| 1 | Safe loading Carriage including unloading and proper stacking of following materials from central store Barabanki to site of work. |
| 2 | PCC Pole 11 Mtr |
| 3 | 11/0.4 KV VCB for O/G CTR 200/100/5 A. (350 MVA 1250 AMP |
| 4 | PCC Pole 8.5 Mtr |
| 5 | Earthing Set Complete |
| 6 | 11 KV XLPE Cable 3x185 Sq.mm. |
| 7 | 11 KV 3x185 sqmm XLPE O/D, I/D Cable Box Jointing Kit |
| 8 | ACSR Rabbit Conductor |
| 9 | 11 kv Pin Insulator |
| 10 | 11 kv Pin with Nut |
| 11 | 11 kv Polymer Disk Insulator |
| 12 | 11 kv Disk Fitting |
| 13 | 11 kv 'V' Type Cross Arm |
| 14 | T-off Channel |
| 15 | Stay Set Complete |
| 16 | GI Wire 6/8 SWG |
| 17 | Top Channel |
| 18 | Dropper Channel |
| 19 | Cross Bracing Angle |
| 20 | Guarding Angle With Clamp |
| 21 | F-Bracket |
| 22 | Dragging of pole from JE Dump Store to site |
| 23 | Grouting of Pole in depth of 1/6th the length of pole in ratio 1:4:8 in cement sand and brick ballast and construction of pole plinth 300mmx45mm above ground level in 1:2:4 in cement, coarse sand and stone grit as per respo norms. |
| 24 | Concreating to Stay |
| 25 | Erection of Substation type single pole with PCC 8.5/11 Mtr. Long including mounting of Top Channal, base angle with clamps with nut & bolt 33/11 KV line. |
| 26 | Erection of Substation type Double pole with PCC 8.5/11 Mtr. Long including mounting of Top Channal, base angle with clamps with nut & bolt 33/11 KV line. |
| 27 | Stringing and sagging of 11 KV line with ACSR Rabbit Conductor including nuzzling binding and jumpering (weasal conductor will be provided by the department) |
| 28 | Earthing of pole with MS Earthing. |
| 29 | Fixing of 11/0.4 KV VCB for O/G CTR 200/100/5 A. (350 MVA 1250 AMP |
| 30 | Fixing of 11 KV XLPE 3x185 sqmm O/D, I/D Cable Box Jointing Kit |
| 31 | Providing & Fixing of various type materials. All materials shall be supplied by the contractor. |
| 32 | Nut & Bolt |
| 33 | Holding Clamp for 11 kv 'V' Type Cross Arm with Nut & Bolt |
| 34 | Clamp for Top/T-off/Dropper |
| 35 | Barbed Wire |
| 36 | Stone Pad (300x300x75 MM) |
| 37 | Aluminium binding Wire |
| 38 | Jointing sleave for ACSR Rabbit |
| 39 | Laying of 11 kv XLPE Cable AL. 3x185Sq.MM S/C by HDD(Drill Method) as per Respo Norms.(All the material required for laying will be supplied by the contractor except 11 kV XLPE cable) |
| 40 | Hosting of 11 kv XLPE Cable AL. 3x185Sq.MM on DP with GI pipe 6\\" its Jumpring complete with clamps, nut and bolts. (All material will be Provided by the contractor except 11 kv cable & O/D J/K. as per RESPO NORMS. |
| 41 | Dismantling of 11 kV grade underground XLPE cable of any size (up to 3•185 sq.mm), including excavation of trench, removal of cable carefully without damage, coiling, loading, transportation to departmental store, unloading, stacking and accounting, complete in all respects. |
| 42 | Other line work Please Enable Macros to View BoQ information |