| 1 | Earth work in filling or embankment in ordinary soil to be in 20 cm layers, including ,watering ,Dressing ,compacting ,ramming the soil to achive 95% proctor density ,and dressing the surface to be required levels and slope and also including 1.50m lift and 30 m lead . The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30m distance as directed by the Engineer-in-charge. (Excluding Royalty) Analysis rate |
| 2 | Providing and layingConcrete with 4cm gauge brick ballast, fine sand of 1.25 fineness modulous and cement in prportion of 1:6:12 in foundation in under floor , including supply of all material labour and T&P etc rfequired of proper completetion of the work . |
| 3 | First class B/w in 1:4 Cement C'sand mortor in F/P including supply of all meterial labour T&P etc required for proper completion of work. |
| 4 | 12 mm thick plaster in 1:5 cement & c'sand mortor over brick work minimum thickness not less then 10 mm including all supply of meterial , Labour T&P etc required for proper completetion of the work. |
| 5 | Providing laying C.C with 2cm gauge approved stone ballast, approved coarse sand and cement in praportion of 1:2:4 including supply of all materials, labour and T&P etc required for proper completetion of the work. |
| 6 | RCC 1:1.50:3 with cement c'sand stone grit of 20 mm gauge in Slabs excluding supply of reinforcement with its bending but including its binding & fixing with supply of all meterial labour T&P etc. required for proper completion of the work. |
| 7 | Mild steel or Iron for plain work such as reinforced concrete brought to proper shape as necessary including its bending with supply of steel with overlaps & wastage also required for proper completion of the work as directed by E/I. |
| 8 | Construction of Granular sub (G.S.B.) by providing, laying, spreding and compacting speciffied graded crushed stone in sub base coarse including premixing the materials at O.M.C. in mechanical mixer (Plug Mill) including carriage of mixed msterials, laying in uniform layers with power roller to achieve the desired density including all materials, labour, machinery, lighting gaurding, barricading and maintance of diversion complete of as per MoRT & HT technical specification clause No. 404B (G3) |
| 9 | P/L of 125 micron Plastic Sheet |
| 10 | Cement concrete with 2 cm. gauge approved stone, ballast, approved coarse sand and cement in the proportion of 3:1.50:1 including supply of all materials, labour and T&P etc. required for proper completion of the work |
| 11 | Supplying and Fixing of 19mm thick Black mirror inaugration stone of size 900X600mm . Including base of 230X900mm brick base with foundation and 230mm x230 brick work around the stone, back base 115mm thick brick work,plastering and painting all copmlete as per direction of E/I. Please Enable Macros to View BoQ information |