|
| 1 | DP Without AB Switch ( 55 Sq MM AAAC):- WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 2 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 2.3 mtr., 2 no's Channel(GI) required =( 2x9.56x2.3) |
| 3 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 4 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 1.66 Mtr., 4 no's Channel(GI) required =( 7.14x1.66x4) |
| 5 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 2.671 mtr., 4 nos Angle(GI) required = (4.5x2.671x4) |
| 6 | Danger Plate, 2 no's. |
| 7 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 8 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 9 | H.T. Stay set (Complete ) |
| 10 | H.T. Stay Insulator Type-C |
| 11 | 7/10 SWG Stay Wire 15kg /stay |
| 12 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 13 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 5x2.36 |
| 14 | GI barbed wire anticlimbing device 3 Kg. Per support, 2 no's qty. required =(2x3kg) |
| 15 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 16 | 11 KV pin insulator polymer |
| 17 | H W fitting(B&S) 70KN, 3Bolt |
| 18 | Disc insulator (B&S) 70 KN polymer |
| 19 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 20 | POLYCARBONATE BIRD GUARD |
| 21 | GI Nut , Bolt & Washer of different sizes (12.261 Kg each DP without AB Switch) |
| 22 | Black Paint(GIS Numbering & Zebra Stripping) |
| 23 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 24 | DP With AB Switch (55 Sq MM AAAC):- WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 25 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 3 mtr., 2 no's Channel(GI) required =( 2x9.56x3) |
| 26 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 27 | AB switch Mounting Channel(GI) 75X40X4.8mm, 7.14KG/Mtr, each Channel(GI) length 3 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 28 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 29 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 30 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 4 no's Channel(GI) required =( 7.14x3x4) |
| 31 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 4 nos Angle(GI) required = (4.5x3.512x4) |
| 32 | Danger Plate, 2 no's. |
| 33 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 34 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 35 | H.T. Stay set (Complete ) |
| 36 | H.T. Stay Insulator Type-C |
| 37 | 7/10 SWG Stay Wire 15kg /stay |
| 38 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 39 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (12.5 Mtr. For L.A, 3 Mtr for AB Switch Body, 2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 20.5x2.36 |
| 40 | GI barbed wire anticlimbing device 3 Kg. Per support, 2 no's qty. required =(2x3kg) |
| 41 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 42 | Lightning Arrester(12KV,10KA) (Station Class,class-2) |
| 43 | AB Switch (11KV,400A.3pole,50Hz) |
| 44 | 11 KV pin insulator polymer |
| 45 | H W fitting(B&S) 70KN, 3Bolt |
| 46 | Disc insulator (B&S) 70 KN polymer |
| 47 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 48 | POLYCARBONATE BIRD GUARD |
| 49 | GI Nut , Bolt & Washer of different sizes (13.718 Kg each DP with AB Switch) |
| 50 | Black Paint(GIS Numbering & Zebra Stripping) |
| 51 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 52 | 11 KV Cut Point with 90 Degree Angle (55 Sq MM AAAC):- WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 53 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 4 no's Channel(GI) required =( 4x9.56x1.2) |
| 54 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 55 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 4 no's Channel(GI) required =( 4x9.56x0.306) |
| 56 | Danger Plate, 1 no's. |
| 57 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 58 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 59 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 60 | 11 KV pin insulator polymer |
| 61 | H W fitting(B&S) 70KN, 3Bolt |
| 62 | Disc insulator (B&S) 70 KN polymer |
| 63 | Earthing of Support ( Coil Type ) |
| 64 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 65 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 66 | POLYCARBONATE BIRD GUARD |
| 67 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 68 | H.T. Stay set (Complete ) |
| 69 | H.T. Stay Insulator Type-C |
| 70 | 7/10 SWG Stay Wire 15kg /stay |
| 71 | GI Nut , Bolt & Washer of different sizes (7.433 Kg each Cut Pole) |
| 72 | Black Paint(GIS Numbering & Zebra Stripping) |
| 73 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 74 | 55 sq.mm AAA conductor |
| 75 | 11 KV Road crossing:- Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 3.5 mtr., 4 no's Channel(GI) required =( 4x7.14x3.5) ( For Double Pole) |
| 76 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 77 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 78 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 79 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 80 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 81 | Civil and Services Works:- Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 82 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 83 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 84 | Provide necessary civil material for construction of Earthing chamber, excavation & installation of incuding earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power , connection & welding with incoming earth Flat(GI). The work to be executed as per TPCODL drawing & design |
| 85 | 100 KVA DP Mounted DSS:- WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 86 | 9 Mtr. long 300 Kg. PSC Pole |
| 87 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 88 | EYE hook for XLPE Aerial bunched Cable |
| 89 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 90 | LT Cable raising Channel(GI) 75x40x4.8 mm GI Channel(GI) (1000 mm long)(7.14Kg./Mtr., 3 No's.) (Each 3x1.000x7.14= 21.42 Kg) |
| 91 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 92 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 93 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 94 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 95 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 96 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 97 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 98 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 99 | Transformer Base GI Channel(GI) 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 100 | Transformer Base Support GI Channel(GI) 100 X 50 X 6 MM (515 mm long) (9.56Kg./Mtr, 2 No's) (Each 2x0.515x9.56= 9.85Kg) |
| 101 | Transformer Belting Angle(GI) 50 X 50 X 6MM GI (3000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x3.0x4.5 Kg) |
| 102 | Transformer Belting Support Angle(GI) 50 X 50 X 6MM GI (580 mm long)(4.5Kg./Mtr,2 No's) (Each 2x0.580x4.5= Kg) |
| 103 | LTDB Mounting Angle(GI) 50 X 50 X 6MM GI (1000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x1x4.5 Kg) |
| 104 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 105 | LT Distribution Box with MCCB, Aluminium Busbar of 2 Bay with kit kat fuse for 100 KVA S/S |
| 106 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 107 | 4 Cx 150 mm2 LT XLPE Cable(Armoured) - FOR 100 KVA Trf. |
| 108 | 1.1kV, 4Core, 150 sqmm, XLPE insulation armoured -Aluminium UG cable from LTDB to Pole |
| 109 | AB Switch(11KV,200A.3pole,50Hz) |
| 110 | D O.Fuse( 11KV.200A.3Pole) |
| 111 | 10 AMP Fuse link |
| 112 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 113 | POLYCARBONATE BIRD GUARD |
| 114 | Disc insulator (B&S)70 KN polymer |
| 115 | H W fitting (B&S)70KN(3bolted) |
| 116 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 117 | 11KV pin insulator polymer |
| 118 | HT stay set complete |
| 119 | HT stay Clamp (1.9Kg/pair) |
| 120 | HT stay insulator TYPE-C |
| 121 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 122 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 123 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 124 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 125 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 126 | Danger plate 11kv |
| 127 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 128 | Name plate |
| 129 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 130 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 131 | Civil and Services Works for 100 KVA DP Mounted DSS:- Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 132 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 133 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (5X3X0.1)= 1.5 Cu. mtr. |
| 134 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 135 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earthresistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 136 | Laying of 4 Cx 150 mm2 LT XLPE Cable |
| 137 | SITC and Erection of GI Fencing with Gate |
| 138 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) (For PSC Pole) |
| 139 | Supply of AL Lugs suitable for 150 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 140 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 120-185sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 141 | 9 Mtr. long 300 Kg. PSC Pole |
| 142 | LT Line ( 50 Sq MM & 35 Sq MM):- WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.) -DP ( Total Pole Weight with Base Plate & Stiffner = 334.84 Kg + 10.74 Kg = 345.58 Kg) |
| 143 | LT Stay set Complete |
| 144 | 7/12 SWG GI stay wire, Grade -2 |
| 145 | LT stay Clamp ( 1.40Kg/pair) |
| 146 | LT Stay insulator |
| 147 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 148 | EYE hook for XLPE Aerial bunched Cable |
| 149 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 150 | Suspension Clamp with EYE hook for ABC |
| 151 | 2X35 + 1X25 (LT AB Cable) |
| 152 | 4C×50 mm² (P)+1C×50 mm²(M)+1CX16 mm²(Street Light) (LT AB Cable) |
| 153 | 4 WAY SERVICE Distb. Box with kit kat fuse and Aluminium bus bar. |
| 154 | Insulated piercing connector.Type-A-main 50 to 150 sq.mm & Tap-50 to 150 sq.mm |
| 155 | Insulated piercing connector.Type-B-main 25 to 150 sq.mm & Tap-6 to 35 sq.mm |
| 156 | GI Pipe Earthing (each 5th pole to earth) |
| 157 | Coil Earthing |
| 158 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 159 | Danger plate (LT) |
| 160 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 161 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 162 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 163 | GI Nut , Bolt & Washer of different sizes (0.5 Kg/ Pole) |
| 164 | Black Paint(GIS Numbering & Zebra Stripping) |
| 165 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 166 | LT Line Road crossing:- Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 3.5 mtr., 4 no's Channel(GI) required =( 4x7.14x3.5) ( For Double Pole) |
| 167 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 168 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 169 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 170 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 171 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 172 | Civil and Services Works:- Fixing of complete LT line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 173 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 174 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.1125Cu.mtr(Per Pole) |
| 175 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1550mm) = 0.375Cu.mtr(Per Pole) |
| 176 | Construction Earthing chamber including installation of earthing pipe making earthing chamber including excavation, soil treatment with bentonide powder, calculation of earth resistance, including, installation of 3 Mtr GI pipe 40/50 mm including welding of GI flat around pipe. |
| 177 | Dismantling :- Dismantling of 11/13 Mtr. Joist/WPB Pole- 150X150 mm/ 160X160 mm |
| 178 | Dismantling of 09/11 Mtr. Joist/WPB Pole- 116X100mm |
| 179 | Dismantling of 9/8 Mtr. PCC/Joist Pole |
| 180 | Dismantling / Removal of MS Channel. from Double Pole Structure /pole |
| 181 | Dismantling of existing 11/0.4kV, 33/0.4KV, Three Phase Distribution Transformer below 100KVA including removal of HT/LT leads, earth connections and unloading by crane if required. |
| 182 | Dismantling of ACSR/AAAC 34/ 55mm2 from overhead line |
| 183 | Dismantling of varous size of LT AB Cable Please Enable Macros to View BoQ information |