| 1 | Civil Works: |
| 2 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches,levelling, dressing and ramming the bottom, bailing out water as required complete. (a)Depth of excavation not exceeding 1500 mm |
| 3 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)(a) With earth obtained from excavation of foundation |
| 4 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge. |
| 5 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.a) In ground floor including roof |
| 6 | Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m.In ground floor including roofa) Upto 150 mm thick |
| 7 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 8 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement, if any, in ground floor as per relevant IS codes.(b ) River bazree |
| 9 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)(f) 25mm to 30mm shuttering without staging in foundation. |
| 10 | Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete.A) UPVC Pipes: (ii) 110 mm. Dia. |
| 11 | c) Bend 87.5 degree, 110 mm dia |
| 12 | d) Shoe, 110 mm dia |
| 13 | Labour for Collecting of existing gravels from switchyard premises and stacking the same within a lead of 75 meter within the Sub-Station area, Re-spreading the same gravels over Plain Cement Concrete in the switchyard premises & Screening, washing the gravels and cleaning the switchyard from plants, jungle, shrubs, mud, slurry etc including cost of tools and tackles Please Enable Macros to View BoQ information |