| 1 | De Launching 20 Nos. beldar are required 20 days for launching of Pantoon Bridge in proper position and alignment. (30 x 20 ) |
| 2 | 4 No. chowkidar (2 No's Day/Night) for 183 Days (30+31+30+31+31+30) 01.04.26 to 30.09.2027) |
| 3 | 2 Nos. Carpenter are required for 10 days for de-launching of pantoon bridge in proper position and alignment. (Skilled) |
| 4 | 2 Nos. Tractor on hire for carriage of sleepers roadways, planks, wheel, guard pieces, R.S. joists, pins, wire rope etc. for 7 days. |
| 5 | 1 No. J.C.B. on hire for leveling material and carriage of material at Pantoon Bridge site 56 hours. |
| 6 | 1 No.Crane (35 Tonnes) on hire charges for fixing of pantoon bridge for 9 days. |
| 7 | Launching 20 Nos. beldar are required 15 days for launching of Pantoon Bridge in proper position and alignment. (30 x 20 ) |
| 8 | 2 Nos. Carpenter are required for 5 days for launching of pantoon bridge in proper position and alignment as per (CSR L-13) |
| 9 | 2 Nos. Tractor on hire for carriage of sleepers roadways, planks, wheel, guard pieces, R.S. joists, pins, wire rope etc. from Baupr Jadid to Sultanpur store to Bridge side for 5 days. |
| 10 | 1 No. J.C.B. on hire for leveling material and carriage of material at Pantoon Bridge site 56 hours. |
| 11 | 1 No.Crane (35 tonnes) on hire charges for fixing of pantoon bridge for 9 days. |
| 12 | Yearly Maintenance Filling cement bags with sand sewing and laying in position within 30 ms in water including cost of E.C. bag & strings (CSR 23.27) |
| 13 | Sal wood wrought, panelled and fixed in position for decking (CSR 17.6) |
| 14 | G-I wire 8 Nos. (SWG) for tightening and anchoring RCC block at river bridge and for binding the pantoon (Railing /Wheel kerbs) |
| 15 | Collection of 1-1/2\\" dia Nariyal Rope on both sides of the bridge. |
| 16 | Supply of Iron Gullas and key L/s |
| 17 | Supply of Nuts and Bolts |
| 18 | Supply of wahers size 3\\"x5\\" complete |
| 19 | 4 Nos. Chowkidar for 182 days(30+31+30+31+31+30)(01-04-2026 to 30.09.2027) |
| 20 | Coolection of Wire Rope 40mm dia for both sides for Main tanchoring of Pantoon. |
| 21 | Collection of concrete anchors on both sides of Pantoons |
| 22 | Collection of Iron Clamps for anchoring of wire rope including concrete |
| 23 | Yearly Maintenance Reflective tape (Red Black Yellow = 110 mtr. each) |
| 24 | Repair & painting to the vertical steel railing L/S |
| 25 | Credit of wooden sleeper removed from bridge being damaged. Please Enable Macros to View BoQ information |