| 1 | Labour charges for removing grass, thorney shrubs, Jungli shrub, Kubabul and alike grass along roadside making the ground clean by showel and phavaras etc. complete. |
| 2 | Excavation for catch / side water gutter in Hard murum and boulder strata to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff as directed |
| 3 | Supplying hard murum/ kankar at the road site, including conveying and stacking complete |
| 4 | Spreading hard murum/ soft murrum/ gravel or kankar for side width complete |
| 5 | Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM) road surface including all mataerials, preparing the existing road surface, spreading 40mm. stone metal layers 100% crusher broken metal with conical crusher plant heating and spraying the bitumen of specified grade @ 1.75 kg/sqm, spreading 12mm.size chips compacting with static roller having weight 8 to 10 MT. to achive the desired degree of compaction as per Technical Specification Clause 506 etc. complete. Including picking of existing WBM surface.(VG-30 bulk bitumen rates are considered to arrive at rates) |
| 6 | Open Graded Premix Surfacing- Providing and Laying OGC 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates premixed with bituminous binder transported to site with VTS , laid over a previously prepared surface, finished to the required grade, level, alignment, and rolling to achieve the desired compaction but excluding prime / tack and Seal coat. For Bitumen of specified grade--USING drum mix type hot mix plant with SCADA, Paver and Vibratory roller ( Over MPM Surface) (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 7 | Providing and applying tack coat on the prepared surface heating by fames in Boiler and spraying bitumen set footed in bitumen boller on B.T. surface 2.5 kg/10 sqm.(VG-30 bulk bitumen rates are considered to arrive at rates) |
| 8 | Providing bituminous Type A liquid seal coat on bituminous surface including supplying all materials and bitumen of specified grade preparing existing road surface, heating and applying bitumen @ 0.98 KgSqm. by mechanical means, spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete. (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 9 | Excavation for foundation in earth, soils of all types, sand, gravel, soft murum including shoring and strutting, dewatering as necessary and disposing off excavated stuff as directed etc. complete. ( By Mechanical Means ) |
| 10 | Excavation for foundation in hard murum and boulders including shoring and strutting, dewatering as necessary and disposing off excavated stuff as directed etc. complete. a) Upto 1.50m lift Normal Rate |
| 11 | Excavation for foundation in soft rock including shoring and strutting, dewatering as necessary and disposing off excavated stuff as directed etc. complete. a) Upto 1.50m lift Normal Rate |
| 12 | Providing and laying in situ / ready mix / ready mix M10 cement concrete of trap/ granite/ quartzite/ gneiss metal in foundation including necessary centering, formwork, bailing out water, compacting and curing etc. complete. (with fully automatic micro processor based PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand) |
| 13 | Providing and laying in situ / ready mix M-15 plain cement concrete of trap /granite/quartzite/ gneiss metal for cast in citu piers, abutment, returns, wings etc. including provision of \\"V\\" shaped false joints to form suitable panels on the faces to approve design with compacting by vibrating and curing complete, including plywood/steel form work centering ( excluding dewatering by means of pump) and including bailling out water and curing finishing in CM 1:3 etc. complete. as directed by engineer in charge basic rate shall be increased for height above 5.00 m in followinh manners (a) Height upto 5 M. (With Concrete Mixer)With fine agreegates of required specifications ( VSI sand finely washed etc |
| 14 | Providing tar paper bearing including laying in proper position etc. complete. |
| 15 | Providing and laying in situ / ready mix M-25 controlled cement concrete of trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork, centering and finishing in cement plaster excluding reinforcement etc. complete. (with fully automatic micro processor based PLC with SCADA enabled concrete batch mix plant / pan mixer and fine agreegates of required specifications ( VSI sand finely washed etc ) i) Height up to 5 m, normal rate. ii) Height 5 to 7.50 m, add 5 percent extra over basic rate. |
| 16 | Providing and laying in situ / ready mix M20 RCC of trap/ granite/ quartzite/ gneiss metal for RCC work of ballast walls, kerbs and box returns including scaffolding, compaction, formwork finishing and curing etc. complete. (excluding reinforcement, with fully automatic micro processor based PLC with SCADA enabled concrete batch mix plant / pan mixer with fine agreegates of required specifications ( VSI sand finely washed etc ) RCC work of Ballast walls & Kerb |
| 17 | Providing and laying in situ / ready mix controlled M-20 cement concrete of of trap / granite / quartzite/ gniess metal for reinforced cement concrete caps over piers and abutments including necessary sacffolding plywood/steel formwork, compacting by vibrating, finishing in CM 1:3 and curing etc complete ( Excluding reinforcement) With reversible drum type mixer/ concrete batch mix plant (pan mixer) . with fine agreegates of required specifications ( VSI sand finely washed etc ) |
| 18 | Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete. |
| 19 | Providing earth work in embankment with approved materials obtained from departmental land upto lead of 50m. including all lifts, laying in layers of 20cm. to 30cm. thickness breaking clods, dressing to the required lines, curves, grades & section, watering and compaction with vibratory roller to achieve not less than 97 % of standard proctor density etc. complete ( Material obtained from departmental Land) |
| 20 | Back filling behind abutment, wing wall and return wall as per drawings and technical specifications etc. complete. (by granular material) |
| 21 | Providing and laying 0.90 meter thick metal mat consisting of rubble, oversize metal and normal size metal in specified thickness as per detailed drawing including supplying all materials, hand packing of rubble, spreading metal in layers and hard murum including watering and compaction with power roller etc. complete. |
| 22 | Providing and laying weep holes of 100 mm diameter PVC pipes as per drawing for abutment returns, return walls etc. Complete. |
| 23 | Providing and fixing stream lined M-20 grade RCC guard stone including mild steel bar reinforcement etc. complete. |
| 24 | Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge |
| 25 | Quality Control Test For Aggregate - Water Absorption, Specific Gravity, Impact Value, Crushing Value |
| 26 | Quality Control Test For Aggregate - Fineness Modulus (Seive Analysis), Silt & Clay Content |
| 27 | Compressive Strength of C.C.Cube (Set of 3 Cubes) M-15 |
| 28 | Compressive Strength of C.C.Cube (Set of 3 Cubes) M-20 |
| 29 | Compressive Strength of C.C.Cube (Set of 3 Cubes) M-25 |
| 30 | Penetration, Softening Point, Flash & Fire Point, Specific Gravity - Bitumen |
| 31 | Provision For Royalty Charges As Per Revenue, and Forest Department notification dated 11/05/2015 as Maharashtra Minor Mineral Extraction Rules 2010 and as per instruction in general notes on SSR |
| 32 | Provision For Royalty Charges As Per Revenue, and Forest Department notification dated 11/05/2015 as Maharashtra Minor Mineral Extraction Rules 2010 and as per instruction in general notes on SSR Please Enable Macros to View BoQ information |