| 1 | Part - A ( Material)Following Material Supplied by the Contractor:- |
| 2 | Cable holding clamp different size |
| 3 | Nut & Bolt |
| 4 | Aluminum lug 300 sqmm |
| 5 | PG Clamp off size |
| 6 | Disc Fitting 70 KN 33 KV |
| 7 | 33 KV Pin with Nut |
| 8 | GI Barbed wire |
| 9 | 33 KV Danger Board(250x200 mm) with Clamp and Nuts & Bolts. |
| 10 | stone pad 300*300*75 mm |
| 11 | The work of safe carriage of the following material with loading/unloading from store centre Darshan Nagar to site of work. (Approx. Distance 0 to 50 Km.) |
| 12 | S.T. Pole 11 Mtr. Long |
| 13 | ACSR Dog Conductor |
| 14 | 33 KV XLPE Cable 3x300 sq mm |
| 15 | 33 KV Cable Jointing Kit Outdoor 3x300 sqmm |
| 16 | 33 KV Staight Through Cable Jointing Kit 3x300 sqmm |
| 17 | 33 KV SF6 type 4 way RMU, SCADA Compatible complete including associated cable and accerrories. |
| 18 | Single core XLPE Insulated Aluminium cable 300 sqmm for jumpering |
| 19 | Other Line material i.e. cross arm / conductor / pin insulator / stay / earthing/cable Box etc. except A.B Cable. |
| 20 | Dragging of ST/PCC Pole from dump site to pit site |
| 21 | Fabrication and Errection of Double Pole Support on ST/PCC Pole Pole including grouting with 1:4:8 ratio Cement, sand & Brick Ballast& including digging of pit and fixing of all accessories clamp & earthing as per RESPo Norms. (Cost of clamps borne by contractor) |
| 22 | Stringing, Sagging, Binding and jumpering of ACSR Weasel as per RESSPO Norms. |
| 23 | Earthing of Poles as per RESPO Norms. |
| 24 | Laying of underground 33 KV 3x300 sq mm XLPE Cable in Normal Soil by digging of trench 1050 mm deep, 750 mm wide including supply of required material as fine sand, Ist class bricks as per norms. (All the material will be supplied by the contractor except 33 KV XLPE cable) |
| 25 | 33 KV XLPE cable 3X300 sq.mm Cable Laying in Constructed trench including the opening the trench cover with the help of hydra and after laying closing the trench cover properly. |
| 26 | Laying of 33 KV XLPE Cable 3x300 sqmm underground by HDD (HORIZONTAL DRILL DIRECTION) Method by HDD Machine Complete in all Respect as per norms. (All the material will be supplied by the contractor . |
| 27 | Hanaging, Hosting & clamping of G.I. Pipe, channel, nut & Bolt 3x300 mm2 XLPE 33 KV cable as per RESSPO Norms (cost of all accessories will be borne by contractor) |
| 28 | Earthing by way of boring and lowering of \\"B\\" class G.I. pipe 50 mm dia 20 mtr. Long from ground upto the water lavel it will be connected to the G.S. Strip for T/F nutral connection the earth strip will be welded to the G.I. pipe the work also included top cap and clamps for pouring water the cost of all material will all labour and T n P etc. complete in all respect . (all the material will be supplied by the contractor.) |
| 29 | Installation of Heat Shrinkable Type cable jointing kits Outdoor end Termination suitable for 33 KV XLPE cable 3x300 mm2 confirming to IS ESI-09-13-IS-13573 of 1992 amendment I&II VDE-0278 of latest version there of if any. ( Jointing Kit supplied by Dept.) |
| 30 | Installation of Heat Shrinkable Type cable jointing kits Staight Through end Termination suitable for 33 KV XLPE cable 3x300 mm2 confirming to IS ESI-09-13-IS-13573 of 1992 amendment I&II VDE-0278 of latest version there of if any. ( Jointing Kit supplied by Dept.) |
| 31 | Construction of RMU Plinth (All Material is Provided by Contractor) As Per RESSPO Norms. |
| 32 | Installation, Erection and commissioning of 11 K.V. RMU on constructed plinth and connecting with system including completion of termination/Jointing kits testing of its and etc complete in all respect. |
| 33 | Supply and Laying of G.I. Pipe 6'' dia with Clamp and Nut Bolt |
| 34 | Road Restoration Charges |
| 35 | Permission of NHI |
| 36 | Railway Crossing Permission |
| 37 | Rect Back old and used Materials etc. Including Cable Iron Drum to store. Please Enable Macros to View BoQ information |