| 1 | PART-A (Material) |
| 2 | Following materials supplied by the contractor :- |
| 3 | Copper L-Piece for 250 KVA T/F. |
| 4 | Suspension Clamp. |
| 5 | Eye Hook Clamp. |
| 6 | Dead end Clamp. |
| 7 | Stone Pad 300x300x75mm. |
| 8 | Clamp for LT T-off with Bolts & Nuts. |
| 9 | Holding Clamp for top channel TPMO & Fuse Srt etc. with Bolts & Nut. |
| 10 | Safe carriage/cartage of following items from Store Centre, Sultanpur to work site including loading, unloading and proper stacking and return back of balance material form site to store at Sultanpur (distance within 0-50 Km.) |
| 11 | Safe carriage of PCC Pole 8.5 Mtr. Long |
| 12 | Safe carriage of LT PVC Cable (3.5x70/35) sq.mm. |
| 13 | Safe carriage of LT PVC Cable (3.5x150/70) sq.mm. |
| 14 | Safe carriage of LT PVC Cable 1x240 sq.mm. |
| 15 | Safe carriage of LT AB Cable (3x95+1x70+1x16) sq.mm. |
| 16 | Safe carriage of Other Line Materials |
| 17 | Safe carriage of T/F 63 KVA |
| 18 | Safe carriage of T/F 100 KVA |
| 19 | Safe carriage of T/F 250 KVA |
| 20 | Dragging of PCC Pole from site to pit point |
| 21 | Fabrication & erection of single pole support on PCC Pole including digging of pit & fixing of all accessories and clamps including grouting & earthing of pole as per RESPO norms. |
| 22 | Fabrication & erection of double pole support on PCC Pole including digging of pit & fixing of all accessories and clamps including grouting & earthing of pole as per RESPO norms. |
| 23 | Mounting of additional 63 KVA T/F on double pole as per RESPO norms. |
| 24 | Mounting of additional 100 KVA T/F on double pole as per RESPO norms. |
| 25 | Installation of 250 KVA T/F on plinth and associated works as per RESPO norms. |
| 26 | Construction of new plinth as per approved drawing for 11/0.4 KV 250 KVA T/F including all requred man and material along with construction of fencing round the transformer plint including man and material and earthing of fencing as per RESPO norms. |
| 27 | Stringing and sagging of LT PVC Cable (3.5x70/35) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 28 | Stringing and sagging of LT PVC Cable (3.5x150/70) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 29 | Stringing and sagging of LT PVC Cable 1x240 sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 30 | Stringing and sagging of LT AB Cable (3x95+1x70+1x16) sq.mm. from DT to Double pole including all associated work as per RESPO norms. |
| 31 | Erection of Distribution Box Single Phase & Three Phase including installation and connection of existing LT service cable as per RESPO norms. |
| 32 | Stay Complete as per RESPO norms. |
| 33 | Providing and installation of Pipe type earthing as per approved drawing including all requred man and material as per RESPO norms. |
| 34 | Earthing of Transformer through earthing rod as per approved drawing including all requred manpower as per RESPO norms. |
| 35 | Supply and Installation of 11 KV Fuse Set With SMC Box For 63 & 100 KVA Transformer as per RESPO norms. |
| 36 | Supply and Installation of LT Tail less Unit For 250 KVA Transformer as per RESPO norms. |
| 37 | Suply & Erection Danger Board with Barbed wire including jumfer (All the material, Manpower and T&P will be arranged by the contractor at his own cost). as per RESPO norms. |
| 38 | Safe carrige of old and used 100 KVA DT from site (different location) to central store, Sultanpur. Please Enable Macros to View BoQ information |