| 1 | Safe loading Carriage including unloading and proper stacking of following materials from central store Barabanki to site of work. |
| 2 | ABC (3x120+1x95+1x16) Sq MM |
| 3 | TRANSFORMER 250 KVA 11/0.430 KV |
| 4 | LT PVC 1x400 sqmm |
| 5 | PCC POLE 8.5 MTR LONG |
| 6 | 11 KV PIN INSULATOR POLYMER |
| 7 | 11 KV DISK INSULATOR POLYMER WITH FITING |
| 8 | GI WIRE 08 S.W.G. |
| 9 | EARTHING ROD OF STP WITH COMPL. |
| 10 | TOP CHANNEL |
| 11 | SUBSTATION ANGLE |
| 12 | ABC (3x95+1x70+1x16) Sq MM |
| 13 | TRANSFORMER 100 KVA |
| 14 | TRANSFORMER 63 KVA |
| 15 | Dragging of pole from Store to site |
| 16 | Grouting of Pole in depth of 1/6th the length of pole in ratio 1:4:8 in cement sand and brick ballast and construction of pole plinth 300mmx45mm above ground level in 1:2:4 in cement, coarse sand and stone grit as per respo norms. |
| 17 | Erection of Stay set of 16x1800 mm rod duly painted with red oxide,anchor plate, thumble turn buckle and stay insulate etc. digging of pit of size of size 0.4x0.6x1.6 m for grouting 1:3:6 cement concrete, with stay of size 7/8 SWG, nuzzling & Grouting. |
| 18 | Installation of Mounting of Following capacity of Transformer including its connection between 11 KV and LT Line mounting provinding Crimping type Aluminium lugs of required size.( All the material except transformer will be arranged by the contractor) |
| 19 | Mounting of 63 KVA Tranformer |
| 20 | Mounting of 100 KVA Tranformer |
| 21 | Mounting of 250 KVA Tranformer |
| 22 | Errection of Substation type double pole with PCC including mounting of Top Channal Dropper Channel, base angle with clamps with nut & bolt 33/11 KV line including grouting of support and plinthing 300 mm above ground level, fitting of 33/11 KV pin & Pin insulator. 1/6 of total lenght of poles will remain under the ground and planted on stone pad of Size 300x300x75 MM. |
| 23 | Stringing and Sagging of LT ABC Cable (3*120+1*95+1*16) & (3*95+1*70+1*16) SQMM (Cable will be provided by the department) |
| 24 | Earthing of Pole with MS Earthing Rod. |
| 25 | Provinding & Fixing of various type materials. All materials shall be supplied by the contractor. |
| 26 | Copper L-piece for DT |
| 27 | PG Clamp |
| 28 | Alluminium Lug 120 sqmm |
| 29 | Alluminium Lug 400 sqmm |
| 30 | M.S. NUTS & BOLTS OFF-SIZES |
| 31 | SACKEL INSULATOR |
| 32 | LT CLAMP FOR PCC |
| 33 | Erection of pipe type earthng for DT with the help of B-Class G.I pipe of size 1.5 inch dia, 60 feet deep boring by providing G.I strip 50x6 MM, 6 meter long attached with clamp L-piece nut & bolt & G.I cap |
| 34 | T/F FENCING 250 KVA wir emess fencing of 11/0.4 KV substation shall be made rectangular off size as nper site requirement not exeeding 3 meter fabrication 45x45x5 mm angle material shall be supply by contracter |
| 35 | T/F PLINTH 250 KVA plinth construction 2x2x1.5 meter with brick cement etc filling wth the sand in the hollow space plastring , 2 No MS channel on the top of plinth for placement of tranceformer , |
| 36 | Construction of LT DistriBution Cum LT Protection Piller Box MS Angle in Rectangle Size 50x50x6 MM 7.5 Meter long For installation Of Henley Type Tailleness Fuse Unit 300 AMP 650 Volt For 3 nos Outgoing Circuits With 4 Nos. Copper Bus bar OF size 1000x50x6 mm Including Proper Grouting of Structure By Digging of pits Off Size 300x300x600 mm With the Help Of Cement, Coresand And Aggregate in the ratio 1:3:6 And Fabrication of structure Complete. |
| 37 | Dismentaling of 100 KVA T/F & Carriage site to store Please Enable Macros to View BoQ information |