| 1 | PART-A [Time of completion of the 1st layer t1=3 months )Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (b) By mechanical means (without millingmachine) :(iii) Above 100 mm thick. |
| 2 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening / binding materials to fill up the interstices of coarse aggregate, watering including lighting, guarding, barricading and making necessary earthen bundh of one metre width on each side and preparing the bed by necessary cutting or filling, including cost of all materials and hire and labour charges of all men and machinery and compacting to the required density, as per Clause 404 of specifications for Road & Bridge Works of MoRT&H (5th Revision).(iii) Grading-II Aggregate (53 mm to 22.4 mm) Using Stone Screening Type B (11.2 mm) B. Manual Means |
| 3 | Prime Coat Providing and applying primer coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 and requisite quantity on prepared surface of granular base including cleaning of road surface and spraying primer using Mechanical means including cost and carriage of bitumen emulsion and all other incidental costs of work complete as per Clause 502 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For WBM / WMM Surface: (With cationic bitumen emulsion (MS, Packed) @0.85 kg/sqm) |
| 4 | Providing and applying tack coat using Cationic bituminous emulsion of approved grade conforming to IS : 8887-1978, over prepared surface including cleaning of surface with mechanical broom, moistening the surface, applying tack coat including cost and carriage of emulsion, hire charges of machineries and labour, cost of fuel and lubricants all complete as per specification and direction of the Engineer-in-charge. (Over bituminous surface using cationic bitumen emulsion (MS, Packed) @0.25 kg/sqm) |
| 5 | Providing and laying bituminous macadam with Mobile Hot Mix Plant (Light Duty) using approved crushed aggregates of specifiedgrading as per Table 500.7 premixed with bituminous binder, transported to site laid over a previously prepared surface at specified laying temperature by means of approved and suitable arrangements to the required grade, level and alignment and rolled with suitable power roller for break down, inter-mediate and finished rolling as per specification to achieve the desired compaction including cost and carriage of stone materials and bitumen, hire charges of machinery and equipment, cost of fuel and lubricants and wages of operational staff, quality control complete as per Specifications for Road & Bridge Works of MoRT&H (5th Revision).With Bitumen VG-30 (Packed) |
| 6 | Repairing pot-holes and making up small depressions with ramming or power rolling including screening, cleaning chips or metals and washing, drying as necessary and heating the chips or metal where necessary, cutting pot holes to regular shapes with vertical edges, cleaning the disintegrated materials, heating matrix and applying tack coat (including sides), finishing the top of repaired surface levelled with adjoining area, including cost and carriage of stone aggregates and matrix, excluding cost of applying tack coat.i) With premixed Chips with 54 kg of bitumen (VG-30, Packed) per m3 of loose net volume of stone chips using concrete mixer machine. (b) Using Mobile HMP (Light duty) |
| 7 | Providing and laying Bituminous Profile Corrective Course using Mobile Hot Mix Plant (Light Duty) and using aggregates of Grading-2 of Table-33 premixed with 75kg of bitumen (VG-30, Packed) per cum, transported to site laid over a previously prepared surface at specified laying temperature to the required grade, level and alignment, as per specification to achieve the desired compaction including cost and carriage of stone materials and bitumen, hire charges of machinery and equipment, cost of fuel and lubricants and wages of operational staff, quality control complete as per direction of Engineer-incharge. |
| 8 | Providing, laying and rolling of Open - graded premix surfacing of 20 mm thickness composed of 13.2 mm (@ 0.018 m³ per m²) and 11.2 mm (@ 0.009 m³ per m²) size stone aggregates, including thoroughly cleaning of the surface, screening, cleaning and pre-heating stone chips and fully pre-coating the same either using viscosity grade paving bitumen (VG-30, Packed), carrying the mixture by any suitable arrangements, laying the mixture uniformly over the surface, including line, grade and level to serve as wearing course on a previously prepared base, including mixing in Mobile Hot Mix Plant (Light Duty) and thoroughly rolling with a smooth wheeled roller8-10 tonne capacity, finished to required level and grades including the cost and carriage of stone chips and matrix, heating the matrix, preheating the aggregates to required temperature and including the hire charges of Mobile Hot Mix Plant (Light Duty) and other machinery, pay of operators, cost of fuel and lubricants etc. complete to be followed by seal coat of either Type A or Type B as per Technical Specification Clause 508 for Rural Roads of MORD. |
| 9 | Providing and laying Premixed Seal Coat (Type B) with approved quality grit @ 0.6 m3/ 100 m2 and bitumen binder on thoroughly cleaned black top surface coated with tack coat, including heating and mixing cleaned grit (100 % passing through 2.36 mm sieve and retained on 180 micron sieve) uniformly with bitumen binder, (VG-30, Packed) laying and spreading the mix at an uniform rate using suitable means, brushing the surface, if necessary, to ensure uniformity, followed by rolling with power roller including the cost and carriage of binder and aggregates, cost of heating the binder and aggregates and all other incidental charges, cost of fuel and lubricants, including hire charges of machineries, tools & plants required for construction and quality control complete as per Clause 511 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).II By Manual Means With Hot Bitumen Binder (@ 6.80 kg / 10 sqm.) |
| 10 | Water Bound Macadam Sub Base by consolidating Jhama metal of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(i) For Construction of Sub Base by consolidating Jhama metal (63 mm to 45 mm) with moorumscreening : |
| 11 | Reinforced cement concrete M15 grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc.(ii) Ordinary kilometer stone (precast) |
| 12 | Supplying fitting and fixing R.C. guard post 1.37m long with C.C. 1:2:4 with graded stone chips of 13.2mm down casting , curing complete including cost of providing 4nos.of 12mm dia. rod of length 1.54m as main reinforcement and 6 nos. of round shaped 8mm dia rods used as binders; the placing of the first binder should be at 75mm below the top finished surface and the other 5 nos of binders should be placed at 245mm c/c ; the guard post is of octagonal section with inscribed circle of dia 24cm at the base tapering to corresponding dimensions of 16cm at the top including two coats of painting with best quality synthetic enamel paint of approved make and grade to form 6 nos. horizontal alternate bands in white/tannery yellow and black to 90 cm length standing up above ground after mendinggood damages if any during striking off shuttering,making hole in ground of 47cm depth and 30cm. minimum dia, fixing the guard posts in the sameholes and repacking the earth properly so as to keep theguard posts standing properly erect in correct position true to line and length including carriage of R. C. Guard Post with due care to the site including loading into the truck and unloading at site complete in all respect. With Pakur variety stone chips |
| 13 | PART-B [Time of completion of the 2nd layer t2=3 months) Laying and rolling of Open - graded premix surfacing of 20 mm thickness composed of 13.2 mm (@ 0.018 m³ per m²) and 11.2 mm (@ 0.009 m³ per m²) size stone aggregates, including thoroughly cleaning of the surface, screening, cleaning and pre-heating stone chips and fully pre-coating the same either using viscosity grade paving bitumen (VG-30, Packed), carrying the mixture by any suitable arrangements, laying the mixture uniformly over the surface, including line, grade and level to serve as wearing course on a previously prepared base, including mixing in Mobile Hot Mix Plant (Light Duty) and thoroughly rolling with a smooth wheeled roller8-10 tonne capacity, finished to required level and grades including the cost and carriage of stone chips and matrix, heating the matrix, preheating the aggregates to required temperature and including the hire charges of Mobile Hot Mix Plant (Light Duty) and other machinery, pay of operators, cost of fuel and lubricants etc. complete to be followed by seal coat of either Type A or Type B as per Technical Specification Clause 508 for Rural Roads of MORD. |
| 14 | Providing and laying Premixed Seal Coat (Type B) with approved quality grit @ 0.6 m3/ 100 m2 and bitumen binder on thoroughly cleaned black top surface coated with tack coat, including heating and mixing cleaned grit (100 % passing through 2.36 mm sieve and retained on 180 micron sieve) uniformly with bitumen binder, (VG-30, Packed) laying and spreading the mix at an uniform rate using suitable means, brushing the surface, if necessary, to ensure uniformity, followed by rolling with power roller including the cost and carriage of binder and aggregates, cost of heating the binder and aggregates and all other incidental charges, cost of fuel and lubricants, including hire charges of machineries, tools & plants required for construction and quality control complete as per Clause 511 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).II By Manual Means With Hot Bitumen Binder (@ 6.80 kg / 10 sqm.) |
| 15 | Providing and applying tack coat using Cationic bituminous emulsion of approved grade conforming to IS : 8887-1978, over prepared surface including cleaning of surface with mechanical broom, moistening the surface, applying tack coat including cost and carriage of emulsion, hire charges of machineries and labour, cost of fuel and lubricants all complete as per specification and direction of the Engineer-in-charge.(i) Over black topped surface using cationic bitumen emulsion (MS, Packed) @ 0.25 kg/sqm |
| 16 | Add GST @ 18% |
| 17 | Add Labour Welfare Cess @ 1% Please Enable Macros to View BoQ information |