| 1 | Supply and ererction of following Material |
| 2 | Armoured Copper control cable 4C X 2.5 sqmm |
| 3 | Armoured Copper control cable 6C X 2.5 sqmm |
| 4 | Clamps for 33 KV VCB |
| 5 | M.S. Flat 50x6 mm |
| 6 | GI Nut Bolts |
| 7 | 11 KV holding clamp |
| 8 | F clamp |
| 9 | Safe Loading carriage & unloading of following material from store centre to pit site/JE Dump store |
| 10 | PCC pole 8.5 mtr long |
| 11 | 11 KV Pin Insulator with GI pin |
| 12 | 11 KV Disk Insulator with Fitting |
| 13 | ACSR Weasel Conductor |
| 14 | Earthing Complete |
| 15 | Dropper Channel |
| 16 | Stay Complete |
| 17 | GI wire |
| 18 | 11 KV XLPE Cable 3x185 |
| 19 | 11 KV Jointing Kit 3x185 Out Door |
| 20 | 11 KV Jointing Kit 3x185 Out Door |
| 21 | 11 KV VCB For O/G CTR 200/100/5A 350 MVA |
| 22 | 33 KV VCB complete 1250 Amp. (OD) IS 13118 (IEC 62271-100/200) |
| 23 | ABC (3x95+1x70+1x16) sq mm |
| 24 | ABC (3x120+1x95+1x16) sq mm |
| 25 | 11 KV X arm |
| 26 | T-OFF channel |
| 27 | Top Channel |
| 28 | Substiation base angle |
| 29 | Erection of above material that is carriage from store center to site |
| 30 | Erection of Single PCC 8.5 mtr long Pole with all accessories (All neceassry decentralized material shall be supplier by the contractor expect pole) |
| 31 | Concreting of PCC 8.5 mtr single and double pole. |
| 32 | Erection of PCC 8.5 mtr long double pole with all accessories (All neceassry decentralized material shall be supplier by the contractor expect pole) |
| 33 | Fixing of 11 KV Pin Insulator with GI pin |
| 34 | Fixing of 11 KV Disk Insulator with Fitting |
| 35 | Fixing of Dropper Channel |
| 36 | Proper use of GI wire |
| 37 | Fixing of 11 KV X arm |
| 38 | Fixing of T-off channel |
| 39 | Fixing of top channel |
| 40 | Fixing of Substation base angle |
| 41 | Grouting and Nuzzling of 11 KV stay set complete including fixing of necessary clamps. Accessories 15 required including its grouting by civil material (sand, brick blast & cement). All material except stay wire shall be supplied by the contractor. |
| 42 | Stay concreting |
| 43 | Ordinary Earthing by 11 KV MS earth Rod 2500 mm per RESPO schedule. |
| 44 | 11 kv XLPE 3x185 sq mm cable Laying work( in preformed trench depending upon the site conditon necessary change) in swichyard and control room |
| 45 | Installation, Fixing of 11 kv O/G VCB Pannel CTR 200/100/5A (rating may vary depending upon the material availability (all Materail like control Cable , HT Tape,t&p ,Lugs wiring and other as required arranged by the contractor except VCB Pannel |
| 46 | Installation, Fixing of 33 KV VCB complete 1250 Amp. (OD) IS 13118 (IEC 62271-100/200) rating may vary depending upon the material availability (all Materail like control Cable , HT Tape,t&p ,Lugs wiring and other as required arranged by the contractor except VCB Pannel) |
| 47 | Stringing & Sagging of ACSR weasel conductor on 11 KV line |
| 48 | Laying of cable 1x185 sqmm including sands and bricks with making box type cable trench |
| 49 | Modification of 33 KV VCB Foundation as per drawing |
| 50 | Boring type earthing with 20 mtr deep or up to water level providing GI pipe 1.5'' dia (''B'' Class) and earthing must be joint in T/F body, netural & Fuse unit by GI Stripe of size 32×5 mm thick long attached with nut & bolts and GI pipe cap (All the material will be arranged by the contractor at his own cost.) |
| 51 | Tree Cutting Please Enable Macros to View BoQ information |