| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineerin-charge. All kinds of soil |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge. Ordinary rock |
| 3 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. |
| 4 | Extra rates for quantities of works, executed:In or under water and/or liquid mud, including pumping out water as required Note:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, 0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored. |
| 5 | Open timbering over areas including strutting, shoring etc. complete. (Measurements to be taken of the face area timbered):Depth exceeding 3 m but not exceeding 4.5 m |
| 6 | Extra for planking and strutting in open timbering if required to be left permanently in position. (Face area of the timber permanently left to be measured). |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 8 | 1:2:4 (1 cement : 2 coarse sand (zone-III) derived fromnatural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 9 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Nte: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 1.10 times of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. All works upto plinth level Concrete of M30 grade with minimum cement content of 350 kg /cum |
| 10 | Add for using extra cement in the items of design mix over and above the specified cement content therein. |
| 11 | Extra for laying reinforced cement concrete in or under water and/ or liquid mud, including cost of pumping or bailing out water and removing slush etc., complete. Note:- The quantity will be calculated by multiplying the depth measured from the subsoil water level up to the centre of gravity of the R.C.C. under subsoil water with the quantity of R.C.C. in cubic metre executed under subsoil water. The depth of centre of gravity shall be reckoned correct to 0.1 m. 0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored. No extra payment shall be made for placing reinforcement or centering & shuttering under sub - soil water conditions. |
| 12 | Centering and shuttering including strutting, propping etc. and removal of form work for : Foundations, footings, bases for columns |
| 13 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete |
| 14 | Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 15 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 16 | Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12 (D=100 mm with tolerance of ± 2%) Zinc coated, Mesh wire diameter 3.0 mm, mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @ 3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-charge. |
| 17 | Supplying and Filling of hard stone (for stone pitching) 22.5 cm thick at site |
| 18 | Providing and fixing unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A, including jointing with seal ring conforming to IS : 5382, for weep holes of 100mm dia |
| 19 | Dismantling of existing gabion structures by mechanical means including cutting and removal of GI wire crates, taking out stones and stacking of reusable boulders separately , disposal of unserviceable material within lead of 50 m, including hire charges of machinery, labour, T&P etc. complete, with credit for recovered GI wire scrap. |
| 20 | Deduct input credit of boulders to be derived from dismantlling of existing gabion structure. Total qty of dismantlling of existing gabion structure = 2019.49 Cum , Net Qty of boulders considered as 80% of that Qty, Net Qty of boulders = 1615.59 Cum Note :- The rate of boulders considered same as considered under the item of Gabion filling Please Enable Macros to View BoQ information |