| 1 | Part-A (Material Provided by Contractor) Vikasnagar |
| 2 | 33 KV Feeder Pillar Box |
| 3 | 33 KV ‘XLPE’ C/J Kit 3x300mm² Outdoor |
| 4 | 33 KV ‘XLPE’ C/J Kit 3x300mm² Straight Through |
| 5 | M S Dropper Angle |
| 6 | M S Holding Clamp for STP Support |
| 7 | Nut Bolt and washer all sizes |
| 8 | Number Plate with clamp and Nut & Bolt |
| 9 | Danger Board with clamp and Nut & Bolt |
| 10 | Barbed Wire |
| 11 | Red Oxide Paint |
| 12 | Aluminium Paint |
| 13 | Earthing Complete (Per set =01 No Earthing Rod + 2Kg GI Wire) |
| 14 | GI Pipe 6\\" Dia |
| 15 | HDPE Pipe 160 mm |
| 16 | 33 KV Polymer Disc Insulator |
| 17 | 33 KV Disc Fitting |
| 18 | PG CLAMP For Dog |
| 19 | 33 KV Stay Set Complete |
| 20 | Armoured copper control cable 2 x 2.5 mm2 |
| 21 | Armoured copper control cable 4 x 2.5 mm2 |
| 22 | PART – B- WORKShifting, Loading Carriage & Unloading of following materials from store centre Gorakhpur to work site. |
| 23 | ST Pole 11 m |
| 24 | ST Pole 9 m |
| 25 | 33 KV 3x300 XLPE Cable |
| 26 | 33 KV Line Isolator |
| 27 | 33 KV Line Isolator structure |
| 28 | 33 KV CT 400/200/1A |
| 29 | 33 KV CT Structure |
| 30 | 33 KV LA |
| 31 | 33 KV LA Structure |
| 32 | 33 KV VCB with structure |
| 33 | 33 KV Control pannel for single feeder |
| 34 | 33 KV Top Channel |
| 35 | ACSR Dog conductor |
| 36 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable in cable trench. As per site requirement |
| 37 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable by HDD mathod OR laying along with cast of digging, bricks & sand. As per site requirement |
| 38 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable by HDD mathed With HDPE Pipe/CI Pipe For Railway Crossing. As per site requirement |
| 39 | Jointing charge of 33 KV ‘XLPE’ C/J Kit 3x300 mm² Outdoor/Indoor |
| 40 | Jointing charge of 33 KV ‘XLPE’ C/J Kit 3x300 mm² Straight Through |
| 41 | Looping and rising of 33 KV ‘XLPE’ cable in air in 6” dia. GI pipe 3m long with cable clamp, GI Pipe clamp Complete work. |
| 42 | Road Restoration Charges (Pakka Road) during cable laying and road cutting. |
| 43 | Making plinth for installation of feeder pillar box |
| 44 | Installation of 33 KV Feeder Pillar Box with complete wiring and earthing complete work |
| 45 | Special pipe earthing with material for cable and kit protection |
| 46 | Erection of Double pole structure on 9 mtr ST Pole for Cable rising with fitting of all accessories, Painting, Earthing Complete Work |
| 47 | Erection of Double pole structure on 11 mtr ST Pole for one side OH Line one side Cable rising with fitting of all accessories, Painting, Earthing Complete Work |
| 48 | Concreting of pole and making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40mm stone ballast), back filling of earth, proper ramming. (as per UPPCL Norms) |
| 49 | Erection and grouting of Line Isolator Structure and install Line Isolator and earthing, Painting complete work. |
| 50 | Erection and grouting of CT Structure and installation of 33 KV CT, wiring and earthing,Painting complete work. |
| 51 | Erection and grouting of LA Structure and installation of 33 KV LA and earthing, Painting complete work. |
| 52 | Erection and grouting of VCB Structure and installation of 33 KV VCB, wiring and earthing complete work. |
| 53 | Installation of 33 KV CR Pannel, wiring and earthing complete work. |
| 54 | Laying from switchyard to control room for 33 KV panel, CT, VCB by digging trench and making connection complete. (As per site requirement laying of cable though cable trench if available with covering brick and sand. |
| 55 | 2 x 2.5 mm2 |
| 56 | 4 x 2.5 mm2 |
| 57 | Grouting of stay rods including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40 mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening & nozzling of stay wire with stay rod with the poles of required tension. |
| 58 | Part-A (Material Provided by Contractor) Surya Hotel |
| 59 | 33 KV ‘XLPE’ C/J Kit 3x300mm² Outdoor |
| 60 | 33 KV ‘XLPE’ C/J Kit 3x300mm² Straight Through |
| 61 | M S Dropper Angle |
| 62 | M S Holding Clamp for STP Support |
| 63 | Nut Bolt and washer all sizes |
| 64 | Number Plate with clamp and Nut & Bolt |
| 65 | Danger Board with clamp and Nut & Bolt |
| 66 | Barbed Wire |
| 67 | Red Oxide Paint |
| 68 | Aluminium Paint |
| 69 | Earthing Complete (Per set =01 No Earthing Rod + 2Kg GI Wire) |
| 70 | GI Pipe 6\\" Dia |
| 71 | PART – B- WORKShifting, Loading Carriage & Unloading of following materials from store centre Gorakhpur to work site. |
| 72 | ST Pole 9 m |
| 73 | 33 KV 3x300 XLPE Cable |
| 74 | 33 KV Top Channel |
| 75 | ACSR Dog conductor |
| 76 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable by HDD mathod OR Laying along with cast of digging,bricks & sand. As per site requirement |
| 77 | Jointing charge of 33 KV ‘XLPE’ C/J Kit 3x300 mm² Outdoor/Indoor |
| 78 | Jointing charge of 33 KV ‘XLPE’ C/J Kit 3x300 mm² Straight Through |
| 79 | Looping and Rising of 33 KV ‘XLPE’ cable in air in 6” dia. GI pipe 3m long with cable clamp, GI Pipe clamp Complete work. |
| 80 | Road Restoration Charges (Pakka Road) during cable laying and road cutting. |
| 81 | Special pipe earthing with material for cable and kit protection |
| 82 | Erection of Double pole structure on 9 mtr ST Pole for Cable rising with fitting of all accessories, Painting, Earthing Complete Work |
| 83 | Concreting of pole and making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40mm stone ballast), back filling of earth, proper ramming. (as per UPPCL Norms) Please Enable Macros to View BoQ information |