| 1 | Carriage of following materials from Elec. Store Center Unnao to work dump site along with loading unloading and propoer stocking. Distance 0-70 Km. |
| 2 | PCC/ST Pole of diff. size |
| 3 | ACSR Weasel Conductor |
| 4 | ABC conductor Three Phase of size 3x50/3x95/3x120 sq mm |
| 5 | L.T. Cable 1x400/1x120/3.5X70/1x240/3.5x400 sq mm |
| 6 | Other loose line materials including GI/stay wire, Single and double Pole accessories, complete stay & earthing, insulator, x-arm, jointing kit etc. |
| 7 | Carriage of following Transformer from Elec. Store Center Unnao to diff. work dump site along with loading unloading and propoer stocking. |
| 8 | T/F 63 KVA 11/0.4 KV |
| 9 | Dismantling of following Transformer from Plinth / Double Pole with Safe Carriage from work site to dump site along with loading unloading and propoer stocking. |
| 10 | T/F 25 KVA 11/0.4 KV |
| 11 | Mounting of following Transformer on double pole including its cartage and dragging from dump site to pit site. |
| 12 | T/F 63 KVA 11/0.4 KV |
| 13 | Providing & fixing of Holding clamps for PCC/ST pole with Nuts & Bolts. |
| 14 | Erection of single pole including digging of pits, fitting of all accessories along with cartage & dragging from dump site to pit site. |
| 15 | Providing & fixing of Stay clamps/ LT Clamps for PCC/ST pole with Nuts & Bolts. |
| 16 | Grouting of PCC/ST Pole as per RESPO Norms with grouting materials. |
| 17 | Earthing of pole as per RESPO Norms. |
| 18 | Making of neutral cum earth wire 7.16 mm or 6 SWG |
| 19 | Laying stringing and sagging of 11 HT Lines by ACSR weaseal conductor including all associated work with joint/jumpers and binding of insulator as required. |
| 20 | Laying stringing and sagging of aerial bunched cable including all fittings on erected PCC/ST Pole of size 3x50/3x95/3x120 sq mm |
| 21 | Fixing of Three Phase Distribution Box with clamp, N&B (Only D.B. Box Provided By Department) |
| 22 | Providing & fixing of dropper channel |
| 23 | Fixing of 11 KV Three Phase D.O. Fuse set ( with M.S. Channel with clamp) |
| 24 | Fixing of Danger board with clamp |
| 25 | Fixing of 11 KV disc insulator with NUT |
| 26 | Fixing of 11 KV PIN insulator with NUT |
| 27 | Providing & fixing of F-Clamp |
| 28 | Providing &fixing of top channel |
| 29 | Providing &fixing of Al. Lugs for 100 KVA Transformer |
| 30 | providing and fixing of LT SACKLE INSULATOR WITH BOLT AND NUT |
| 31 | Fixing of G.I barbed wire |
| 32 | Fixing of L.T. cable 1x400/3.5X400 sq mm |
| 33 | Safe Carriage of following T/F from work dump site to Electricity store center Unnao with loading, unloading and proper stocking. |
| 34 | Recevied back old T/F 25 KVA 11/0.4 KV Please Enable Macros to View BoQ information |