| 1 | SITC OF 25 KW SOLAR POWER PLANT FOR MPS:- |
| 2 | Design, manufacturing, Supply, erection, testing, net metering and commissioning including warrantee and AMC for 5 year grid connected solar power plants including all required items and accessories such as solar monocrystalline PV module, string inverter and associated component, DC and AC cable with termination kits, jointing kits, control cables/communication cable, electrical panels, lighting arrester chemical earthing (03 Nos) etc for proper completion of works as per latest IE rules and MNRE guidelines. |
| 3 | Miscellaneous works i.e. meter testing and commissioning of transformer with fixing of 1.1 KV power cable and required construction work for required meter room/ (inverter housing room), survey work of site, Site clearance, fencing, grouting and land levelling works, Removal of any existing voluminous from the site for solar plant provision of sufficient electrical lighting at the solar power plant location during the installation & commissioning etc. |
| 4 | SITC of Data logging system (Hard ware and software) for measuring solar irradiance, temperature, AC voltage AC output current output power, energy DC input voltage DC input Current, Temperature invertor stutus, module temperature string voltage & current through GSM modem / wifi with storage of data. |
| 5 | 11KV bidirectional net metering complete as per UPCL guideline with supply of net meter & meter box ( suitable for fixing of solar meter with CT ) and all accessories. |
| 6 | SITC OF 05 KW SOLAR POWER PLANT FOR IPS:- |
| 7 | Design, manufacturing, Supply, erection, testing, net metering and commissioning including warrantee and AMC for 5 year grid connected solar power plants including all required items and accessories such as solar monocrystalline PV module, string inverter and associated component, DC and AC cable with termination kits, jointing kits, control cables/communication cable, electrical panels, lighting arrester chemical earthing (03 Nos) etc for proper completion of works as per latest IE rules and MNRE guidelines. |
| 8 | Miscellaneous works i.e. meter testing and commissioning of transformer with fixing of 1.1 KV power cable and required construction work for required meter room/ (inverter housing room), survey work of site, Site clearance, fencing, grouting and land levelling works, Removal of any existing voluminous from the site for solar plant provision of sufficient electrical lighting at the solar power plant location during the installation & commissioning etc. |
| 9 | SITC of Data logging system (Hard ware and software) for measuring solar irradiance, temperature, AC voltage AC output current output power, energy DC input voltage DC input Current, Temperature invertor stutus, module temperature string voltage & current through GSM modem / wifi with storage of data. |
| 10 | 11KV bidirectional net metering complete as per UPCL guideline with supply of net meter & meter box ( suitable for fixing of solar meter with CT ) and all accessories. Please Enable Macros to View BoQ information |