| 1 | 11 KV feeder Strengthening work under Sub Station EDD I Maharajganj Business Plan 2026-27 |
| 2 | Safe Loading, Carriage & Unloading of P.C.C. POLE 8.5 Mtr From Electricity Store Center Maharajganj to Work Site. |
| 3 | Safe Loading, Carriage & Unloading of A.C.S.R. WEASEL CONDUCTOR From Electricity Store Center Maharajganj to Work Site. |
| 4 | Safe Loading, Carriage & Unloading of 11 KV V TYPE STEEEL CROSS ARM From Electricity Store Center Maharajganj to Work Site. |
| 5 | Safe Loading, Carriage & Unloading of 11KV COMPOSIT POLYMER PIN INSULATOR From Electricity Store Center Maharajganj to Work Site. |
| 6 | Safe Loading, Carriage & Unloading of 11KV COMPOSIT POLYMER DISC INSULATOR From Electricity Store Center Maharajganj to Work Site. |
| 7 | Safe Loading, Carriage & Unloading of Stay Set Complete From Electricity Store Center Maharajganj to Work Site. |
| 8 | Safe Loading, Carriage & Unloading of Earthing Complete From Electricity Store Center Maharajganj to Work Site. |
| 9 | Providing and Installation of CROSS ARM HOLDING CLAMP |
| 10 | Providing and Installation of F - Braket with Clamp |
| 11 | Providing and Installation of Stone pad |
| 12 | Providing and Installation of Nut and Bolt |
| 13 | The Excavation of Foundation Pit in Mix Soil/ Normal Soil/ Soft soil &hard rock as per site condition and its back filling and leveling etc. The size of the pit will be (750 X 450) mm and having depth of 1/6 of the full length of the support of PCC Pole (8.5 Mtr Long) as per drawing. |
| 14 | Erection of 8.5 mtr Single PCC Pole with all accessories (Cross arm, 11KV Pin insulator with pin, Disc Insulator, F-bracket etc.) as per specification. |
| 15 | Grouting of 8.5 mtr PCC Pole With Material as per specification. |
| 16 | Laying sagging and binding of of ACSR Weasel Conductor on eracted pole |
| 17 | Intallation of Stay set complete as per specification |
| 18 | Concreting of stay set as per specification |
| 19 | Earthing Complete of 8.5 Mtr PCC Pole as per specification. |
| 20 | Carriage of Dismentalled Material from work site to store centre Maharajganj Please Enable Macros to View BoQ information |