| 1 | Excavation for roadway in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes in accordance with requirements on lines, grades and cross sections, and transporting to the embankement location within all lifts and lead upto 1000 m as per MORTH Specification 301 |
| 2 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. |
| 3 | Centering and shuttering including struttings, propping etc. and removal of formwork for : |
| 4 | a) Foundations, footings, bases for columns and mass concrete. |
| 5 | b)vertical surfaces such as retaining walls , return walls, walls (any thk) including attached pilasters, buttresses, plinth and string courses, fillets, etc. |
| 6 | Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggrt. 20 mm. nominal size) excluding cost of centering, shuttering and finishing in: |
| 7 | a) All works upto plinth level |
| 8 | b)In retaining walls , return walls(any thk) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks, plain window sills, fillets etc, upto floor five level. |
| 9 | Providing and fixing weepholes with rigid PVC make laid in position with a required slope and level while layingpipes of approved the concrete of retaining wall,wing wall and earth retainig structure complete as directed by the Engineer in charge |
| 10 | B) 75 mm dia |
| 11 | Refilling the pipeline/foundation trenches plinth sides, foundation etc. with available excavated earth in layers not exceeding 20 cm depth consolidating each layer ramming and watering lead upto 50 M and all lifts and disposal of surplus earth as directed by Engineer in Charge. Please Enable Macros to View BoQ information |