| 1 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.Cement Concrete |
| 2 | Cleaning the exposed corroded Reinforcement as well as worn out concrete by sand blasting with air compressor including all materials, hire charges of machineries and labour etc. all complete as per technical specification and direction of the Engineer-in-Charge. |
| 3 | Providing anti-corrosive protective coating to inhibit the corrosion to HYSD reinforcements including two coats of anti-corrosive coatings of consumption as per manufacturer's specification, cleaning etc. complete as per the direction of the Engineer-in Charge. |
| 4 | Epoxy Bonding of new concrete to old concrete |
| 5 | Providing and inserting nipples with approved fixing compound after drilling holes for grouting as per Technical specifications including subsequent cutting/removal and sealing of the hole as necessary of nipples after completion of grouting with Cement/Epoxy. |
| 6 | Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as per clause 2803.1. |
| 7 | Applying epoxy mortar ( 10 mm nominal thick) over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per Technical specification |
| 8 | Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture mechanically with compressed air under pressure, comprising of cement, sand, coarse aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength not less than 25 MPa and workmanship conforming to clause 2807.6. (40 mm average thickness.) |
| 9 | Guniting concrete surface with cement mortar (25 mm nominal thick) applied with compressor after cleaning surface and spraying with epoxy complete as per Technical specification. |
| 10 | Sealing of cracks / porous concrete by injection process through nipples/Grouting complete as per Technical specification.Cement mortar (1:1) Grouting |
| 11 | Hire and labour charges for staging with sal bullah for super structure of bridge (Major and Minor) including stripping off and removing clearing on completion of work as per design and drawing approved by the Engineer-in-charge. |
| 12 | Add GST @ 18% of sum of item 1.00 to 11.00 |
| 13 | Add L.W. Cess @ 1% of sum of item 1.00 to 12.00 Please Enable Macros to View BoQ information |