| Sl. No. | Item Description |
| 1 | Dewatering During Construction |
| 2 | Dewatering of Surface Construction Sites including supply, installation and removal of pumping equipment from the site |
| 3 | Surface Excavation |
| 4 | Common excavation |
| 5 | Rock excavation |
| 6 | Control perimeter blasting |
| 7 | Line drilling |
| 8 | Dental Excavation |
| 9 | Minor Excavation |
| 10 | Removal of material arising from overbreak accepted due to geological conditions. |
| 11 | Extra for haulage of excavated material |
| 12 | beyond 3 km and up to 6 km |
| 13 | Not Used |
| 14 | Rock stabilization and Supports |
| 15 | Soil Nailing |
| 16 | Soil Nailing (25mm dia, 4m long)-all including drilling, installation, grouting, tensioning etc. |
| 17 | Rock Bolt 32 mm dia |
| 18 | Length upto 6.0 m |
| 19 | Rock Anchors 32 mm dia |
| 20 | Length upto 6.0 m |
| 21 | Self Drilling Hollow Core Anchors 25 mm dia |
| 22 | Length 6.0 m to 9.0m |
| 23 | Grouted Anchor bar 25 mm dia. |
| 24 | Length upto 6.0 m |
| 25 | Extensions for embedding into concrete where required |
| 26 | Post tensioned Rockbolts (Tendons)(120Ton Capacity) |
| 27 | Mesh reinforcement |
| 28 | wiremesh (Chain link) |
| 29 | welded wiremesh |
| 30 | Shotcrete |
| 31 | Plain Shotcrete |
| 32 | Cement variation in shotcrete |
| 33 | Superplasticiser |
| 34 | Embankment Construction and Backfill |
| 35 | Coffer dyke in 1st & 2nd Stage River Diversion |
| 36 | Random Backfill (Zone 3A) |
| 37 | Compacted Rockfill material (Zone 3B) |
| 38 | Compacted Backfill for rasing bed level in barrage d/s bed protection area & behind toe wall of cladding |
| 39 | Graded filter (Below CC block at u/s & d/s apron) |
| 40 | Drilling, Grouting and Pressure Relief Holes |
| 41 | Drilling for consolidation grouting |
| 42 | Drilling for grout holes 45 mm dia |
| 43 | Placing grout (excluding cement) |
| 44 | Consolidation grouting |
| 45 | Drilling for Pressure Relief holes |
| 46 | Drilling of 45 mm dia hole |
| 47 | Supply and installation of 36 mm dia perforated PVC pipes |
| 48 | Drilling of exploratory holes, check holes and holes for instrumentation |
| 49 | Drilling of 45 dia holes |
| 50 | Drilling of 76 dia holes |
| 51 | Water pressure testing-simple water test |
| 52 | Grouting materials |
| 53 | Cement |
| 54 | Bentonite |
| 55 | Admixtures |
| 56 | Permeation grouting |
| 57 | Permeation grouting under retaining wall (dyke) & Barrage |
| 58 | Permeation grouting trials including reports etc. |
| 59 | Permeation Grout cut-off/curtain complete in all respect including materials, equipment, testing and monitoring etc. |
| 60 | Plastic Diaphragm wall |
| 61 | Excavation of Trench |
| 62 | Plastic concrete (1m thick) including all ingreadients |
| 63 | Concrete in Barrage/Intake str. |
| 64 | Plain Cement Concrete |
| 65 | M10/A20 levelling concrete |
| 66 | M15/A40 Backfill Concrete in surface works at unspecified location |
| 67 | M20A40 CC Blocks, TBM Launching Platform etc. |
| 68 | Non-shrinkage Self Compacting M35/A20 blockout concrete |
| 69 | Reinforced Cement Concrete |
| 70 | RCC M25/A20 in control room, DG room & Power Pack room etc. |
| 71 | RCC M25/A20 for miscellaneous work |
| 72 | RCC M25/A40 in barrage Raft & cutoff wall, toe wall, apron slab, Diversion tunnel Outfall etc |
| 73 | RCC M 30/A20 for bridge |
| 74 | RCC M30A40 in Pier, Trunion beam, Divide wall, Guide wall, counterfort wall, Intake structure incl. deck slab etc |
| 75 | High Performance Concrete |
| 76 | HPC M65/A20 in spillway glacis |
| 77 | Silica fume @ 50 kg/m³ |
| 78 | Superplasticizer for HPC |
| 79 | Cement variation in concrete |
| 80 | Admixtures for concrete |
| 81 | Air-entraining agent |
| 82 | Superplasticizer |
| 83 | Concrete in River Diversion & Protection work |
| 84 | Plain Cement Concrete |
| 85 | M10/A20 levelling concrete, dyke core |
| 86 | M15/A40 Backfill Concrete in surface works at unspecified location |
| 87 | M20/A40 concrete dyke |
| 88 | M20A40 CC Blocks at water face of dyke |
| 89 | Reinforced Cement Concrete |
| 90 | M25/A40 in Retaining wall & Channel lining |
| 91 | Cement variation in concrete |
| 92 | Admixtures for concrete |
| 93 | Air-entraining agent |
| 94 | Superplasticizer |
| 95 | Bridge Ancillaries |
| 96 | Elastomeric bearing |
| 97 | Drain Boxes |
| 98 | Formwork |
| 99 | Barrage |
| 100 | Class F1 |
| 101 | Class F2 |
| 102 | Class F2C |
| 103 | Class F3 |
| 104 | Class F3C |
| 105 | Reinforcing Steel |
| 106 | Deformed Reinforcing bars |
| 107 | Plain reinforcing bars |
| 108 | Couplers |
| 109 | 32 mm dia |
| 110 | Waterstops and joints |
| 111 | P.V.C. water stops |
| 112 | 300 mm wide |
| 113 | 230 mm wide |
| 114 | Joint Sealing Compound |
| 115 | Joint fillers |
| 116 | Metalworks |
| 117 | Railing |
| 118 | SS pipe |
| 119 | GI pipe |
| 120 | Steel pipe hand rail |
| 121 | Ladders |
| 122 | SS Gratings |
| 123 | Climbing irons |
| 124 | Steel pipe of any diameter |
| 125 | Miscellaneous steel sections as edge protection, frames, bearing plates, brackets, etc. of various dimensions, including bolts, screws, anchors, and other accessories for interior and exterior purpose. |
| 126 | Installation of Metal works supplied by other contractor |
| 127 | Steel covers, frames |
| 128 | Not Used |
| 129 | Building and Architectural works |
| 130 | Architectrual design and construction of control room, DG room and power pack room alongwith associated architectural works for barrage complex |
| 131 | Miscellaneous and Ancillary Works |
| 132 | Fencing and gates |
| 133 | Fencing |
| 134 | Gates |
| 135 | Weep holes |
| 136 | PVC Pipes |
| 137 | 36 mm dia |
| 138 | 50 mm dia |
| 139 | 75 mm dia |
| 140 | 100 mm dia |
| 141 | 150 mm dia |
| 142 | 200 mm dia |
| 143 | Slope and river bed protection works |
| 144 | Rock Paving |
| 145 | Stone pitching |
| 146 | Wire crates/ Gabions |
| 147 | Supply of mechanically woven double twisted hexagonal gabions of size 2m x 1m x 1m (Zn coated). |
| 148 | Supply and placing boulders of around 20 kg to 40 kg in weight and 150 mm to 300 mm in size in Boulder Wire Crates |
| 149 | Supply of 9 mm 4-strand Polypropylene (PP) Rope Gabions (UV stabilized size 2m x 1m x 1m). |
| 150 | Supply and placing boulders of around 20 kg to 40 kg in weight and 150 mm to 300 mm in size in PP rope gabion for box barrage protection. |
| 151 | Random Rubble Masonary Wall |
| 152 | Wet R R Masonry |
| 153 | Dry R R Masonry |
| 154 | Terta-pods (5T) |
| 155 | Wattling Trenches |
| 156 | Mulching / Plantation of Grass / Shrubs |
| 157 | Jute Geo-Textiles |
| 158 | Balli Benching |
| 159 | Bamboo Piling |
| 160 | Monitoring Instruments |
| 161 | Instrumentation in Barrage/Power Intake |
| 162 | Load Cells(120 T Capacity) |
| 163 | Survey targets with base plate |
| 164 | Inclinometer |
| 165 | Joint meter |
| 166 | Temperature gauges |
| 167 | Multiple point Bore hole Extensometer |
| 168 | Electrical type |
| 169 | Mechanical type |
| 170 | Uplift measuring device |
| 171 | Piezometer |
| 172 | Automatic water level recorder (AWLR) |
| 173 | Strong motion accelorograph |
| 174 | Automatic weather station |
| 175 | Stress meter/Pressure cell |
| 176 | Strain gauge |
| 177 | water level recorder |
| 178 | water level measuring gauge |
| 179 | Data acquisition system and web based data monitoring |
| 180 | Water Supply & Sewerage |
| 181 | Laying of water G.I. Pipe line with complete fittings, fixing valves, testing and commissioning |
| 182 | 100 mm nominal dia |
| 183 | 75 mm nominal dia |
| 184 | 50 mm nominal dia |
| 185 | 25 mm nominal dia |
| 186 | Supply & installation of pumps 3 H.P capacity for water supply including all electric panels, cables, level switches etc |
| 187 | No. of Operational units |
| 188 | No. of Standby units |
| 189 | Design, supply & installation of Water treatment plant including Sodium hypochlorite dosing unit with complete accessories as specified in Technical specification. |
| 190 | Supply and installation of automatic sewage treatment plant for barrage control room |
| 191 | Laying of HDPE sewage Pipe line including fittings and fixtures |
| 192 | 150 mm nominal dia |
| 193 | 100 mm nominal dia |
| 194 | Design, supply & installation of Pumping unit for sewage system |
| 195 | Electrical and Mechanical works |
| 196 | Illumination system |
| 197 | Drainage pumping system for barrage |
| 198 | Grounding works for barrage and Intake |
| 199 | Road Works |
| 200 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge. |
| 201 | Ordinary Rock (30%) |
| 202 | Hard rock (blasting prohibited) (70%) |
| 203 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. |
| 204 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earthwith lead upto 50 metres. |
| 205 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge With material conforming to Grade-I (size range 75 mm to 0.075 mm) having CBR Value-30 |
| 206 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-ChargeWith material conforming to Grade-II (size range 53 mm to 0.075 mm ) having CBR Value-25 |
| 207 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge With material conforming to Grade-III (size range 26.5 mm to 0.075 mm ) having CBR Value-20 |
| 208 | Supplying, stacking and Spreading 6 mm thick bajri, watering and rolling complete including preparation of the surface and rolling With road roller/ hand roller |
| 209 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads & lifts, laying in uniform layers with mechanical paverfinisher in sub- base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achievethe desired density, complete as per specifications and directions of Engineer-in-Charge |
| 210 | Surface dressing on new surface in two coats with bitumen of grade VG -10 of approved quality using 1.8 kg of bitumen per sqm with 1.5 cum of stone chippings 13.2 mm nominal size per 100 sqm of road surface for first coat and 1.1 kg. of bitumen per sqm with 1.00 cu. metre of stone chippings 11.2 mm nominal size per 100 sqm of road surface for second coat, including consolidation of each coat separately with road roller of 6 to 8 tonne capacity etc. complete. |
| 211 | Providing and laying Bitumen Penetration Macadam with hard stone aggregate of quality, size and grading as specified, with bitumen of suitable penetration grade, including required key aggregate as specified, spreading coarse aggregate with the help of self propelled/ tipper tail mounted aggregate spreader and applying bitumen by a pressure distributor and then spreading key aggregate with the help of aggregate spreader complete, including consolidation with road roller of minimum 8 to 10 tonne capacity to achieve specified values of compaction and surface accuracy : For 50mm compacted thickness using coarse aggregate of size 50-20 mm graded @ 0.60 cum per 10 sqm key aggregate of size 12.5 mm graded @ 0.15 cum per 10 sqm. With paving asphalt grade VG - 10 @50 kg/ 10 sqm. |
| 212 | Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With medium setting bitumen emulsion On W.B.M / W.M.M. @ 0.4kg/sqm |
| 213 | 2.5 cm premix carpet surfacing with 2.25 cum and 1.12 cum of stone chippings of 13.2 mm and 11.2 mm size respectively per 100 sqm and 52 kg and 56 kg of hot bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively, including a tack coat with hot straight run bitumen, including consolidation with road roller of 6 to 9 tonne capacity etc. complete (tack coat to be paid for separately). With paving Asphalt grade VG - 10 heated and then mixed with solvent at the rate of 70 grams per kg of asphalt |
| 214 | 4cm thick bitumastic sheet with hot bitumen of approved quality, using stone chippings (60% with 12.5 mm nominal size and 40% with 10 mm nominal size) @ 2.60 cum per 100 sqm and coarse sand @ 2.60 cum per 100 sqm of road surface and with bitumen @ 56 kg/cum of stone chippings and @ 128 kg/cum of sand over a tack coat with hot straight run bitumen, including consolidation with road roller of 8 to 10 tonne etc.complete. (tack coat to be paid separately) :With paving asphalt grade VG - 30 with no solvent |
| 215 | Centering and shuttering including strutting, propping etc. and removal of form work for : Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 216 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand) : 6 graded stone aggregate 20 mm nominal size) |
| 217 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:3:6 (1 cement : 3 coarse sand) : 6 graded stone aggregate 20 mm nominal size) |
| 218 | U-PVC pipes (working pressure 4 kg / cm²) Single socketed pipe 110 mm dia |
| 219 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level |
| 220 | Providing and laying Non Pressure NP-4 class (Heavy duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. 1800 mm dia RCC pipes (Laying by mannual/ machanical means) |
| 221 | Dewatering During Construction |
| 222 | Dewatering of Underground Construction sites including supply, installation and removal of pumping equipment from the site |
| 223 | Not Used |
| 224 | Underground Excavation |
| 225 | Excavation of all Construction/Access Adits, Gate Operation Chamber, TBM retrieval chamber etc |
| 226 | - Class I, II, & III |
| 227 | - Class IV and V |
| 228 | - By Multiple drifting due to geological reasons |
| 229 | Excavation of all Hydraulic tunnels (Water Diversion Tunnel, Intake Tunnel) |
| 230 | - Class I, II, & III |
| 231 | - Class IV and V |
| 232 | - By Multiple drifting due to geological reasons |
| 233 | Removal of material arising from overbreak accepted due to geological conditions. |
| 234 | Extra for haulage of excavated materials |
| 235 | - Beyond 3 km and upto 6 km |
| 236 | Line drilling |
| 237 | Dental excavation |
| 238 | Common excavation |
| 239 | Excavation by mechanised means |
| 240 | Excavation of vertical intake gate shaft in all classes of rock |
| 241 | Underground Excavation by Tunnel Boring Machine |
| 242 | Water Diversion Tunnel excavation by TBM |
| 243 | - Class I, II, & III |
| 244 | - Class IV and V |
| 245 | Casting of Pre-Cast Segment lining |
| 246 | Transportation and placing of Pre-Cast Segment lining in tunnel |
| 247 | Filling of Pea Gravel and Grouting between Pre-Cast Segment lining and tunnel wall |
| 248 | Rock stabilization and Supports |
| 249 | Expansion shell rockbolts 25 mm dia |
| 250 | - Length upto 4.0 m |
| 251 | - Length more than 4.0 m and upto 6.0 m |
| 252 | Expansion Shell rockbolts 32 mm dia |
| 253 | - Length 6.0 m to 9.0 m |
| 254 | - Length more than 9.0 m and upto 12.0 m |
| 255 | Expansion Shell rockbolts 36 mm dia |
| 256 | - Length 6.0 m to 9.0 m |
| 257 | - Length more than 9.0 m and upto 12.0 m |
| 258 | Resin grouted rockbolts 25 mm dia |
| 259 | Length upto 4.0 m |
| 260 | Length more than 4.0 m and upto 6.0 m |
| 261 | Resin grouted rockbolts 32 mm dia |
| 262 | Length upto 6.0 m |
| 263 | Length more than 6.0 m and upto 9.0 m |
| 264 | Length more than 9.0 m and upto 12.0 m |
| 265 | Resin grouted rockbolts 36 mm dia |
| 266 | Length more than 6.0 m and upto 9.0 m |
| 267 | Length more than 9.0 m and upto 12.0 m |
| 268 | Water expandable friction anchor |
| 269 | - Length 6.0 m |
| 270 | Self drilling rockbolt |
| 271 | - 25 mm dia |
| 272 | - 32 mm dia |
| 273 | Grouted anchor bar |
| 274 | - 25 mm dia Length up to 3m |
| 275 | - 32 mm dia Length up to 5m |
| 276 | Rockbolt testing |
| 277 | Rock Anchor 25 mm dia |
| 278 | Rock Anchor 32 mm dia |
| 279 | Rock Anchor 36 mm dia |
| 280 | Rock bolts/Grouted anchor bar extension into concrete 25 / 32 / 36 mm dia. |
| 281 | Steel ribs, supply and installation (including accessories) |
| 282 | Lattice Girder |
| 283 | Steel lagging supply and installation |
| 284 | Precast concrete lagging |
| 285 | Pregrouting |
| 286 | Drilling for Pregrouting |
| 287 | Drilling 45 mm dia |
| 288 | Drilling 57 mm dia |
| 289 | Grouting Operations |
| 290 | for 45 mm dia |
| 291 | for 57 mm dia |
| 292 | Fore poling 32 mm dia (Drilling & Installation) |
| 293 | - Grouting Operations |
| 294 | Pipe Roofing |
| 295 | Pre-drainage holes |
| 296 | - 45mm dia |
| 297 | - 76mm dia |
| 298 | Mesh reinforcement |
| 299 | -Welded Wiremesh |
| 300 | -Chain link fabric |
| 301 | Shotcrete |
| 302 | Plain Shotcrete |
| 303 | SFR Shotcrete |
| 304 | Cement variation in shotcrete |
| 305 | Superplasticizer |
| 306 | Steel fibre |
| 307 | Micro silica |
| 308 | Not Used |
| 309 | Drilling, Grouting and Pressure Relief Holes |
| 310 | Drilling of 45mm dia Curtain grouting in Tunnel Plugs etc. |
| 311 | - Drilling for curtain grouting |
| 312 | - Re-drilling for curtain grouting( 50% of rate in 7.1.1) |
| 313 | Grouting operations |
| 314 | - Multi Stage Grouting |
| 315 | Drilling of 45 mm dia holes for Contact grouting |
| 316 | - In the Tunnels & tunnel plugs |
| 317 | Grouting operations |
| 318 | - In the Tunnels & tunnel plugs |
| 319 | Drilling of 45 mm dia holes for Consolidation grouting |
| 320 | - In tunnels & tunnel plug |
| 321 | - Re-drilling for Consolidation grouting( 50% of rate of 7.5.1) |
| 322 | Grouting operations |
| 323 | - Single Stage Grouting |
| 324 | - Multi Stage Grouting |
| 325 | Drilling of 45 mm dia holes for Consolidation grouting in TBM excavated tunnel |
| 326 | - In tunnels |
| 327 | - Re-drilling for Consolidation grouting( 50% of rate of 7.7.1) |
| 328 | Grouting operations |
| 329 | - Single Stage Grouting |
| 330 | - Multi Stage Grouting |
| 331 | 45 mm dia pressure relief holes in the tunnels |
| 332 | - Drilling of 45 mm dia hole |
| 333 | - Supply and installation of 36 mm dia perforated PVC pipes |
| 334 | - Supply and installation of drain outlet devices |
| 335 | - Non Return Valve |
| 336 | Drilling of exploratory holes, check holes and holes for instrumentation in tunnels etc. |
| 337 | - 45mm dia holes |
| 338 | - 76mm dia holes |
| 339 | - 98mm dia holes |
| 340 | - Extra for core recovery |
| 341 | Water pressure testing - simple water test |
| 342 | Embedded steel pipes and fittings for grouting left permanently in place |
| 343 | Contact grouting operations ordered by Engineer-in-charge |
| 344 | Fill grouting |
| 345 | - In Temporary drainage system |
| 346 | - In exploratory holes |
| 347 | Grouting materials |
| 348 | - Cement |
| 349 | - Sand |
| 350 | - Bentonite |
| 351 | - Admixtures |
| 352 | - Microfine |
| 353 | - Colloidal Silica |
| 354 | - PU grout |
| 355 | Not Used |
| 356 | Concrete |
| 357 | Concrete lining including formwork in all hydraulic tunnels - Water Diversion Tunnel, Intake Tunnels etc. |
| 358 | Plain Cement Concrete lining |
| 359 | -In Invert (M45/A40) |
| 360 | -In Overt (M45/A40) |
| 361 | -M45/ A40 in Approved Overbreaks (75% of rate in 9.1.1.2) |
| 362 | Reinforced Cement Concrete in Water Diversion Tunnel, Intake Tunnels etc. |
| 363 | -In Invert (M45/A40) |
| 364 | -In Overt (M45/A40) |
| 365 | -M45/ A40 in Approved Overbreaks (75% of rate in 9.1.2..2) |
| 366 | -In Invert (M30/A40) |
| 367 | -In Overt (M30/A40) |
| 368 | -M30/ A40 in Approved Overbreaks (75% of rate in 9.1.3.2) |
| 369 | Concrete lining including formwork in Adits, Gate Operation Chamber etc. |
| 370 | Plain Cement Concrete M20/A40 lining |
| 371 | -In Invert (M20/A40) |
| 372 | -In Overt (M20/A40) |
| 373 | -M20/ A40 in Approved Overbreaks (75% of rate in 9.2.1.2) |
| 374 | Plain Cement Concrete M25/A40 lining |
| 375 | -In Invert |
| 376 | -In Overt |
| 377 | -M25/ A40 in Approved Overbreaks (75% of rate in 9.2.2.2) |
| 378 | Tunnel plugs - M20/ A40 |
| 379 | Reinforced Cement Concrete in tunnel including formwork. |
| 380 | - M25/A40 in lining |
| 381 | - M25/ A40 in Approved Overbreaks (75% of rate in 9.2.4.1) |
| 382 | -M35/A20 self compacting concrete in blockout including formwork |
| 383 | Backfill Concrete in geological approved overbreak in tunnels etc. |
| 384 | - M15/A40 |
| 385 | Concrete M15/A40 at specified Locations |
| 386 | M25/A20 precast concrete including formwork |
| 387 | Cement variation in concrete |
| 388 | Admixtures for concrete |
| 389 | - Air-entraining agent |
| 390 | - Superplasticizer |
| 391 | Formwork - Not Used |
| 392 | Reinforcing Steel |
| 393 | Deformed Reinforcing bars - Grade Fe 500 |
| 394 | Plain reinforcing bars |
| 395 | Couplers |
| 396 | - 32 mm dia |
| 397 | Waterstops and joints - Not Used |
| 398 | Metalworks |
| 399 | Climbing iron |
| 400 | Steel pipe of any dia |
| 401 | Miscellaneous steel sections as edge protection, frames, bearing plates, brackets, etc. of various dimensions, including bolts, screws, anchors, and other accessories for interior and exterior purpose. |
| 402 | Steel covers, frames |
| 403 | Not Used |
| 404 | Not Used |
| 405 | Not Used |
| 406 | Not Used |
| 407 | Monitoring Instruments |
| 408 | Supply, installation and commissioning of monitoring instrument as per Technical Specifications. |
| 409 | Load cells |
| 410 | -50t capacity |
| 411 | Convergence measuring tape |
| 412 | Convergance Bolt |
| 413 | Single point borehole extensometer |
| 414 | - Mechanical type |
| 415 | - Electrical type |
| 416 | Multi point borehole extensometer |
| 417 | - Mechanical type |
| 418 | - Electrical type |
| 419 | Piezometer |
| 420 | Water level measuring gauge (mechanical type) |
| 421 | Seepage measuring system (mechanical type) |
| 422 | Optical targets |
| 423 | 3D Tunnel Seismic Prediction test |
| 424 | Strain Gauge |
| 425 | Not Used |
| 426 | Not Used |
| 427 | Not Used |
| 428 | Spillway Radial Gates & Hydraulic hoists |
| 429 | Radial Gates complete in all respect including stiffener, girders, arms, trunnion, guide rollers etc, as described in technical specifications. |
| 430 | First Stage Embedded Parts for 1.1 as described in technical specifications. |
| 431 | Second Stage Embedded Parts including sill beam, wall plates, hoist supporting structure, trunnion brackets including pin, Dogging etc, as described in technical specifications. |
| 432 | Hydraulic Cylinder complete in all respect including suitable arrangement for gate position indication as described in technical specifications. |
| 433 | Hydraulic Power packs complete in all respect including Piping, Electrical Control Panels etc. for 1.1 |
| 434 | Gasoline engine operated portable power pack unit complete in all respect for 1.1 |
| 435 | Electrically operated portable oil filter unit complete in all respect for online filtering of power pack hydraulic oil. |
| 436 | Low Vacuum dehydration & degasification unit complete in all respect |
| 437 | Contamination checking kits |
| 438 | Mandatory Spare Parts (As per statement-IB) |
| 439 | Spillway Stoplogs and Gantry Crane |
| 440 | Slide type Stoplogs (one set comprising 6 units) as described in technical specifications. |
| 441 | First Stage Embedded Parts as described in technical specifications. |
| 442 | Second Stage Embedded Parts including Dogging arrangement, groove covers for 2.1 as described in technical specifications. |
| 443 | Lifting Beam with automatically engaging and disengaging hooks including probe mechanism etc. as described in technical specifications. |
| 444 | Gantry Crane complete in all respect and control equipment for 2.1 including Rails and fixtures as described in technical specifications. |
| 445 | Storage Grooves with 1st and 2nd Embedded Parts for Stoplogs units. |
| 446 | Mandatory Spare Parts (As per statement 1B) |
| 447 | Intake Trash Racks and Radially Travelling Trash Rack Cleaning Machine |
| 448 | Trash racks for complete intake openings comprising suitable nos. trash rack panels and sizes for Intakes as described in technical specifications. |
| 449 | First stage Embedded parts for 3.1 as described in technical specifications. |
| 450 | Second stage embedded parts including bottom base etc. for 3.1 as described in technical specifications. |
| 451 | Lifting beam with automatically engaging and disengaging hooks for 3.1 as described in technical specifications. |
| 452 | Radially Travelling Trash rack cleaning machine complete in all respect along with bucket, control devices, movable apron devices, rails and fixtures etc, grapple hoist, cable reeling drum along with tool kits etc. as described in technical specifications. |
| 453 | Prime mover operated self-unloading trash disposal vehicle Tipper type (Volume 3.5 m3 (min.) and capacity 5MT (Min.) as described in technical specifications. |
| 454 | Mandatory Spare Parts (As per statement-IB) |
| 455 | Intake Service Gates and Rope Drum Hoists |
| 456 | Intake Service Gate (fixed wheel type) as described in technical specifications. |
| 457 | First Stage Embedded Parts for 4.1 including 500mm dia. Air vent pipe etc as described in technical specifications. |
| 458 | Second Stage Embedded Parts including dogging etc. for 4.1 as described in technical specifications. |
| 459 | Rope drum hoist complete in all respect and control equipment for 4.1 as described in technical specifications. |
| 460 | Common Hoist supporting structure (each common hoist supporting structure accommodating the rope drum hoists of both Intake & Intake Maintenance gate for each intake tunnel) & trestle etc. for 4.1 & 5.1 as described in technical specifications. |
| 461 | Mandatory Spare Parts (As per statement-IB) |
| 462 | Intake Maintenance Gates and Rope Drum Hoists |
| 463 | Intake Maintenance Gate (slide type) as described in technical specifications. |
| 464 | First Stage Embedded Parts for 5.1 as described in technical specifications. |
| 465 | Second Stage Embedded Parts including dogging etc. for 5.1 as described in technical specifications. |
| 466 | Rope drum hoist complete in all respect and control equipment for 5.1 as described in technical specifications |
| 467 | Hoist support structure |
| 468 | Mandatory Spare Parts (As per statement-IB) |
| 469 | Heating Arrangement of Hydromechanical Works |
| 470 | Deicing arrangement for Radial gates as per specification appended with PTS (Particular Technical Specification) |
| 471 | De-icing arrangement for Radial gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 472 | De-icing arrangement for Spillway Stoplogs Embedded Parts as per specification appended with PTS (Particular Technical Specification) |
| 473 | De-icing arrangement for Intake Trash Racks as per specification appended with PTS (Particular Technical Specification) |
| 474 | De-icing arrangement for Intake gates as per specification appended with PTS (Particular Technical Specification) |
| 475 | De-icing arrangement for Intake Embedded parts as as per specification appended with PTS (Particular Technical Specification) |
| 476 | De-icing arrangement for Intake Maintenance gates as per specification appended with PTS (Particular Technical Specification) |
| 477 | De-icing arrangement for Intake Maintenance gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 478 | Instrumentation and Remote-Control System |
| 479 | A). PLC based Remote Control System complete in all respects as described in GTS/PTS |
| 480 | B). Following instruments shall also be provided at their respective locations complete in all respect and are not part of PLC system: - i) Two (2) sets of Differential pressure measurement and indication equipment along with necessary alarms across Intake Trash Racks including guiding pipes. The indication shall be provided at a remote panel mounted in Barrage Control Room. |
| 481 | C) Main distribution board & feeder pillar for all HM equipment’s. |
| 482 | Mandatory Spare Parts (As per statement-IB) |
| 483 | Diesel Generator Set (capacity 500kVA) |
| 484 | Diesel Generator Set complete in all respect with Mounting Frame, acoustic enclosure, Control Panels and Change-over System etc. |
| 485 | Mandatory Spare Parts (As per statement-IB) |
| 486 | Mandatory tools & tackles (As per statement-1A) |
| 487 | Spillway Radial Gates & Hydraulic hoists |
| 488 | Radial Gates complete in all respect including stiffener, girders, arms, trunnion, guide rollers etc, as described in technical specifications. |
| 489 | First Stage Embedded Parts for 1.1 as described in technical specifications. |
| 490 | Second Stage Embedded Parts including sill beam, wall plates, hoist supporting structure, trunnion brackets including pin, Dogging etc, as described in technical specifications. |
| 491 | Hydraulic Cylinder complete in all respect including suitable arrangement for gate position indication as described in technical specifications. |
| 492 | Hydraulic Power packs complete in all respect including Piping, Electrical Control Panels etc. for 1.1 |
| 493 | Gasoline engine operated portable power pack unit complete in all respect for 1.1 |
| 494 | Electrically operated portable oil filter unit complete in all respect for online filtering of power pack hydraulic oil. |
| 495 | Low Vacuum dehydration & degasification unit complete in all respect |
| 496 | Contamination checking kits |
| 497 | Mandatory Spare Parts (As per statement-IB) |
| 498 | Spillway Stoplogs and Gantry Crane |
| 499 | Slide type Stoplogs (one set comprising 6 units) as described in technical specifications. |
| 500 | First Stage Embedded Parts as described in technical specifications. |
| 501 | Second Stage Embedded Parts including Dogging arrangement, groove covers for 2.1 as described in technical specifications. |
| 502 | Lifting Beam with automatically engaging and disengaging hooks including probe mechanism etc. as described in technical specifications. |
| 503 | Gantry Crane complete in all respect and control equipment for 2.1 including Rails and fixtures as described in technical specifications. |
| 504 | Storage Grooves with 1st and 2nd Embedded Parts for Stoplogs units. |
| 505 | Mandatory Spare Parts (As per statement 1B) |
| 506 | Intake Trash Racks and Radially Travelling Trash Rack Cleaning Machine |
| 507 | Trash racks for complete intake openings comprising suitable nos. trash rack panels and sizes for Intakes as described in technical specifications. |
| 508 | First stage Embedded parts for 3.1 as described in technical specifications. |
| 509 | Second stage embedded parts including bottom base etc. for 3.1 as described in technical specifications. |
| 510 | Lifting beam with automatically engaging and disengaging hooks for 3.1 as described in technical specifications. |
| 511 | Radially Travelling Trash rack cleaning machine complete in all respect along with bucket, control devices, movable apron devices, rails and fixtures etc, grapple hoist, cable reeling drum along with tool kits etc. as described in technical specifications. |
| 512 | Prime mover operated self-unloading trash disposal vehicle Tipper type (Volume 3.5 m3 (min.) and capacity 5MT (Min.) as described in technical specifications. |
| 513 | Mandatory Spare Parts (As per statement-IB) |
| 514 | Intake Service Gates and Rope Drum Hoists |
| 515 | Intake Service Gate (fixed wheel type) as described in technical specifications. |
| 516 | First Stage Embedded Parts for 4.1 including 500mm dia. Air vent pipe etc as described in technical specifications. |
| 517 | Second Stage Embedded Parts including dogging etc. for 4.1 as described in technical specifications. |
| 518 | Rope drum hoist complete in all respect and control equipment for 4.1 as described in technical specifications. |
| 519 | Common Hoist supporting structure (each common hoist supporting structure accommodating the rope drum hoists of both Intake & Intake Maintenance gate for each intake tunnel) & trestle etc. for 4.1 & 5.1 as described in technical specifications. |
| 520 | Mandatory Spare Parts (As per statement-IB) |
| 521 | Intake Maintenance Gates and Rope Drum Hoists |
| 522 | Intake Maintenance Gate (slide type) as described in technical specifications. |
| 523 | First Stage Embedded Parts for 5.1 as described in technical specifications. |
| 524 | Second Stage Embedded Parts including dogging etc. for 5.1 as described in technical specifications. |
| 525 | Rope drum hoist complete in all respect and control equipment for 5.1 as described in technical specifications |
| 526 | Hoist support structure |
| 527 | Mandatory Spare Parts (As per statement-IB) |
| 528 | Heating Arrangement of Hydromechanical Works |
| 529 | Deicing arrangement for Radial gates as per specification appended with PTS (Particular Technical Specification) |
| 530 | De-icing arrangement for Radial gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 531 | De-icing arrangement for Spillway Stoplogs Embedded Parts as per specification appended with PTS (Particular Technical Specification) |
| 532 | De-icing arrangement for Intake Trash Racks as per specification appended with PTS (Particular Technical Specification) |
| 533 | De-icing arrangement for Intake gates as per specification appended with PTS (Particular Technical Specification) |
| 534 | De-icing arrangement for Intake Embedded parts as as per specification appended with PTS (Particular Technical Specification) |
| 535 | De-icing arrangement for Intake Maintenance gates as per specification appended with PTS (Particular Technical Specification) |
| 536 | De-icing arrangement for Intake Maintenance gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 537 | Instrumentation and Remote-Control System |
| 538 | A). PLC based Remote Control System complete in all respects as described in GTS/PTS |
| 539 | B). Following instruments shall also be provided at their respective locations complete in all respect and are not part of PLC system: - i) Two (2) sets of Differential pressure measurement and indication equipment along with necessary alarms across Intake Trash Racks including guiding pipes. The indication shall be provided at a remote panel mounted in Barrage Control Room. |
| 540 | C) Main distribution board & feeder pillar for all HM equipment’s. |
| 541 | Mandatory Spare Parts (As per statement-IB) |
| 542 | Diesel Generator Set (capacity 500kVA) |
| 543 | Diesel Generator Set complete in all respect with Mounting Frame, acoustic enclosure, Control Panels and Change-over System etc. |
| 544 | Mandatory Spare Parts (As per statement-IB) |
| 545 | Mandatory tools & tackles (As per statement-1A) |
| 546 | Spillway Radial Gates & Hydraulic hoists |
| 547 | Radial Gates complete in all respect including stiffener, girders, arms, trunnion, guide rollers etc, as described in technical specifications. |
| 548 | First Stage Embedded Parts for 1.1 as described in technical specifications. |
| 549 | Second Stage Embedded Parts including sill beam, wall plates, hoist supporting structure, trunnion brackets including pin, Dogging etc, as described in technical specifications. |
| 550 | Hydraulic Cylinder complete in all respect including suitable arrangement for gate position indication as described in technical specifications. |
| 551 | Hydraulic Power packs complete in all respect including Piping, Electrical Control Panels etc. for 1.1 |
| 552 | Gasoline engine operated portable power pack unit complete in all respect for 1.1 |
| 553 | Electrically operated portable oil filter unit complete in all respect for online filtering of power pack hydraulic oil. |
| 554 | Low Vacuum dehydration & degasification unit complete in all respect |
| 555 | Contamination checking kits |
| 556 | Mandatory Spare Parts (As per statement-IB) |
| 557 | Spillway Stoplogs and Gantry Crane |
| 558 | Slide type Stoplogs (one set comprising 6 units) as described in technical specifications. |
| 559 | First Stage Embedded Parts as described in technical specifications. |
| 560 | Second Stage Embedded Parts including Dogging arrangement, groove covers for 2.1 as described in technical specifications. |
| 561 | Lifting Beam with automatically engaging and disengaging hooks including probe mechanism etc. as described in technical specifications. |
| 562 | Gantry Crane complete in all respect and control equipment for 2.1 including Rails and fixtures as described in technical specifications. |
| 563 | Storage Grooves with 1st and 2nd Embedded Parts for Stoplogs units. |
| 564 | Mandatory Spare Parts (As per statement 1B) |
| 565 | Intake Trash Racks and Radially Travelling Trash Rack Cleaning Machine |
| 566 | Trash racks for complete intake openings comprising suitable nos. trash rack panels and sizes for Intakes as described in technical specifications. |
| 567 | First stage Embedded parts for 3.1 as described in technical specifications. |
| 568 | Second stage embedded parts including bottom base etc. for 3.1 as described in technical specifications. |
| 569 | Lifting beam with automatically engaging and disengaging hooks for 3.1 as described in technical specifications. |
| 570 | Radially Travelling Trash rack cleaning machine complete in all respect along with bucket, control devices, movable apron devices, rails and fixtures etc, grapple hoist, cable reeling drum along with tool kits etc. as described in technical specifications. |
| 571 | Prime mover operated self-unloading trash disposal vehicle Tipper type (Volume 3.5 m3 (min.) and capacity 5MT (Min.) as described in technical specifications. |
| 572 | Mandatory Spare Parts (As per statement-IB) |
| 573 | Intake Service Gates and Rope Drum Hoists |
| 574 | Intake Service Gate (fixed wheel type) as described in technical specifications. |
| 575 | First Stage Embedded Parts for 4.1 including 500mm dia. Air vent pipe etc as described in technical specifications. |
| 576 | Second Stage Embedded Parts including dogging etc. for 4.1 as described in technical specifications. |
| 577 | Rope drum hoist complete in all respect and control equipment for 4.1 as described in technical specifications. |
| 578 | Common Hoist supporting structure (each common hoist supporting structure accommodating the rope drum hoists of both Intake & Intake Maintenance gate for each intake tunnel) & trestle etc. for 4.1 & 5.1 as described in technical specifications. |
| 579 | Mandatory Spare Parts (As per statement-IB) |
| 580 | Intake Maintenance Gates and Rope Drum Hoists |
| 581 | Intake Maintenance Gate (slide type) as described in technical specifications. |
| 582 | First Stage Embedded Parts for 5.1 as described in technical specifications. |
| 583 | Second Stage Embedded Parts including dogging etc. for 5.1 as described in technical specifications. |
| 584 | Rope drum hoist complete in all respect and control equipment for 5.1 as described in technical specifications |
| 585 | Hoist support structure |
| 586 | Mandatory Spare Parts (As per statement-IB) |
| 587 | Heating Arrangement of Hydromechanical Works |
| 588 | Deicing arrangement for Radial gates as per specification appended with PTS (Particular Technical Specification) |
| 589 | De-icing arrangement for Radial gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 590 | De-icing arrangement for Spillway Stoplogs Embedded Parts as per specification appended with PTS (Particular Technical Specification) |
| 591 | De-icing arrangement for Intake Trash Racks as per specification appended with PTS (Particular Technical Specification) |
| 592 | De-icing arrangement for Intake gates as per specification appended with PTS (Particular Technical Specification) |
| 593 | De-icing arrangement for Intake Embedded parts as as per specification appended with PTS (Particular Technical Specification) |
| 594 | De-icing arrangement for Intake Maintenance gates as per specification appended with PTS (Particular Technical Specification) |
| 595 | De-icing arrangement for Intake Maintenance gates Embedded parts as per specification appended with PTS (Particular Technical Specification) |
| 596 | Instrumentation and Remote-Control System |
| 597 | A). PLC based Remote Control System complete in all respects as described in GTS/PTS |
| 598 | B). Following instruments shall also be provided at their respective locations complete in all respect and are not part of PLC system: - i) Two (2) sets of Differential pressure measurement and indication equipment along with necessary alarms across Intake Trash Racks including guiding pipes. The indication shall be provided at a remote panel mounted in Barrage Control Room. |
| 599 | C) Main distribution board & feeder pillar for all HM equipment’s. |
| 600 | Mandatory Spare Parts (As per statement-IB) |
| 601 | Diesel Generator Set (capacity 500kVA) |
| 602 | Diesel Generator Set complete in all respect with Mounting Frame, acoustic enclosure, Control Panels and Change-over System etc. |
| 603 | Mandatory Spare Parts (As per statement-IB) |
| 604 | Mandatory tools & tackles (As per statement-1A) |
| 605 | SUB TOTAL FOR PRICE SCHEDULE-1 |
| 606 | SUB TOTAL FOR PRICE SCHEDULE-2 |
| 607 | SUB TOTAL FOR PRICE SCHEDULE-3 |
| 608 | SUB TOTAL FOR PRICE SCHEDULE-4 |
| 609 | SUB TOTAL FOR PRICE SCHEDULE-5 Please Enable Macros to View BoQ information |
| SR No | FileName | File Description |
| 1 | Click here to download tender document | Tender Documents |
| 2 | Click here to download tender document | Tender Documents |
| 3 | Click here to download tender document | Tender Documents |
| 4 | Click here to download tender document | Tender Documents |
| 5 | Click here to download tender document | Tender Documents |
| 6 | Click here to download tender document | Tender Documents |
| 7 | Click here to download tender document | Tender Documents |
| 8 | Click here to download tender document | Tender Documents |
| 9 | Click here to download tender document | Tender Documents |
| 10 | Click here to download tender document | Tender Documents |
Copyright © 2026 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail