| 1 | Construction of Carpentry with Pottery Work Shop to Aggal (Pudhu Kotagiri) in Kotagiri Municipality |
| 2 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS 20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc., complete. |
| 3 | Plain Cement concrete 1:4:8 (one cement, four sand, eight aggregate) using 40mm gauge hand broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15cm thick and compacted,etc., complete complying with standard specfication. |
| 4 | Plain Cement concrete 1:2:4 (one cement, Two sand, Four aggregate) using 40mm gauge hand broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15cm thick and compacted,etc., complete complying with standard specfication. |
| 5 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation -COLUMN |
| 6 | Grade Beam |
| 7 | Slab and Beam |
| 8 | Supply and fabrication of steel required for all RCC items of works involved in the schedule, cost of steel at site fabrication, labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as as per design given and specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc complete as per standard specification |
| 9 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - |
| 10 | Ground Floor |
| 11 | Brick Work in Cement Mortor 1:5 Mix (one cement, five M-sand) using new best II Class Bricks of size 9 ” x 4 3/8 “x 2 3/4 ” from approved quarry including cost and conveyance of all materials to site. Loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications.Upto Basement |
| 12 | Above Basement |
| 13 | Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Louvered Ventilators of from the profile the size of outer frame 60mm x 58mm and shutter profile size of 60 x 78mm both profiles are reinforced with GI/1mm 125GSM and 100% corrosion free, the profile are multi chambered sections with wall thick of 2mm. The EPDM rubber (black colour) covered with all over the edges of frame and shutter. The corners and joints should be welded and cleaned. Radiations pin headed glass 4mm thick should be provided in the louvers. The window should be fixed to the wall with 100% packing with screws and silicon packing all round the frames. The ventilator should be got approved from the Executive Engineer before use on work |
| 14 | Manufacturing supplying and fixing of MILD STEEL DOOR made out of 50 x 50 x 6 mm M.S angle for outer frame,35 X 35 X 5mm M.S.Angle for outer frame of shutter. The entire shutter area shall be covered with CRC sheets (18 G) with 5Nos, of stiffners using M.S.Flats of size 25 X 6mm at equal intervals horizontally. The corners of the frames and shutter with CRC sheets shall be welded by adopting flash butt welding or any other suitable method. Provision towards 3Nos, of Hinges incase of single shutters / 6Nos,of Hinges incase of Double shutters of 125 X 31 X 1.25mm size placed at appropriate intervals and provisions shall be made for Tower bolts 2Nos, Aldrop 1No. The frame shall be provided with 6Nos,of Hold fast of 200mm length using 50 X 6mm M.S.Flat. The entire frame and shutter shall be provided with one coat of red oxide primer including cost of hold fasts,hinges, locking arrangements, handles wind appliences etc., complete and as directed by the departemental officers. |
| 15 | Manufacturing supplying and fixing of MILD STEEL Window made out of 40 x 40 x 6 mm M.S angle for outer frame, 35 X 35 X 5mm M.S.Angle for outer frame of shutter. The entire shutter area shall be covered with CRC sheets ( 18 G ) with 5Nos,of stiffners using M.S.Flats of size 25 X 6mm at equal intervals horizontally. The corners of the frames and shutter with CRC sheets shall be welded by adopting flash butt welding or any other suitable method. Provision towards 3Nos, of Hinges incase of single shutters / 6Nos,of Hinges incase of Double shutters of 125 X 31 X 1.25mm size placed at appropriate intervals and provisions shall be made for Tower bolts 2Nos, Aldrop 1No. The frame shall be provided with 6Nos,of Hold fast of 200mm length using 50 X 6mm M.S.Flat. The entire frame and shutter shall be provided with one coat of red oxide primer including cost of hold fasts,hinges, locking arrangements, handles wind appliences etc., complete and as directed by the departemental officers. |
| 16 | Special Ceiling Plastering in all floors and finishing the exposed surface of RCC items of work such as slab, beam, sunshade, facia, canopy slab, staircase waist slab, landing slab etc., with cement mortar 1:3 (One cement and three sand) 10mm thick including hacking the surfaces and providing cement mortar nosing, beading for sunshade, staircase, step, landing slab etc., including neat finishing and curing etc.,Complete |
| 17 | Plastering with cement mortar 1:5 (One cement and five sand) 12mm thick in all floors including cost and conveyance of all materials to site etc.,complete as per standard specifications |
| 18 | Dadooing walls with ceramic tiles of sizes 300mm X 450mm X 8mm size of approved make and quality and colour Set in cement mortar 1:2 (One part of Cement and two part of Plastering Sand (P- Sand)) over 10 mm base layer plastering and pointing with white cement neatly as directed. |
| 19 | Paving the floor with design Antiskid ceramic tiles (colour and shade as directed) of size 305 mm x 305mm x 6 mm in all floors over a base layer of cement mortar 1:3 (one cement and three sand ) 20mm thick laid in-situ and pointed with same coloured cement etc, complete as per standard specification. |
| 20 | Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification. |
| 21 | Painting the new iron work with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat and including cost of painting materials, brushes, putty, preparation of surfaces and scaffolding charges etc., complete complying with standard specification and as directed by the departmental officer. |
| 22 | Supplying and fixing in position Indian water closet of size 580 X 440mm, white glazed earthen ware of approved quality with 'P' trap or 'S' trap confirming to IS:2556 - Part XII with sand cushion and forming flooring alround the closet using 40mm broken brick jelly in lime concrete 1:2:5 ( one part of lime, two parts of sand and five parts of brick jelly) 100mm thick and finishing the top to required slope and including giving necessary connection to cast iron soil pipes/ PVC pipes by dismandling brick masonry, reinforced cement concrete roof/floor slab and making good the disturbed portion to original condition without leakage etc., complete complying with standard specifications and as directed by the departmental officers. |
| 23 | Supplying and fixing in position White Glazed European Water Closet of best quality and approved make with 100mm 'P' os 'S'' trap with Double flapped rigit P.V.C. seat cover with C.P. brass hinges with 12.5 litres PVC Low Level Flushing Tank with all internal fittings etc., complete Please Enable Macros to View BoQ information |