| 1 | 33 KV LINE PART:- S.T.P. 11.0 Mtr. Long |
| 2 | Stone Pad (300x300x75 mm) |
| 3 | 33KV Pin Insulator |
| 4 | 33KV Pin with nuts |
| 5 | G I Barbed Wire |
| 6 | Aluminium winding wire |
| 7 | Number Plate with clamp and Nut & Bolt |
| 8 | Danger Plate with clamp and Nut & Bolt |
| 9 | Nut Bolt and washer all sizes |
| 10 | The Grouting and making of plinth of the support (1/6 of the full length of the supports) will be done as per norms in the CC 1:4:8 with cement, course sand and brick ballast including back filling and proper ramming.fixing of all clamps and other accessories as per relevant drawing. (i) 11.0 Mtr. Long S.T.P. poles |
| 11 | Earthing of Pole by M S Earthing Rod 20 x 2500 mm and 6 SWG earthing wire etc |
| 12 | E-bracket for 33 KV |
| 13 | Aluminium Paint |
| 14 | Red Oxide Paint |
| 15 | Earth wire Clamp |
| 16 | Top Channel 125x65 mm, 3200 mm long |
| 17 | Dropper Channel 100x50mm, 3000 mm long |
| 18 | Holding Clamp |
| 19 | Complete Stay (GI Stay Rod 20x1800 mm, stay wire 7/8 SWG, Stay Clamp, Bolt, nut and washer) |
| 20 | Grouting of Stay Rods 20x1800 mm. including all works of excavation, fixing, tightening & nozzling of stay with the poles and of required tension as per relevant drawing including back filling of earth and proper ramming. |
| 21 | 33 KV Disc Insulator 70 KN B&S Type |
| 22 | 33 KV Disc Fitting for Dog Conductor 70 KN B&S type |
| 23 | PG Clamp Dog to Dog |
| 24 | ACSR Dog Conductor |
| 25 | Tee off channel 125x65x1600 mm |
| 26 | Holding clamp for Tee off Channel |
| 27 | M.S. Guarding Angle 65x65x6x2300 mm. |
| 28 | M.S. Guarding Angle Holding clamp with nuts and bolts |
| 29 | Eye Bolts |
| 30 | G.I. wire 6 SWG |
| 31 | G.I. wire 8 SWG |
| 32 | Binding wire |
| 33 | Turn Buckle |
| 34 | G.I. M+6 Tower 19.30 Mtr. Long weight above (2400 KG Weight) as per dvvnl approved GTP |
| 35 | Concreting of M+6 Tower |
| 36 | Insulated Single lead Cable 300 sqmm for cable connection |
| 37 | Lug 3x300 sqmm. |
| 38 | HDPE Pipe PE-100 PN-6 dia 160 mm |
| 39 | 33 KV 3x300 sqmm XLPE cable. |
| 40 | 33 KV H/S Jointing Kit 3x300 sqmm |
| 41 | Cable route Marker |
| 42 | G.I. Pipe 160 mm dia |
| 43 | G.I. Pipe Hoding Clamp |
| 44 | Cable Under ground work : Laying of 33 KV Cable in Air |
| 45 | Laying of HDPE Pipe PE-100, PN-6, DN-160 mm dia Pipe for laying of 33KV, 3x300Sq.mm, XLPE Cable with HDD (trenchless) method including cable laying. |
| 46 | Digging & laying of 33 KV Cable in trench with sand & brick |
| 47 | Making of 33 KV J/kit |
| 48 | Top channel 100x50x2240 mm. |
| 49 | Clamps for Top & Droper Channel with Nut & Bolts |
| 50 | 11 KV Disc Insulators T&C Type 4500 Kg. |
| 51 | 11 KV Disc fittings T&C Type 4500 Kg. |
| 52 | 11 KV Pin Insulator |
| 53 | 11 KV Pin with nut |
| 54 | Line Isolator |
| 55 | Structure for Line Isolator with Plinth & Foundation |
| 56 | Chemical Earthing Complete |
| 57 | Choping of branches of Tree |
| 58 | Carriage of following material from Center Store to Site : 11 Mtr. long S.T. Pole |
| 59 | 33 KV 3x300 sqmm XLPE cable. |
| 60 | A.C.S.R. DOG CONDUCTOR Please Enable Macros to View BoQ information |