| 1 | PART-A (Material) |
| 2 | Following materials supplied by the contractor :- |
| 3 | Eye Hook. |
| 4 | Clamp with nut & boults |
| 5 | Suspension Clamp. |
| 6 | Stone Pad 300x300x75mm |
| 7 | Dead-End Clamp |
| 8 | Safe carriage/cartage of following items from Store Centre, Sultanpur to work site including loading, unloading and proper stacking and return back of balance material form site to store at Sultanpur (distance within 0-50 Km.) |
| 9 | Safe carriage of PCC Pole 8.5 Mtr. Long |
| 10 | Safe carriage of ACSR weasel conductor |
| 11 | Safe carriage of LT PVC Cable (3.5x70/35) sq.mm. |
| 12 | Safe carriage of LT AB Cable (3x50+1x35+1x16) sq.mm. |
| 13 | Safe carriage of LT AB Cable (3x95+1x70+1x16) sq.mm. |
| 14 | Safe carriage of Other Line Materials |
| 15 | Safe carriage of T/F 100 KVA |
| 16 | Safe carriage of T/F 63 KVA |
| 17 | Dragging of PCC Pole from site to pit point |
| 18 | Fabrication & erection of single pole support on PCC Pole including digging of pit & fixing of all accessories and clamps including grouting & earthing of pole as per RESPO norms. |
| 19 | Fabrication & erection of double pole support on PCC Pole including digging of pit & fixing of all accessories and clamps including grouting & earthing of pole as per RESPO norms. |
| 20 | Mounting of additional 100 KVA T/F on double pole as per RESPO norms. |
| 21 | Mounting of additional 63 KVA T/F on double pole as per RESPO norms. |
| 22 | Stringing and sagging of LT PVC Cable (3.5x70/35) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 23 | Stringing and sagging of LT AB Cable (3x50+1x35+1x16) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 24 | Stringing and sagging of LT AB Cable (3x95+1x70+1x16) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 25 | Laying Stringing & sagging of ACSR Weasel Conductor etc. |
| 26 | Earthing of Transformer through earthing rod as per approved drawing including all requred manpower as per RESPO norms. |
| 27 | Erection of Distribution Box 3 Phase including installation and connection of existing LT service cable as per RESPO norms. |
| 28 | Supply and Installation of LT Fuse Set With SMC Box For 63/100 KVA Transformer. |
| 29 | Stay Complete as per RESPO norms. |
| 30 | Suply & Erection Danger Board with Barbed wire including jumfer (All the material, Manpower and T&P will be arranged by the contractor at his own cost). as per RESPO norms. Please Enable Macros to View BoQ information |