| 1 | Supply and Errection of Decentralised materials given by Contractor .Note- Consumable Material (nut&bolt&clamp) which is given by contractor. |
| 2 | Stone Pad 300x300x75mm |
| 3 | LT pole clamp with nut and bolt for PCC pole |
| 4 | Earth wire clamp for PCC pole |
| 5 | Suspension clamp |
| 6 | I Hook |
| 7 | Dead end clamp |
| 8 | LT piercing connector 120sqmm |
| 9 | Connecting lead 1x16 sqmm |
| 10 | Rigid PVC pipe size 110 mm ODX thickness 6.1mmx2.5meter long |
| 11 | Hot dip Galvanized Earthing Pipe electrode of size 1.5 dia |
| 12 | Hot dip Galvanized Earthing strpe of size 50mmx6mmx2100mm long |
| 13 | CARRIAGE & ERECTION OF WORK Note:- All Centralised Materials will be provided by Department at Store. |
| 14 | Carriage of 8.5m PCC Pole from store to site (Accroding to Estimate) with lodding and unlodding. |
| 15 | Errection of 8.5m PCC Pole with all fitting as per respo Norms. |
| 16 | Carriage of LT ABC Cable (3x95+1x70+1x16) sqmm from store to site (Accroding to Estimate) with lodding and unlodding. |
| 17 | Errection of LT ABC Cable (3x95+1x70+1x16)sqmm with all fitting as per respo Norms. |
| 18 | Carriage of Extra for stays at angle location (stay rod 16x1800mm, stay wire 5 kg, stay clamp, bolt and nuts) from store to site (Accroding to Estimate) with lodding and unlodding. |
| 19 | Errection of Extra for stays at angle location (stay rod 16x1800mm, stay wire 5 kg, stay clamp, bolt and nuts) with all fitting as per respo Norms |
| 20 | Carriage of Earthing of pole by MS earthing rod 20x2500mm and 6SWG earthing wire etc store to site (Accroding to Estimate) with lodding and unlodding. |
| 21 | Errection of Earthing of pole by MS earthing rod 20x2500mm and 6SWG earthing wire etc with all fitting as per respo Norms |
| 22 | Carriage of LT distribution Box from store to site (Accroding to Estimate) with lodding and unlodding. |
| 23 | Errection of LT distribution Box with all fitting as per respo Norms. |
| 24 | Carriage of 11 kv 3x185 XLPE cable from store to site (Accroding to Estimate) with lodding and unlodding. |
| 25 | Errection of 11 kv 3x185 XLPE cable with all fitting as per respo Norms. |
| 26 | Carriage of 11kv VCB for O/G CTR 200/100/5A, 350 MVA(1250amp) from store to site (Accroding to Estimate) with lodding and unlodding. |
| 27 | Errection 11kv VCB for O/G CTR 200/100/5A, 350 MVA (1250amp) with all fitting as per respo Norms. |
| 28 | Carriage of H/S O/D 11KV 3X185sqmm J/Kit from store to site (Accroding to Estimate) with lodding and unlodding. |
| 29 | Errection of H/S O/D 11KV 3X185sqmm J/Kit with all fitting as per respo Norms. |
| 30 | Carriage of GI PIPE 6\\" dia from store to site (Accroding to Estimate) with lodding and unlodding. |
| 31 | Errection of GI PIPE 6\\" dia with all fitting as per respo Norms |
| 32 | Welding work |
| 33 | Drilling of Trench 10 Ft. long |
| 34 | Laying of GI pipe 6 dia\\" pipe for laying of 11 kv 3x185sqmm xlpe cable |
| 35 | Digging & Laying of 11 kv cable(Double ckt) in trench with sand &brick and back filling |
| 36 | Road Restoration Charge |
| 37 | Making of J/kit |
| 38 | Receive back of material |
| 39 | Concreting/Grouting of PCC Pole as per respo Norms. (0.268cu.m.each) |
| 40 | Concreting/Grouting of stay as per respo Norms (0.268cu.m.each) Please Enable Macros to View BoQ information |