| 1 | fo|qr forj.k [k.M lyseiqj ds {ks=kUrxZr 25 ls 63 ds0oh0,0 ds 30 vn~n ifjorZd {kerko`f} djusa dk dk;ZA |
| 2 | Loading, Unloading and safe carriage, with complete fitting, of 63 KVA T/F from Store Centre, Deoria to work site |
| 3 | Loading, Unloading and safe carriage of 25 KVA T/F from work site to Store Centre, Deoria |
| 4 | Earthing of T/F |
| 5 | Supply of Aluminium Cripling Lug 100 sqmm |
| 6 | fo|qr forj.k [k.M lyseiqj ds {ks=kUrxZr 63 ls 100 ds0oh0,0 ds 40 vn~n ifjorZd {kerko`f} djusa dk dk;ZA |
| 7 | Loading, Unloading and safe carriage, with complete fitting, of 100 KVA T/F from Store Centre, Deoria to work site |
| 8 | Loading, Unloading and safe carriage of 63 KVA T/F from work site to Store Centre, Deoria |
| 9 | Earthing of T/F |
| 10 | Supply and Installtion of Aluminium Cripling Lug |
| 11 | Supply and Installtion of 11 KV Fuse Set |
| 12 | fo|qr forj.k [k.M lyseiqj ds {ks=kUrxZr 100 ls 250 ds0oh0,0 ds 29 vn~n ifjorZd {kerko`f} djusa dk dk;ZA |
| 13 | Loading, Unloading and safe carriage, with complete fitting, of 250 KVA T/F from Store Centre, Deoria to work site |
| 14 | Loading, Unloading and safe carriage of 100 KVA T/F from work site to Store Centre, Deoria |
| 15 | Earthing of T/F |
| 16 | Construction of plinth size 1.75 x 1.50 x 1.50 mrt. And 0.25 mtr. Under ground brick wall far plinth of ratio sand and cement 6:1 and plastering by ration 5:1 feeling the peet by sand clay, brick blast and remaining if fixing M.S. Channel 02 no 50 x50 x 100 mm with standard space the top floor be made of RCC and left for quring for 7 days |
| 17 | Pale Fencing |
| 18 | Supply of Aluminium Cripling Lug |
| 19 | Supply of Copper L-piece 50x225x10 mm |
| 20 | Supply of Al Leg Long Barrel Off size |
| 21 | Supply and Installtion of Tailless Unit |
| 22 | fo|qr forj.k [k.M lyseiqj ds {ks=kUrxZr 10 ls 25 ds0oh0,0 ds 27 vn~n ifjorZd {kerko`f} djusa dk dk;ZA |
| 23 | Loading, Unloading and safe carriage of PCC Pole 8.5 Meter Long From Store to Work Site |
| 24 | Loading, Unloading and safe carriage of ACSR Weasel Conductor From Store to Work Site |
| 25 | Erection Of PCC Pole With All Accessories complete in all respects as per site requirement |
| 26 | Grouting of Pole |
| 27 | Fitting of Earthing set on Pole |
| 28 | Fittiing of Stay |
| 29 | Grouting of Stay |
| 30 | Loading, Unloading and safe carriage, with complete fitting, of 25 KVA T/F from Store Centre, Deoria to work site |
| 31 | Loading, Unloading and safe carriage of 10 KVA T/F from work site to Store Centre, Deoria |
| 32 | Earthing of T/F |
| 33 | Supply and Installtion of Stone Pad 300x75 mm |
| 34 | Supply and Installtion of Clamp For Top & Dropper Channal |
| 35 | Supply and Installtion of Clamp For Stay |
| 36 | Supply and Installtion of 11 KV Fuse Set |
| 37 | Supply and Installtion of Stay insulator |
| 38 | Supply of Aluminium Cripling Lug |
| 39 | fo|qr forj.k [k.M lyseiqj ds {ks=kUrxZr 16 ls 25 ds0oh0,0 ds 02 vn~n ifjorZd {kerko`f} djusa dk dk;ZA |
| 40 | Loading, Unloading and safe carriage of PCC Pole 8.5 Meter Long From Store to Work Site |
| 41 | Loading, Unloading and safe carriage of ACSR Weasel Conductor From Store to Work Site |
| 42 | Erection Of PCC Pole With All Accessories complete in all respects as per site requirement |
| 43 | Grouting of Pole |
| 44 | Fitting of Earthing set on Pole |
| 45 | Fittiing of Stay |
| 46 | Grouting of Stay |
| 47 | Fitting of MS Angle (T/F Base) 75x75x6x2028 mm with clamp and nut bolt |
| 48 | Loading, Unloading and safe carriage, with complete fitting, of 25 KVA T/F from Store Centre, Deoria to work site |
| 49 | Loading, Unloading and safe carriage of 16 KVA T/F from work site to Store Centre, Deoria |
| 50 | Earthing of T/F |
| 51 | Supply and Installtion of Stone Pad 300x75 mm |
| 52 | Supply and Installtion of Clamp For Top & Dropper Channal |
| 53 | Supply and Installtion of Clamp For Stay |
| 54 | Supply and Installtion of 11 KV Fuse Set |
| 55 | Supply and Installtion of Stay insulator |
| 56 | Supply of Aluminium Cripling Lug 100 sqmm Please Enable Macros to View BoQ information |