| 1 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 14.9 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. |
| 2 | Pruning, trimming, shaping of trees /shrubs (ht 15 feet and above) i/c removal of cut materials upto 50mt. Lead, as per direction of officer in charge. T&P shall be arranged by the contractor. |
| 3 | Banking excavated earth in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m :(a) All kinds of soil |
| 4 | Carriage of earth by mechanical transport upto a lead of 1 km including loading,unloading and stacking. |
| 5 | Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of unserviceable material within 50 metres lead : |
| 6 | Dry brick pitching half brick thick in drains including supply of bricks and preparing the surface complete :With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 7 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar |
| 8 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:2:4 (1 cement : 2 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 4 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%) |
| 9 | 1:5:10 (1 cement : 5 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 10 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) ) |
| 10 | 6 mm cement plaster of mix : 1:3 (1 cement : 3 fine sand) |
| 11 | Neat cement punning. |
| 12 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 13 | Taking out existing CC interlocking paver blocks from footpath/ centralverge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. |
| 14 | Providing and laying 60 mm thick faciory made cement concreteinterlocking paver block of M -30 grade made by block making machinewith strong vibratory compaction, of approved size, design & shape, laidin required colour and pattern over and including 50 mm thick compactedbed of coarse sand, filling the joints with line sand etc. all complete as perthe direction of Engineer-in-charge |
| 15 | Centering and shuttering including strutting, propping etc. and removal of form for Small lintels not exceeding 1.5 m clear span, moulding as in cornices, window sills, string courses, bands, copings, bed plates, anchor blocks and the like |
| 16 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 17 | Hydraulic Excavator (3D) with driver and fuel |
| 18 | Amount after applying GST Multiplying Correction factor @0.973 =2833272.70 Please Enable Macros to View BoQ information |