| 1 | Cartage of following material from ESC Noida/Sahibabad/ Ghaziabad /Any other ESC of Meerut Discom to JE Store and from JE store to various points site of work including loading and unloading at both ends : - |
| 2 | 11/0.4 KV T/F 250 KVA |
| 3 | 11/0.4 KV T/F 63 KVA |
| 4 | PCC Pole 8.5 Mtr. Long. |
| 5 | LT ABC 3Cx120+1x95+1x16 Sq.mm. |
| 6 | LT ABC 3Cx95+1x70+1x16 Sq.mm. |
| 7 | LT PVC Cable Al. 1x400 Sq.mm. |
| 8 | LT PVC Cable Al. Armoured 3.5x150 Sq.mm. |
| 9 | ACSR Dog Conductor |
| 10 | ACSR Rabbit Conductor |
| 11 | 11 KV Polymeric Disc Insulator with fitting |
| 12 | 11 KV Polymeric Pin Insulator with pin |
| 13 | Earthing Complete |
| 14 | Stay Set complete |
| 15 | 11 KV Cross Arm V-type |
| 16 | Providing of following material of standard make / best quality for complete the work of I/C of DTs & other related work with disconnecting & reconnection of cable etc. as per RESSPO norms by the contractor at his own cost : - |
| 17 | Concreating of pole |
| 18 | Concreating of Stay |
| 19 | Stone Pad |
| 20 | I Hook with nut & bolts |
| 21 | J Hook with nut & bolts |
| 22 | Suspention Clamp with nut & bolts |
| 23 | Dead End Clamp with nut & bolts |
| 24 | Al. Lug long barrel off size (LS) |
| 25 | Holding Clamp with nut & bolts |
| 26 | Copper L-piece 50x225x10mm (LS) |
| 27 | Piercing Clamp with Bolt & Nut |
| 28 | Aluminium Crimping Lug off size (LS) |
| 29 | MS Angle 75x75x6x2028 Sq.mm with clamp & Bolt & Nut (T/F Base) |
| 30 | MS T-Off Channel size 100x50x1640mm with clamp & Bolt & Nut |
| 31 | MS Top Channel size 100x50x2280/2400mm with clamp & Bolt & Nut |
| 32 | MS Dropper Channel size 100x50x2280/3200mm with clamp & Bolt & Nut |
| 33 | MS Channel Size 65x65x6 Sq.mm. for HT Fusing Arrangement |
| 34 | Fabrication, Installation / Erection / Fixing of following material for complete the work of DT & other related work with disconnecting & reconnection of cable for DT Metering etc. as per RESSPO norms by the contractor at his own cost : - |
| 35 | Concreating of pole |
| 36 | Concreating of Stay |
| 37 | Stone Pad |
| 38 | I Hook with nut & bolts |
| 39 | J Hook with nut & bolts |
| 40 | Suspention Clamp with nut & bolts |
| 41 | Dead End Clamp with nut & bolts |
| 42 | Al. Lug long barrel off size (LS) |
| 43 | Holding Clamp with nut & bolts |
| 44 | Copper L-piece 50x225x10mm (LS) |
| 45 | Piercing Clamp with Bolt & Nut |
| 46 | Aluminium Crimping Lug off size (LS) |
| 47 | MS Angle 75x75x6x2028 Sq.mm with clamp & Bolt & Nut (T/F Base) |
| 48 | MS T-Off Channel size 100x50x1640mm with clamp & Bolt & Nut |
| 49 | MS Top Channel size 100x50x2280/2400mm with clamp & Bolt & Nut |
| 50 | MS Dropper Channel size 100x50x2280/3200mm with clamp & Bolt & Nut |
| 51 | MS Channel Size 65x65x6 Sq.mm. for HT Fusing Arrangement |
| 52 | 11 KV Polymeric Disc Insulator with fitting |
| 53 | 11 KV Polymeric Pin Insulator with pin |
| 54 | 11 KV Cross Arm V-type |
| 55 | Dismantling & Carriage from work site to store with loading & unloading of 10 KVA T/F |
| 56 | Dismantling & Carriage from work site to store with loading & unloading of 16 KVA T/F |
| 57 | Dismantling & Carriage from work site to store with loading & unloading of 160 KVA T/F |
| 58 | Dismantling & Carriage from work site to store with loading & unloading of 100 KVA T/F |
| 59 | The Excavation of foundation pit in CC road/ mix soil/ normal soil/ soft & hard rack by using heavy duty compressor and its back filling and leveling etc. The size of the pit will be 600x600x1800 mm for each pole and having a depth of 1/6 of the full length of the support. |
| 60 | Erection of PCC pole 8.5 Mtr. including fitting of all reqired accessories of LT/HT line as per RESSPO schedule. |
| 61 | Grouting of each pole (In ratio of 1:4:8 in Cement, sand and Brick Ballast) in size 450mmx450mmx1800 mm as per RESSPO schedule Complete in all respects. |
| 62 | Grouting of stay rod 1800x16 mm & Fixing, Tighting & nozzling of stay wire 5 kg with the pole of required tension with clamps, bolt & nut. |
| 63 | Excavation of earth and driving of M.S. earthing rod of size 20x2500 mm in earth and jointing through G.I wire of 6 SWG between support and earth electrode by providing proper size of bolts and nuts etc. as per RESSPO schedule Complete in all respects. |
| 64 | Making of Chair of 2x2x1.5 or as per site requirement & RESSPO norms.(i) MS channel size 100x50x2240 mm. - 10 Nos.(ii) MS Angle size 65x65x6 mm. - 2 Set.(iii) Holding clamp with nut & bolt. - 12 Nos.(iv) Earthing complete. - 6 Nos.(v) Danger board - 4 Nos.(vi) Sundry items. - LS |
| 65 | Construction of new distribution T/F Plinth. The size of plinth shall be 2 Mtrs. long, 2 Mtrs. wide and height 1.5 Mtrs. from ground level OR AS PER WORK SITE REQUIREMENT with 15 CM thick top CC slab with 02 Nos. Channel. The above work includes Excavation of earth, laying of bring ballast pad for foundation brick work, CC and plastering and proper curing complete with all respects as per RESPO schedule. (providing material for Plinth : Cement - 14 Bag; Fine Sand - 3 Cu.mtr; Coarse sand - 1.2 Cu.mtr; Brick Ballast - 0.45 Cu.mtr; 1st Class Bricks - 1300 Nos.; Stone Ballast - 0.4 Cu.mtr; MS channel 125x65mm - 48 Kg.; MS Twisted bar of size 20mm - 40 Kg.) |
| 66 | Laying of LT PVC / XLPE Cable Al. 1x400 (1880 Mtrs.) / 3.5x150 Sq.mm. (20 Mtrs.) including fixing of lug & all accessories as per RESSPO schedule Complete in all respects. |
| 67 | Laying, Lifting and final Binding, Sagging of ACSR Rabbit Conductor including fixing of all accessories as per RESSPO schedule Complete in all respects. |
| 68 | Laying, Lifting and final Binding, Sagging of ACSR Dog Conductor including fixing of all accessories as per RESSPO schedule Complete in all respects. |
| 69 | Laying, Lifting and final Binding, Sagging of Cable LT ABC size 3Cx120+1x95+1x16 Sq.mm. including fixing of all accessories as per RESSPO schedule Complete in all respects. |
| 70 | Laying, Lifting and final Binding, Sagging of Cable LT ABC size 3Cx95+1x70+1x16 Sq.mm. including fixing of all accessories as per RESSPO schedule Complete in all respects. |
| 71 | Mounting, installation of T/F (250 KVA) on Plinth / Chair, alongwith double earthing of the same, complete in all respect as per RESSPO schedule. |
| 72 | Mounting, installation of T/F (63 KVA) on Pole, alongwith double earthing of the same, complete in all respect as per RESSPO schedule. |
| 73 | WORK OF PROVIDING AND FIXING OF 47 NOS. NEW WIREMESH FENCING OF 11/0.4 KV L.T. SUB-STATION INSTALLED AT DIFFERENT PLACES AS PER FOLLOWING (All Material provided by contractor for above work.) :- |
| 74 | 1. Frames of size 4x5x2 Meter for each fencing of LT Sub-stations. (All Material provided by contractor for above work.) or as per site requirement.2. The fencing shall be fabricated out of MS angle iron of size 50x50x6 mm having 2 Nos. legs of 75 Cm. long in each frame duly welded and fixed with wire mesh of size 75mm 25mm, 10 SWG within the frame, pressed under MS flat of size 25x5 mm inside the angle iron on all four sides with the help of duly Welded along with cross bracing of 25x5 mm MS flat on every frame will be grouted in 1:2:4 cement mortar with cement, coarse sand 20 mm gauge stone ballast. 3. Every frame after Fabrication will be painted with one coat of red oxide and two coats of Green synthetic enamel paint of approved make after proper cleaning. 4. The above mentioned frame will be jointed with each other with 70 mm long MS flat of size 25x5mm by first class welding as per site.5. Fabrication and providing of wire mesh fencing frame for gate of size 4’x6’. Fabricated as per above specifications with proper locking arrangement. |
| 75 | Construction of boundry / toe wall in bottom of fencing in brick work cement mortar 1:6 (1 cement : 6 coarse sand) for link in the size of 0.22mx0.60m (0.30m in earth, 0.30m above ground level) including plaster in cement mortar 1:4 and finishing with water proof cement paint. (Approx construction 18 Mtrs. boundry / toe wall for each fencing of LT Sub-stations.) (All Material provided by contractor for above work) or as per site requirement. |
| 76 | CHEMICAL EARTHING WORK (SUPPLY AND INSTALLATION) AS PER FOLLOWING:-Note :- The all material and labour shall be provided by the contractor with 24 month guarantee for resistance value less than one OHM. |
| 77 | Providing of earthing electrode :-Material Description : GI Electrode, Galvanization : 150 Micron (Min),IS Standard : IS 3043 / IEEE - 837, Short Time Current Rating kA (rms) For 1 Sec : 42 KA For 1 Sec, Dia of Electrode : 50mm, Length of Electrode : 3000mm, Weight of Electrode : 15 Kgm, Pipe Thickness : 4mm or As per IS : 1239 4mm, Inside Filling Material : Crystalline Conductive Mixture, Inner Strip : 3100 X 50 X 6 mm,Terminal Hole Dia : 16 MM. Technology : Metal Thermal Spray (Joints) Protection Earthing Resistance Value in Different Soil Conditions with ERIC Backfill Compound : Normal Soil - Upto 2 Ohms, Sand. Muran Soil - Upto 4 Ohms, Rock Soil - Upto 4 Ohms,Electrode Testing Cetificate : CPRI Testd. Surrounding Filling Material (ERIC):- Product : ERIC (Earth Resitance Improvement Compound), IS Standard : IS 3043/IEEE 837, Chemical Composition : Graphite, Activated Carbon, Bentonite, ETC., Resistivity Value : >0.2 Ohm Per Meter, Melting Temperature : 2500 Degree Centigrade,Specific Gravity : 2.6, PH Value of Chemical : 7-9, Solubility in water : 3.54, Colour : Light cream/Ash, Main Caution ; Sodium, Moisture Capacity at 105 Degree : 10%, Weight of Chemical used / Earthing Pit : 50 Kg, Water Absorbing Capacity : 20 Times, Environmental Effects : Eco Friendly. Test Certifictae : ROHS Certified, Thermal Stability : Testsed, Corrosion Resistance : Tested, Swell Test Certificate : Yes, Ph Value Test Certificate : Yes. Installation Parameter :- Need Hole Dia : 6\\"-8\\" Need Hole Depth : 3 Meter,Guarantee : 24 Month. |
| 78 | Providing and fixing of GI strip of size 50 mm x 6 mm suitable for T/F (Body & Neutral). |
| 79 | Providing and fixing of PVC Pit covers for above earthing electrode terminals. |
| 80 | Geo-tagging of complete work as per PVVNL order No. 2259 Dated 21.08.2025 (Letter attached with condition). Please Enable Macros to View BoQ information |