| 1 | 125 TPD FEED PRESS MUD TO COMPRESSED BIOGAS (CBG) PLANT:The brief scope of work shall include Project Management; Complete Process Design & Detailed Engineering; Procurement; Fabrication; Inspection; Supply; Manufacture; Transportation of all equipment/materials to the work site & Storage at site; assembly, erection & installation; Construction and Erection of Civil & Structural, Mechanical, Electrical, Instrumentation & Piping works; Acid /Alkali resistant proof tiling; Painting; Testing; Pre-commissioning; commissioning; 3D modeling; HAZOP; Training of EIL’s personnel; performance guarantee test run for 72 hours continuous operation in presence of EIL’s Representatives; guaranteeing and handing over of 125 TPD feed Press Mud to Compressed Biogas Plant (CBG) Plant to EIL on lump sum turnkey basis as per scope of work/supply, equipment list, standards, P&IDs, data sheets, drawings, etc., all complete within Contractor's specified battery limits including supply of spares, chemicals & consumables all complete as per Bidding Document and directions of Engineer incharge. Contractor shall be responsible for coordination & interaction as required with EIL, local authorities, state/ central/ local regulatory and statutory bodies and any other agencies required during execution/ commissioning of the project. All Necessary Statutory approvals required for the Proposed CBG plant shall be in the Contractors Scope including payment of applicable fees. |
| 2 | Total Lumpsum Price |
| 3 | Design and Detailed Engineering of complete 125 TPD feed Press Mud to Compressed Biogas Plant (CBG) Plant as per DESCRIPTION PROVIDED IN FURTHER BREAK-UP OF PRICE FOR DESIGN & DETAILED ENGINEERING (Form SP-4) and as per Bidding Document. |
| 4 | Design and Detailed Engg. prices included in SP-0 Prices |
| 5 | Procurement, supply, transportation, Shop fabrication, assembly, testing of all items/ Equipment’s / Components / Materials / bought outs, Procurement of materials and sub-ordered equipment, bought outs, shop fabrication/assembly, inspection, testing, supply of all spares, chemicals & consumables, lubricants, as required, special tools and tackles required for work as per DESCRIPTION PROVIDED IN FURTHER BREAK-UP OF LUMP SUM PRICES (Form SP-5) and as per Bidding Document. |
| 6 | Total Supply Prices included in SP-0 Prices |
| 7 | Lump sum price for construction portion as per requirement detailed out in various section of bidding document which includes following but not limited to: Construction, installation completion of work in all respects for Package including required Cranes, Scaffolding, temporary barricading, Transportation and site handling of material/equipments, supply of consumables, tools and tackles, field engineering services, Receipt, storage, conservation, preservation of FIM and contractor supplied items etc.Fabrication, construction, assembly, erection at site for all piping, civil, structural,architectural,mechanical, electrical and instrumentation works within battery limit, coating, painting, testing, etc.providing all temporary works/structures and equipment for completion, obtaining statutory approvals,pre-commissioning, commissioning, performance guarantee test runs, Training to Owner personals,completing all the work in all respects to make system smooth, operable and handing over as per Bidding Document requirements and instructions of the Engineer In Charge. |
| 8 | Construction prices included in SP-0 Prices |
| 9 | FIXED CHARGES for Operation & Maintenance (O&M) of 125 TPD FEED PRESS MUD TO COMPRESSED BIOGAS (CBG) PLANT . |
| 10 | Fixed O&M Charges for FIRST YEAR (during Defect Liability Period) |
| 11 | Fixed O&M Charges for SECOND YEAR |
| 12 | Fixed O&M Charges for THIRD YEAR |
| 13 | Fixed O&M Charges for FOURTH YEAR |
| 14 | Fixed O&M Charges for FIFTH YEAR |
| 15 | VARIABLE CHARGES for Operation & Maintenance (O&M) of 125 TPD FEED PRESS MUD TO COMPRESSED BIOGAS (CBG) PLANT |
| 16 | Variable O&M Charges for FIRST YEAR (during Defect Liability Period) |
| 17 | Variable O&M Charges for SECOND YEAR |
| 18 | Variable O&M Charges for THIRD YEAR |
| 19 | Variable O&M Charges for FOURTH YEAR |
| 20 | Variable O&M Charges for FIFTH YEAR |
| 21 | Total Lumpsum charges for 5 (Five) years O&M of 125 TPD FEED PRESS MUD TO CBG PLANT as per the provisions of bidding document = TOTAL OF ABOVE 1.01+1.02+1.03+1.04+1.05+2.01+2.02+2.03+2.04+2.05) |
| 22 | COOLING TOWER PACKAGE ON LUMPSUM TURNKEY BASIS WITH SINGLE POINT RESPONSIBILITY INCLUDING BUT NOT LIMITED TO THE FOLLOWING ACTIVITIES OF WORKS:FORM-SP-9 |
| 23 | Guaranteed Electric Power Consumption (GPC) |
| 24 | COOLING TOWER PACKAGE ON LUMPSUM TURNKEY BASIS WITH SINGLE POINT RESPONSIBILITY INCLUDING BUT NOT LIMITED TO THE FOLLOWING ACTIVITIES OF WORKS:FORM-SP-9 |
| 25 | Guaranteed Water Consumption (GWC) Name of Work/Item: CONSTRUCTION OF PRESS MUD BASED CBG PLANT ON LSTK AT KOLAPUR. Bidding Document No: DC/ 7715-000-EP-T-1005 / 6 Notes: |
| 26 | Bidder shall furnish CIF value against each quoted item and give description of goods along with its quantities (UNIT TO BE SPECIFIED BY THE BIDDER) to be imported in the above Format. |
| 27 | Bidder to consider import tax credit of IGST available at their end (in case of import of raw materials/components) in their quoted prices. |
| 28 | Merit rate of custom duty shall be applicable. |
| 29 | The CIF values(s) indicated by the vendor shall be deemed to be the maximum values(s) for the purpose of variation in Basic Custom Duty and Social Welfare Surcharge. Bidder Name : SCHEDULE OF PRICES (FORM SP-10) (DETAILS OF BUILT-IN-CIF VALUE OF IMPORT CONTENT)(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) DESCRIPTION CIF Value of Import Content included in Quoted Prices for Column (5) Quantity(INR)(6) RATE OF CUSTOM DUTY INCLUDED IN QUOTED SUPPLY PRICES S no.(1) For Item no./ Sl . No. as per price schedule format(2) Description of Imported items (3) Unit of Measurement (4) Quantity (5) Custom Tarrif No(7) BASIC CUSTOMS DUTY (%)(8) SOCIAL WELFARE SURCHARGE(%)(9) IGST(%)(10) TOTAL CUSTOM DUTY (%)(11) Please Enable Macros to View BoQ information |