all requisite items/equipments as per RESSPO,s specn and safe energizsation after connecting body & neutral of transformer to earth. only transformer shall be supplied by deptt. |
| 18 | Mounting of 100 KVA Transformer on D/P structure as per RESPO Norms (Except T/F all the materials will be supplied by the contractor ) |
| 19 | Boring type earthing of 11/0.4 KV Substation by boring and lowering of 100 fit deep 1.5” dia B Class Jindal make GI Pipe its connection in between transformer and boring with G.I. Strip of size 50x6 mm (All the material will be arranged by the contractor) (Earthing value should be 1 ohm). |
| 20 | Fabrication, erection of single 11 Mtr ST/8.5 PCC Pole with fixing of necessary clamps, accessories required including supply & fixing of clamp, nuts & bolts, Grouting with cement, sand, brick ballast in ratio :1:4:8 and earthing as per RESPO specification & direction of E/I with fixing of T-off with fitting & tapping pole. (Only Pole shall be Supplied by the deptt.) |
| 21 | Fabrication, erection of wire mesh fencing 2.0 Mtr. Height, on cements boundry of height 1.0 fit. including grouting of fabrication MS Angle 50x50x6 mm. Painting of fencing and support with all material as per specification around 11/.4 KV Sub-Station. (All material shall be supplied by the contractor.) |
| 22 | Construction of Transformer plinth of size 2x2x1.5 meter with the help of first class brick and masonry in the ratio 1:4 cement & sand coare. Filling the structure completely as per norms with RCC top 1:1:2 cement, sand coarse and stone grith with MS Bar and MS channel for resting transformer wheel 2x(125x65x2000)mm and plaster. (All material shall be arranged by the contractor.) |
| 23 | Construction of massonary/Henly type distribution piller box with first class brick ballast cement coarse sand, local sand, brick ballast and MS round bar of 10 mm. Dia including fixing of 3 Nos 500 Amp/650 Volt fuse unit with Copper Busbar etc. (All material shall be supplied by the contractor.) |
| 24 | Providing and fixing of copper L Pieces with suitable nuts and bolt for100 kva transformes with proper disconnection and reconnection. |
| 25 | Fabrication erection of Substation D/P on 9/11 Mtr. ST pole Long with fixing of necessary clamps accessories required including supply and fixing of straight MS Channel 100x50 mm. (2240 mm long ) one Nos with arrangement of fixing 3 Nos. pin insulator,(ST pole/ PCC Pole supplied by the deptt). |
| 26 | Earthing of poles as per RESPO Norms with earth rod (All the material supplied by the contractor ) |
| 27 | Grouting of ST/PCC pole |
| 28 | Painting of ST/PCC pole |
| 29 | Providing and fixing of TPMO |
| 30 | Providing and fixing DO fuse set |
| 31 | `Providing and fixing Nut and bolts |
| 32 | Providing & Fixing of Suspension clamps (Insulated) with bolts & nut. |
| 33 | Providing & Fixing of dead emd clamps (Insulated) with bolts & nut. |
| 34 | Fixing of Distribution Box with proper clamps, nuts and bolts & taking connection from ABC to distribution for supply. |
| 35 | Providing and Fixing of M.S. channel/Dropper channel |
| 36 | Making of bus-bar on double pole with the help of M.S. channel, M.S. T-off, pin & pin insulator |
| 37 | Providing and fixing ALU LUG OFF SIZE |
| 38 | Providing & Fixing of I-Hook (Insulated) for above clamps with bolts & nut. |
| 39 | Providing & Fixing of J-Hook (Insulated) for above clamps with bolts & nut. |
| 40 | Providing and fixing of danger board |
| 41 | Providing and fixing of stone pad |
| 42 | Providing and fixing of 11 KV Single Core Lead 25 sqmm. |
| 43 | Grouting & concreting of stay rod 1800x16 mm. Fixing , tighting and nozzling of stay wire with the pole of required tension with clamps as per RESPO schedule, complete in all respects(All material shall be arranged by the contractor.) |
| 44 | Laying of 11 KV 3x70/120/185 sq.mm XLPE cable by manual method |
| 45 | Part-B, Carriage, loading-unloading with proper stacking of following material from Central Store /department store to Site distance approx 20 Km. |
| 46 | 11 KV 3x185/300 sq.mm XLPE cable |
| 47 | 9/11 Mtr long ST pole |
| 48 | 11 KV cable box straight thru |
| 49 | 11 KV cable box O/D |
| 50 | 11 KV pin insulator with pin |
| 51 | ACSR DOG CONDUCTOR |
| 52 | HDPE Pipe PE-80, PN-6, DN-200mm dia |
| 53 | 11 KV VCB FOR OG CTR 200/100/5. |
| 54 | Fabrication, erection of cable exposure on 11 Meter long ST pole with fixing of necessary clamps, accessories required including supply and fixing of straight Ms 100x50mm Top channel (2240mm long) One no, dropper channel 100x50mm (2240mm long) 2 Nos, with arrangement of fixing 3 nos. pin insulator, along with 11 KV DO Fuse set as per RESPO spenc & direction of E/I. ST Pole shall be supplied by the deptt. |
| 55 | Fixing of M.S. channel |
| 56 | Earthing of poles as per RESPO norms . (All the materials supplied by contractor) |
| 57 | Grouting of poles with help of cement sand & brick ballast. |
| 58 | Painting of pole |
| 59 | Laying of 11 KV 3x185 sq.mm XLPE cable by manual method |
| 60 | Laying of HDPE Pipe PE-80, PN-6, DN-200mm dia pipe for laying of 11 KV 3x185 sqmm, XLPE Cable with HDD (Trenchless) method including cable laying. |
| 61 | Hoisting of cable with the help of GI pipe 4\\" dia each having length of 3 meter along with supply and fixing of MS brackets and GI pipe. |
| 62 | Making of bus-bar on double pole with the help of M.S. channel, M.S. T-off, pin & pin insulator |
| 63 | High presure testing of cable |
| 64 | Providing and fixing of danger board |
| 65 | Providing and fixing of cable route marker |
| 66 | Providing and fixing of under ground warning tape |
| 67 | Installation of 11KV I/C &O/C VCB as per norms. |
| 68 | Chemical earthing of VCB. |
| 69 | Complete testing of VCB. |
| 70 | Making of J/Kit |
| 71 | If, due to any circumstances, the plinth construction work is not feasible, then the 250 KVA transformer shall be installed on a double pole arrangement as per requirement. The cost of this work shall also be equivalent to the cost of plinth construction. Please Enable Macros to View BoQ information |