| 1 | fo|qr uxjh; forj.k [k.M&Jh xksj[kukFk] xksj[kiqj ds vUrxZr fctusl Iyku 2026&27 esa Lohd`r ttZj ,0ch0 dscyksa dks cnyus ds dk;ksZ dks djkus gsrq dk;Z dk fooj.k |
| 2 | Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :- |
| 3 | LT AB Cable (3X120+1X95+1X16) sq mm |
| 4 | PCC Pole 8.5 Mtr |
| 5 | Earthing complete |
| 6 | Supply of following material/fitting complete in all respect :- |
| 7 | LT Cable 1X35 sq mm |
| 8 | GI Nuts & bolts of different sizes |
| 9 | LT pole Clamp with nuts & bolts |
| 10 | LT Three Phase Distribution box |
| 11 | Clamp for LT Three Phase DB Box |
| 12 | Suspension Clamp with I hook (Insulated) |
| 13 | Dead end Clamp with I hook (Insulated) |
| 14 | Piercing Connector (Insulated) |
| 15 | The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of PCC Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/PCC/LT clamp, insulator, Nuts & Bolts off size etc will be provided by the contractor.Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).All work will be done as per RESPO norms & relevent IS Specification. |
| 16 | Earthing of PCC Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms. |
| 17 | Dismentling & Carriage of Old Line including Pole |
| 18 | Laying, stringing and sagging of LT ABC (3×120 + 1×95 + 1×16 Sq.mm) cable complete with Distribution Box, clamps, piercing connectors, XLPE cable for energizing/street light, consumer disconnection & reconnection, nuts & bolts and accessories as per RESPO norms and relevant IS specifications |
| 19 | fo|qr uxjh; forj.k [k.M&Jh xksj[kukFk] xksj[kiqj ds vUrxZr fctusl Iyku 2026&27 esa Lohd`r ttZj ,y0Vh0 ds iksyksa dks cnyus ds dk;ksZ dks djkus gsrq dk;Z dk fooj.k |
| 20 | Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :- |
| 21 | ST Pole 9 mtr Long |
| 22 | Earthing complete |
| 23 | Supply of following material/fitting complete in all respect :- |
| 24 | Nuts & bolts of different sizes |
| 25 | LT pole Clamp with nuts & bolts |
| 26 | Suspension Clamp with I hook (Insulated) |
| 27 | Dead end Clamp with I hook (Insulated) |
| 28 | The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of ST Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/STP/LT clamp, F-Bracket, LT shackle insulator, Nuts & Bolts off size etc will be provided by the contractor.Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).including re-sagging of conductors wherever requiredIn case of ST Pole making Plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification. |
| 29 | Earthing of PCC Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms. |
| 30 | Painting of ST Poles with material |
| 31 | Dismentling & Carriage of Old Line including Pole |
| 32 | fo|qr uxjh; forj.k [k.M&Jh xksj[kukFk] xksj[kiqj ds vUrxZr fctusl Iyku 2026&27 esa Lohd`r cl diyj dks cnyus ds dk;ksZ dks djkus gsrq dk;Z dk fooj.k |
| 33 | Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :- |
| 34 | 11 kV Bus Coupler 350 MVA |
| 35 | Fabrication, erection, testing and commissioning of 11 kV Bus Coupler complete with all accessories, fittings, connections and earthing arrangement in all respect as per RESPO norms and relevant IS specifications Please Enable Macros to View BoQ information |