| 1 | Part - A ( Material)Following Material Supplied by the Contractor:- |
| 2 | G.I. Pipe 6'' dia |
| 3 | Stone Pad |
| 4 | G.I. Pipe Clamp 6'' |
| 5 | 11 KV F- Clamp |
| 6 | 11 KV E- Clamp |
| 7 | Nut & Bolt |
| 8 | Carriage including loading,unloading & Proper stacking of following Stock materials from store/departmental store to Dump site distance 0 to 80 Kms. (distance approx) |
| 9 | PCC Pole 11 Mtr. long |
| 10 | PCC Pole 8.5 Mtr. Long |
| 11 | ACSR Weasel Conductor |
| 12 | 11 KV XLPE Cable 3x120 sqmm |
| 13 | 11 KV Out door Cable Jointing kit 3x120 |
| 14 | 11 KV Indoor Cable Jointing kit 3x120 |
| 15 | 11 kv VCB for outgoing CTR 200/100/5 Amp. |
| 16 | Other matching Materials |
| 17 | Dragging of ST/PCC Pole from dump site to pit site |
| 18 | Fabrication and Errection of Double Pole Support on ST/PCC Pole Pole including grouting with 1:4:8 ratio Cement, sand & Brick Ballast& including digging of pit and fixing of all accessories clamp & earthing as per RESPo Norms. (Cost of clamps borne by contractor) |
| 19 | Fabrication and Errection of Single Pole Support on ST/PCC Pole Pole including grouting with 1:4:8 ratio Cement, sand & Brick Ballast& including digging of pit and fixing of all accessories clamp & earthing as per RESPo Norms. (Cost of clamps borne by contractor) |
| 20 | Earthing of Pole as Per RESSPO Norms |
| 21 | Grouting and Binding of Stay in 1:4:8 ratio with cement, sand and brick ballast including cost of all grouting materials as per RESSPO Norms. |
| 22 | Stringing, Sagging, binding and jumpering of ACSR Weasel Conductor as per RESSPO Norms |
| 23 | Laying of 11 KV XLPE Cable 3x120 sqmm underground by HDD (HORIZONTAL DRILL DIRECTION) Method by using suitable HDPE Pipe & HDD Machine Complete in all Respect as per norms. (All the material will be supplied by the contractor except 11 KV XLPE cable. |
| 24 | Laying of underground 11 KV 3x120 sq mm by trunch XLPE Cable in Normal Soil by digging of trench 1050 mm deep, 500 mm wide including supply of required material as fine sand, Ist class bricks as per norms. (All the material will be supplied by the contractor except 11 KV XLPE cable) |
| 25 | Road Restroration Charge Pakka Road Crossing |
| 26 | Road Restroration Charge Foothpath Side |
| 27 | Hanaging, Hosting & clamping of G.I. Pipe, channel, nut & Bolt 3x120 mm2 XLPE 11 KV cable as per RESSPO Norms (cost of all accessories will be borne by contractor) |
| 28 | Installation of Heat Shrinkable Type cable jointing kits Outdoor end Termination suitable for 11 KV XLPE cable 3x120mm2 confirming to IS ESI-09-13-IS-13573 of 1992 amendment I&II VDE-0278 of latest version there of if any. ( Jointing Kit supplied by Dept.) |
| 29 | Installation of Heat Shrinkable Type cable jointing kits indoor end Termination suitable for 11 KV XLPE cable 3x120mm2 confirming to IS ESI-09-13-IS-13573 of 1992 amendment I&II VDE-0278 of latest version there of if any. ( Jointing Kit supplied by Dept.) |
| 30 | Boaring Type Earthing of Pilfer AS Per RESSPO Norm (All Matrial will be Provided by Contractor) |
| 31 | Cutting of Tree Branches way of line |
| 32 | Installation of 11 kv VCB for outgoing CTR 200/100/5 Amp. |
| 33 | Rect Back old and used Materials etc. Including Cable Iron Drum to store. Please Enable Macros to View BoQ information |