| 1 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 2 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 3 | Additional rate for excavation of Pit for A type pole in Laterite. |
| 4 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 5 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 6 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 7 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 8 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 9 | Additional rate for providing one disc set, PG clamp etc. complete, on any type of HT pole for making cut point. |
| 10 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 11 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 12 | Fitting one Additional V cross arm in existing single pole including conveyance of materials. |
| 13 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 14 | Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 15 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 16 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at standard distance (1.5m) away from the pole/structure in ordinary soil & backfilling the pit with 15cm alternate layer of charcoal, salt and sand up to 90cm from the bottom. including the cost of 20kg salt, 25kg charcoal, excluding supply of earth pipe. |
| 17 | Fitting and providing one HT Fly stay for 11kV pole using A type pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 18 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 19 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Laterite. |
| 20 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 21 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 22 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 23 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 24 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 25 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 26 | Stringing of one km 11kV line with ACSR Raccoon (3 conductors) after fitting insulators and giving jumper connections including cutting and removing tree branches wherever necessary excluding cut point works. |
| 27 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 28 | Fitting one LT 2 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 29 | Fitting one LT 4 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 30 | Fitting and providing one Strut using A type pole, including digging and back filling pit in ordinary soil. |
| 31 | Renewal of existing damaged/old 11kV PSC/RCC DP with new A type DP in place including excavation, erection of new pole, backfilling pit and refitting of all items etc. and conveyance of all materials except poles. |
| 32 | Doing straight joint on HT XLPE UG cables of sizes beyond 3x185 sqmm and upto and including 3x300 sq mm using the cable jointing kit supplied departmentally as per specification after providing proper traffic signalling and caution board fencing etc. wherever necessary, including charges for cable jointer and other sundries etc. as per the direction of departmental officers at site. |
| 33 | Mounting and connecting HT XLPE UG cable ends of all sizes upto and including 3x300 sq mm with special type cable clamps, bolts, nuts, terminal protectors etc.including cost of extra materials if needed and giving necessary jumper connections. |
| 34 | Doing horizontal directional drilling along/ across roads, supplying and pulling 125mm HDPE pipe duct for drawing 11kV 3x300Sq mm Aluminium XLPE UG cable through the duct including surveying the site for collecting information about under ground utility installations and other obstructions using suitable modern sensing equipments, restoring the damages occurred if any, pit marking, pilot drilling, pre raming, closing of pits with normal soil/filled sand/crusher sand and consolidation to the satisfaction of the road owner and traffic police as they insist, taking the cable to the open trenches, RMUs, transformer yards etc., mounting the cable after providing loop at 1.2m depth , putting HDPE (PN-6,Kg/sq mm) at rising point(0.5 m below ground level and 1.5m above ground level) making RCC jointing chambers for straight joints if any, testing commissioning, placing route markers at 100m interval, writing identification name ,date of laying ,date of commissioning etc. legibly on the cable rising using polyurathane paint etc. as per the direction of departmental officers including supply of HDPE pipe. (includes cost of HDPE pipe, labour, transportation charges etc.) |
| 35 | Providing, laying and fixing 150mm dia GI pipe (medium class) in ground complete with GI fittings including trenching (75cm deep) and refilling etc as required. |
| 36 | Doing one cable end termination on HT XLPE UG cables of sizes beyond 3x185 sqmm and upto and including 3x300 sq mm using the cable jointing kit supplied departmentally after making fencing,caution board and all other safety measures including charges for cable jointer etc. complete as per the direction of the departmental officers. |
| 37 | Renewing one damaged PSC/RCC Transformer DP structure with a new A type Transformer DP including excavation, dismantling accessories like AB switch, DO fuse, LA, LT fuses, HT, LT and earth connections, dismantling existing Transformer, keeping it in safe custody and re erecting all accessories including Transformer on the new DP as per standards and drawing sufficient length of GI earthing leads to the ground for earthing, excluding renewal of pipe earthing. |
| 38 | Renewal of existing damaged/old 11kV PSC/RCC Pole with new A type pole in place including excavation, erection of new pole, backfilling pit and refitting of all items etc. and conveyance of all materials except pole. |
| 39 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 40 | Renewal of existing damaged/old 11kV Stay with new stay in place including excavation & backfilling of pit, dismantling, refitting of all items and conveyance of all materials. |
| 41 | Renewal of any type of existing damaged/old 11kV Strut with new A type strut in place including excavation & backfilling of pit, consolidating, dismantling and refitting of all items and conveyance of all materials except pole. |
| 42 | Additional rate for refitting/redoing one Disc set while renewing any type of 11kV cut pole. |
| 43 | Renewing one V Cross arm on the 11kV Pole including dismantling and conveyance. |
| 44 | Renewing one 1.8m Channel cross arm on the 11kV Pole including dismantling and conveyance. |
| 45 | Quoted Amount of BOQ1 in figures |
| 46 | GST Rate in percentage Please Enable Macros to View BoQ information |