| 1 | Dragging, loading, carriage and unloading of following store materials with proper stacking from ESCSitapur to JE dumps store and from JE dump store to work site within Mehmudabad area. |
| 2 | 11 Mtr ST Pole |
| 3 | 8.5 Mtr PCC Pole |
| 4 | ACSR Weasel Conductor |
| 5 | ACSR Rabit Conductor |
| 6 | 11kv X arm |
| 7 | 11 kv pin insulator with pin |
| 8 | 11 kv Disc insulator with fitting |
| 9 | M S Earthing Rod 20x2500 mm |
| 10 | Stay Set 16x1800 Complete |
| 11 | Stay wire 7/10sqmm |
| 12 | Top channel ( 125*65*3200) |
| 13 | Droper Channel(100*50*2500) |
| 14 | T-off Channel (125*65*1300) |
| 15 | Sub Station Base angle(75*75*6) |
| 16 | ABC CABLE 3X120+1X95+1X25 SQMM |
| 17 | ABC CABLE 3X95+1X70+1X16 SQMM |
| 18 | ABC CABLE 1X25+1X16 SQMM |
| 19 | G I wire 10 swg |
| 20 | Errection work |
| 21 | Fabrication & erection of single pole for 11 KV line/LT Line on PCC/STP 8.5/11mtr long Pole with fixing of necessary clamp & other acessories like Channel, cross arm, Fbracket, etc(f bracket, Clamps, Nut bolt Provided by contractor .as per RESPO norms. ( Digram as per tender specification) |
| 22 | Double Pole- Fabrication, erection, of double pole for 11 KV line on 8.5 M long PCC pole with fixing of necessary clamps & other accessories like disc insulator, 1 no. top chennel 65×65 mm - 2.8M,droper chanal 1 no. X bracing,disc fittingits, gaurding angle, 11kv pin with pin insulator,jumpering by PG clamp, complete work ( E Bracket ,Clamps, Nut Bolt & Guy Insulator etc material arranged by contractor).as per RESPO norms. |
| 23 | S/S Type Double Pole- Fabrication, erection, of double pole FOR TRANSFORMER on 8.5/11 M long PCC/ST pole with fixing of necessary clamps & other accessories like disc insulator, top channel 65×65 mm - 2.8M, Dropper Channel TRANSFORMER BASE ANGLE, ,jumpering by PG clamp etc ( E Bracket ,Clamps, Nut Bolt & Guy Insulator etc material arranged by contractor).as per RESPO norms |
| 24 | Laying Stringing & Sagging of ABC CABLE 3X95+1X70+1X25 SQMM as per RESPO Norms(material arranged by contractor Eye Huk Lt clamp, Suspension clamp,Ded End Clamp, Nut Bolt).as per RESPO norms. |
| 25 | Laying Stringing & Sagging of ABC CABLE 3X120+1X95+1X35 SQMM as per RESPO Norms.(material arranged by contractor Eye Huk Lt clamp, Suspension clamp,Ded End Clamp, Nut Bolt).as per RESPO norms. |
| 26 | Laying Stringing & Sagging of ABC CABLE 1X25+1X16 SQMM as per RESPO Norms.(material arranged by contractor Eye Huk Lt clamp, Suspension clamp,Ded End Clamp, Nut Bolt).as per RESPO norms. |
| 27 | Laying Stringing & Sagging of three phase 11 kv line on ACSRWeasel conductor as per RESPO Norms. |
| 28 | Laying Stringing & Sagging of three phase 11 kv line on ACSR Rabit conductor as per RESPO Norms. |
| 29 | Gauarding of O/H Line - Fabrication and fixing of gaurding angle on single/double Poles as per RESSPO Norms including provision of all necessary clamps and hooks.Shifting of existing line conductor of 11 KV/LT lines to maintain proper clearence in between both Lines.and road |
| 30 | Earthing of pole by M.S. Earthing Rod 20x2500mm with GI wire as per Resspo Norms only earting rod provided by deptt. |
| 31 | Painting of new erected 11M long ST poles P O Red & Silver Paint provid by Contractoras per RESPO Norms |
| 32 | Grouting of pole in depth of 1/6 the length of pole in ratio 1:4:8 in cement sand and brick balast as per RESPO norms. |
| 33 | Tree branches cutting and chopping where required |
| 34 | Nozzling, Fixing of stay & Grouting of stay 150mmx150mm (Grouting material provided by contractor) |
| 35 | Dismentaling of HT /LT Line |
| 36 | Safe Carriage of Dismental Line material from work site to ESC, Sitapur Store 0-80 KM with Loading and Unloading Charges. |
| 37 | S/F Reflectors For Every pole With MVVNL 1912 tool free Number |
| 38 | chemical Earthing With Gi strip All material provided by contractor |
| 39 | Dismente and lingInstalation of 16/25/63/100kva Transfarmer |
| 40 | Dismente and lingInstalation of 250 kva Transfarmer |
| 41 | Construction of massonary type T/F plinth of size 2x2x1½ M with fixing of two nos. Channel on the top of the plinth.RCC slab of 4\\" thick on the top of the plinth, plastering outer surface of walls and its proper curing for erection and commissioning of 11/0.4 KV 250 KVA T/F. |
| 42 | Fabrication, erection, grouting, plinthing & painting of wiremesh fencing 3 M height with M.S Angle 50x50x6 and wiremesh 10 SWG. The work also includes making of retaining wall as per norms . Please Enable Macros to View BoQ information |