| 1 | Percentage BoQ BoQ_Ver3.0 Percentage Normal INR Only INR Select, At Par, Excess (+), Less (-) IOCL Tender Inviting Authority: EXECUTIVE ENGINEER PROVINCIAL DIVISION, BATHINDA NAME OF WORK:- NEW CONSTRUCTION OF LINK ROAD INDUSTRIAL AREA LEHRA KHANA BHUCHO MANDI Contract No: CIVIL Works Name of the Bidder/ Bidding Firm / Company : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Sl.No. Work Name Item Code / Make Quantity Unit RateRs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT inRs. P TOTAL AMOUNT With Taxes TOTAL AMOUNT In Words |
| 2 | CIVIL WORK |
| 3 | Compaction of earth work & Prepration of Sub grade including loosing,leveling of earth 225mm thick top layer, rough dressing of soil, final dressing of earth to give level camber,watering,rolling with road roller, compacting the bed to achieve minimun dry density as given in Table 300-2 as per technical clause 305 of MORT&H specifications (in case of link roads earth work to be done by villagers.) as per CSR 24.4(c) |
| 4 | Providing and laying brick on end edging as per CSR 24.14 |
| 5 | Construction of granular sub-base by providing material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per MORD technical specifications CSR-24.7 |
| 6 | Providing, laying, spreading and compacting stone aggregates of Grading I to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical specifications (without screening for low volume Roads/undersigned) 24.11(ii) |
| 7 | Providing, laying, spreading and compacting stone aggregates of Grading II to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical specifications (without screening for low volume Roads/undersigned) 24.12(ii) |
| 8 | Providing and laying surface dressing in single coat using crushed stone aggregates of specified size on a layer of bituminous binder VG-10 @ 1kg per sqm laid on prepared surface after cleaning theroad surface and rolling with 8-10 tonne smooth wheeled steel roller complete as per technical clause 509 of MORT&H specifications CSR 24.24 |
| 9 | Providing and applying tack coat with penetration grade bitumen VG-10 using bitumen pressure distributor at the rate of 0.40 kg per sqm on the prepared bituminous surface/granular surface treated with prime coat after cleaning the surface complete as per technical specifications CSR 24.16(b) |
| 10 | Providing, laying and compaction of open - grade surfacing of 20 mm thickness consisting of crushed stone aggregates of specified grading premixed in a Continuous type hot mix plant with bituminous binder VG-10 @ 1.46kg per sqm, laid with Paver Finisher Mechanical and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades complete as per technical clause 510 of MORT&H specifications CSR24.25(a) |
| 11 | Providing and laying of premix sand seal coat premixed in Continuous type hot mix plant using specified fine aggregates and penetration grade bitumen VG-10 @ 0.68kg per sqm, laid to the specified levels, grade and cross fall complete as per technical clause 511 of MORT&H specifications CSR 24.28(c) |
| 12 | Kassi work undressed involving an average horizontal throw up to 2.0metres and an average vertical lift up to 0.5 metres including breaking of clods. 6.2 a |
| 13 | Hazard Marker sign board 300x900mm rectangular as per IRC 67- 2012 with high intensity Microprismatic grade retro reflective Sheeting as per ASTM D 4956 09 and IRC 67 2012, fixed over 4mm thick Aluminium Composite Material (ACM) sheeting having skin thickness of 0.4 to 0.5 mm on both sided and fixing the same with suitable size aluminium alloy rivets @ 200 mm c/c to back support frame of 25x25x3mm angle iron supported on a square hollow steel section post 60x60x3.2mm conforming to IS 4923 firmly fixed to ground including foundation concrete M-25 of size 0.45x0.45x0.60m for vertical post complete as per clause 801 of MORT&H specifications Using high intensity Microprismatic grade retro reflective Sheeting Type IV as per ASTM D 4956 09 and as per IRC 67 2012 CSR 24.51 b |
| 14 | Road marking with hot applied thermoplastic compound 2.5mm thick including reflectorising glass beads @ 0.25kg per sqm area as per IRC:35 1997 complete as per technical clause 803 of MORT&H specifications as per CSR 24.57 |
| 15 | Videography of Road |
| 16 | Cultural Cess on Part-A Total in Figures 1013651.0 1013651.0 INR Ten Lakh Thirteen Thousand Six Hundred & Fifty One Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 INR Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |