| 1 | Kunnnumal road |
| 2 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 3 | 4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) (A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (i) For Grading I Material |
| 4 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
| 5 | OD385466/2025-2026:Providing and fixing Granite of any colour and shade for Name board, of required size laid overbase of cement mortar 1:4 ( 1 cement : 4 coarse sand), including all charges etc. complete at all,levels, including lettering & fixing |
| 6 | Kizhakkumuri road |
| 7 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 8 | 4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) (A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (i) For Grading I Material |
| 9 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
| 10 | OD385465/2025-2026:Providing and fixing Granite of any colour and shade for Name board, of required size laid overbase of cement mortar 1:4 ( 1 cement : 4 coarse sand), including all charges etc. complete at all,levels, including lettering & fixing |
| 11 | METRO Nagar pockt road |
| 12 | 3.5.2:Excavation in Soil with Dozer with lead upto 100 m Excavation for roadway in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 m, including trimming bottom and side slopes in accordance with requirements of lines, grades and cross-sections. |
| 13 | 4.1.A.1:Granular Sub-base with Well Graded Material (Table 400.1) (A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (i) For Grading I Material |
| 14 | 75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification(i) Nominal mix (1:2:4) |
| 15 | OD385467/2025-2026:Providing and fixing Granite of any colour and shade for Name board, of required size laid overbase of cement mortar 1:4 ( 1 cement : 4 coarse sand), including all charges etc. complete at all,levels, including lettering & fixing |
| 16 | Metro nagar road hand rail |
| 17 | 4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 18 | 5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 19 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 20 | 10.25.2:Item Shifted to Sub head 14 as item 14.73Item Shifted to head 14 as item 14.74Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 21 | EXCLUSIVE OF GST |
| 22 | Note :1 All materials, Items, Equipment shall be best branded items with IS and approved by client/KEL |
| 23 | 2:Rate should be inclusive of Insurance,Transportation, delivery and installation cost for all items |
| 24 | 3.Rate should be Exclusive of GST. |
| 25 | 4.Work should be executed as per DSR/PWD specification and direction of Engineer at site. |
| 26 | 5.CEMENT: Make use Malabar cement only as per Govt. direction and in case of non availabilty of Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference. |
| 27 | 6.RCC: (Assessment of strength of concrete by Cube testing at Approved Govt labs as per IS) Cement make: Use Malabar cement only as per Govt. direction and in case of non availabilty of |
| 28 | Malabar cement use Ultra Tech, Dalmia, Ramco or eq. brand in the order of preference. |
| 29 | 7.STEEL REINFORCEMENT: Make: Tata,Vaishak, SAIL, JSW or eq primary make in the order of preference |
| 30 | 8.CENTERING & SHUTTERING: (Centering and shuttering for different category of work may be considered separately.) |
| 31 | 9. ACRYLIC SMOOTH EXTERIOR PAINT/ SYNTHETIC ENAMEL PAINT/WHITE CEMENT BASEDPUTTY/ CEMENT PRIMER: Make: Asian, Berger, Nerolas or eq. in the order of pref. |
| 32 | 10.GRANULAR SUB BASE: Quantity by level calculation & reporting to CTE as per norms Please Enable Macros to View BoQ information |