| 1 | Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed.Earth work in excavation of foundation trenches or drain ..............complete. |
| 2 | Cement concrete (1:1.5:3) with graded stone chips 5.6 mm size with hexagonal square mesh wire netting, I.R.C. fabric mesh or X.P. M. fitted and fixed after tying the existing reinforcement on concrete without distributing the same and with proper scarping and cleaning the reinforcement and disturbed concrete with wire brush etc. after applying a coat of cement including the cost of wire netting I.R.C or X. P. M. & cost of all handling and scaffolding complete as per direction of Engineer-in -charge.). b) 25 mm thick |
| 3 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc. including supply of rods, initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape,placing in proper position and binding with 16 gauge black annealed wire at every inter-section, complete as per drawing and direction. (i) Tor steel/Mild steelTor steel / Mild Steel ( SAIL/TATA/RINL ) |
| 4 | Welding in M.S. structural work with gas or electric:(a) Tack weld |
| 5 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortarincluding rounding off or chamfering corners as directed andraking out joints including throating, nosing and drip course,scaffolding/staging where necessary (Ground floor).[Excludingcost of chipping over concrete surface](i) With 1:6 cement mortar (b) 20 mm thick plaster |
| 6 | (ii) With 1:4 cement mortar(c) 10 mm thick plaster |
| 7 | Cleaning the exposed reinforcement preferably upto full diameter by wire brush, applying two coats of polymer based rust removing compound left for 24 hours, removing the coating and then applying two (2) coats of polymer modified anti corrosive protective coating formulated to inhibit the corrosion of reinforcement as per manufacturer's specification] [Mode of measurement: The affected surface area of reinforcement shall be considered for payment] |
| 8 | Applying epoxy based reactive joining agent for joining the old concrete with fresh concrete to be applied within manufacturer's specified time as per manufacturers specification. (0.4 Kg / m² of concrete surface). |
| 9 | White washing including cleaning and smoothening surface thoroughly.(b) Two coats (to be done on specific instruction). |
| 10 | (c) Three coats (on new works only). |
| 11 | (a) Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. |
| 12 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (b) On steel or other metal surface :(iv) Two coats (with any shade , except white)With super gloss (hi-gloss) |
| 13 | Removing old paint from blistered painted surface of steel or other metal by chipping including scraping and cleaning and exposing the original surface. |
| 14 | Supplying best Indian sheet glass panes set in putty and fitted and fixed with nails and putty complete. (In all floors for internal wall & upto 6 m height for external wall)(i) 3 mm thick (weighing 7.4 kg/Sq.m) |
| 15 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond thecompound, in conformity with the Municipal /Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge. |
| 16 | Add GST @18% |
| 17 | Add labour welfare cess @ 1% Please Enable Macros to View BoQ information |