| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils |
| 2 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils: Add extra rate for quantities of works, executed : In or under water and /or liquid mud, including pumping out water as required |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. |
| 4 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level.: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). |
| 5 | Add Extra for laying concrete in or under foul positions. |
| 6 | Providing & fixing precast cement concrete coping 1 : 2 : 4 mix 50mm thick complete as per specification : |
| 7 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in: Cement Mortar 1:4 ( 1-Cement : 4-Sand). |
| 8 | Random Rubble stone masonry with hard stone in superstructure above plinth level and upto five level above 30cm. thick walls in : Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 9 | Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. |
| 10 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting (height upto 10 m) , fixing in position and applying a priming coat of approved steel primer all complete: |
| 11 | Supplying and fixing of chain link fencing with angle iron posts 50x50x6mm placed at every 3 Mtr. apart 30cm in ground embedded in cement concrete 1:3:6 (30x30x45cm) corner and every tenth post to be strutted with (50 x 50 x 6cm) angle iron provided and fixed and fitted with posts including earth work in excavation etc. complete with chain link size. 75mm x 15mm x 3.15mm |
| 12 | Add or deduct for each wire line over basic item |
| 13 | Extra for using galvanized barbed wire instead of black barbed wire. |
| 14 | Plaster on new surface on walls in cement sand mortar 1:4 including racking of joints etc. complete fine finish : 25 mm thick. |
| 15 | Finishing walls with Acrylic Smooth exterior paint of required shade including all scaffolding. New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm ). |
| 16 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : Two or more coats on new work |
| 17 | Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge: In cement mortar. Please Enable Macros to View BoQ information |