| 1 | Dismantling of existing structures like culverts, bridges, retaining walls, CC road and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 50 metres as directed by Engineer Cement Concrete Grade M-15 and above and PCC blocks |
| 2 | Carriage of Materials by mechanical transportincluding loading, unloading and stacking : Earth for 2.0 Km |
| 3 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth upto 1.5 m |
| 4 | Providing granular bedding having width = outer dia of pipe (Bc) + 500mm, thickness below pipe = 0.25Bc or 100mm (whichever is higher) and haunching = 0.5Bc, with graded hard crusher broken stone of 100% passing through 20mm sheive, 20 to 50 % passing through 10mm sheive and 100 % retain on 6.3mm sheive, laying in layers of thickness 10/15cm including ramming, consolidation etc complete for all type of pipes of following sizes as per drawing and or as directed by Engineer. 100 mm internal diameter |
| 5 | Providing at site, lowering & laying in trenches, aligning & jointing of PVC-U pipes (SN 8) as per IS 15328 (amended up to date) and as per specifications with rubber rings with socket and spigot joint, (EPDM/SBR) for all depths for pipe length as per drawing and specification including hydraulic field testing (including the cost and conveyance of water to site for testing) and commissioning etc complete as directed by Engineer. Note : E/w to be measured and paid separately. Length of pipe shall be measured in between the outer wall of two manholes / Inspection chambers. Pipe in the manhole/inspection chamber’s wall shall deemed to be included in the item of manhole/inspection chamber shall not be payable. 110 mm Nominal Dia |
| 6 | Constructing providing and fixing of pre-cast RCC M-40 grade circular Road Side Inspection Chamber including earthwork with following dia and depth cylindrical piece with 100mm wall thickness, inbuilt 100mm thick base slab, inbuilt cover & frame on top, provision for 110mm OD in and out sewer connection with making proper inbuilt benching and channel with PCC M-15 grade including providing cast-in-situ 100mm thick base foundation of PCC M-10 grade, supplying and fixing circular precast SFRC Circular 300 / 450 mm dia manhole cover with frame MD-10 (as per IS-12592 amended upto date), including steel reinforcement minimum @ 80kg/cum, testing for water tightness complete in all respect as per drawing, specification and the direction of the Engineer. Pre-cast Road side inspection chamber of 300mm dia (internal), 450mm depth and 600mm dia base foundation |
| 7 | Pre-cast Road side inspection chamber of 450mm dia (internal), 600mm depth and 750mm dia base foundation |
| 8 | Pre-cast Road side inspection chamber of 450mm dia (internal), 900mm depth and 750mm dia base foundation |
| 9 | Providing and laying lean cement concrete 1:4:8 in Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in concrete mixer, laid manually, compacted with surface vibrator, finishing and curing complete as per clause 601, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. |
| 10 | Providing and laying un-reinforced, plain cement concrete mix with Concrete Mixer & vibrator pavement over a prepared sub base with 43 grade cement , coarse and fine aggregate conforming to IS: 383, maximum size of coarse aggregate not exceeding 25 mm, mixed as per approved mix design, laid, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints etc including all material, labour, machinery, lighting, guarding and maintenance of diversion. PCC M-20 Please Enable Macros to View BoQ information |