| 1 | HSR Item 27.1-Brick masonry work in 1:3 in sub-structure including scaffolding complete excluding pointing and plastering, as per drawing and MoRTandH Specifications1300 and 2200 HSR Rate(Rs.) 4882.00 Through Rate |
| 2 | HSR Item 27.5-Plain/Re-inforced cement concrete in sub- structure complete as per drawing and MoRTandH specifications 1500,1700 and 2200. PCC Grade M15 (with concrete Mixer) Height up to 5m HSR Rate (Rs.) 3985.00 Through Rate |
| 3 | HSR Item 27.10.1.2-RCC Grade M25 1.2. With Batching Plant, Transit Mixer and Concrete Pump HSR Rate(Rs.) 4312.00 Through Rate |
| 4 | HSR Item 14.70-Demolishing of lining with Bricks/Tiles /Cement concrete blocks of any size manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.HSR Rate(Rs.) 457.00 Through Rate |
| 5 | HSR Item 27.51.3-Filler joint 3. Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to caterfor a horizontal movement up to 20 mm, covered with sealant complete as per drawing and MoRT&H specifications.HSR Rate(Rs.) 132.00 Through Rate |
| 6 | HSR Item 10.1-Providing and laying of base course of floors consisting of 100 mm thick cement 1:8:16 and 100 mm sand or stone filling. HSR Rate(Rs.) 260.00 Through Rate |
| 7 | HSR Item 7.21.1-Brick work with common burnt clay nonmodular bricks of class designation 10.5 in foundation and plinth in: 1. Cement mortar 1:4 (1 cement : 4 coarse sand)HSR Rate(Rs.) 4128.00 Through Rate |
| 8 | HSR Item 6.14.2-Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work upto plinth level : 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) HSR Rate(Rs.) 3875.00 Through Rate |
| 9 | HSR Item 10.77-Providing and laying 80mm thick factory made cement concrete interlocking paver block of M -35 grade made by block making machine with strong vibratorycompaction, of approved size, design and shape, laid in required colour and pattern over (BIS 15658:2006) and including 60mm thick compacted bed of coarse sand, fillingthe joints with line sand etc. all complete as per the direction of Engineer-in-charge.HSR Rate(Rs.) 637.00 Through Rate |
| 10 | HSR Item 4.14.1-Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm onplan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of50 m. 1. All kinds of soil.HSR Rate(Rs.) 83.00 Through Rate |
| 11 | HSR Item 14.71-Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 1 km .HSR Rate(Rs.) 115.00 Through Rate |
| 12 | HSR Item 11.25.2-Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): 2. Raised and cut pointingHSR Rate(Rs.) 105.00 Through Rate |
| 13 | HSR Item 6.29.1-Centering and shuttering including strutting, propping etc. and removal of form work for : 1. Foundations, footings, bases for columns HSR Rate(Rs.) 155.00 Through Rate |
| 14 | HSR Item 34.49-Painting Two Coats on New Concrete Surfaces Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfacesHSR Rate(Rs.) 59.00 Through Rate size)HSR Rate(Rs.) 3476.00 Through Rate |
| 15 | HSR Item 27.28.1.1-Using Batching Plant, Transit Mixer and Concrete Pump 1.1. For formwork and staging add the following: For solid slab super-structure, 20-30 per cent of labour, material and machinery cost Height up to 5m HSR Rate(Rs.) 4634.00 Through Rate |
| 16 | HSR Item 27.13-Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing andMoRTandH Specifications 1600 & 2200.HSR Rate(Rs.) 61506.00 Through Rate Please Enable Macros to View BoQ information |